Sei Societa Esplosivi Industriali Spa v. L-3 Fuzing & Ordnance Systems, Inc.

843 F. Supp. 2d 509, 2012 U.S. Dist. LEXIS 116566, 2012 WL 523526
CourtDistrict Court, D. Delaware
DecidedFebruary 17, 2012
DocketCivil Action No. 11-149-RGA
StatusPublished
Cited by1 cases

This text of 843 F. Supp. 2d 509 (Sei Societa Esplosivi Industriali Spa v. L-3 Fuzing & Ordnance Systems, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sei Societa Esplosivi Industriali Spa v. L-3 Fuzing & Ordnance Systems, Inc., 843 F. Supp. 2d 509, 2012 U.S. Dist. LEXIS 116566, 2012 WL 523526 (D. Del. 2012).

Opinion

MEMORANDUM OPINION

ANDREWS, District Judge:

Presently before the Court is the “Renewed Petition to Confirm International Arbitration Award” (D.I. 28) filed by Petitioner SEI Societa Esplosivi Industriali SpA and a Memorandum of Law opposing that petition filed by Respondent L-3 Fuzing and Ordnance Systems, Inc. (D.I. 35). For the reasons discussed, the renewed petition is granted.

BACKGROUND

This lawsuit arises out of SEI’s and L-3’s collaboration, along with other defense contractors, in obtaining and satisfying a military procurement contract for fuzes for aircraft-delivered attack munitions. On July 5, 2000, the parties agreed to Purchase Order No. 453 (“Purchase Order”), by which L-3 was to produce certain electronic components of the fuzes and deliver them to SEI. The Purchase Order contained an arbitration clause extending to “[a]ny disputes or differences which may arise out of or in connection with” the Purchase Order. (D.I. 34-1 at 22).

L-3’s electronics presented a safety issue, namely that the fuzes could arm earlier than a pilot intended in certain circumstances, such that L-3 did not deliver product that conformed to the contract specifications. (D.I. 32 at 3-4; D.I. 33 at 3). Without the electronics, SEI was unable to fulfill the procurement contract and agreements it had with the other defense contractors. (D.I. 33 at 6).

On May 12, 2006, SEI terminated the Purchase Order with a letter (“Termination Letter”) that read, in part, as follows:

[L-3] has expressly refused to deliver the equipment referred to in SEI’s letter of April 13, 2006, free from defects and corresponding to the Purchase Or[511]*511der No. 00453. Moreover, [L-3] has not delivered such equipment within the deadline set by SEI. In doing so, [L-3] is breaching its obligations under the contract binding SEI and [L-3] and is in default. Therefore, SEI terminates the purchase order No. 00453 in accordance with the provisions of Article 23.1 [“Termination for Default”]....

(D.I. 34-2; D.I. 34-1 at 15).

On October 1, 2007, the parties executed a letter agreement (“Letter Agreement”) dated August 2, 2007, agreeing to arbitrate the dispute over the Purchase Order:

All contract related disputes of SEI and [L-3] arising from the termination of Purchase Order No. 453 dated 5 July 2000, directed by SEI letter dated May 12, 2006, shall be submitted to arbitration in accordance with the Rules of Arbitration of the International Chamber of Commerce.
The arbitration to be held in Geneva, Switzerland.
Three arbitrators to decide the case with one arbitrator selected by each party and the two arbitrators selecting the third arbitrator.
Swiss law shall govern the Arbitration. The Arbitration to be conducted in English Language.
Mrs. Sabine Simkhovitch-Dreyfus shall not be an arbitrator in this matter.

(D.I. 34-3 at 3-4).

SEI brought a request for arbitration against L-3 on March 19, 2008, before the ICC, and L-3 counterclaimed. The parties agreed to Terms of Reference (“Terms of Reference”) for the arbitration, agreeing to the scope of jurisdiction set forth in the 2007 Letter Agreement. (D.I. 34 at 7-8).

The arbitrator rendered a 109 page decision and entered a final award, dated October 25, 2010, to SEI totaling approximately $7 million, with interest accruing. (D.I. 30-33). The arbitrator summarized this as SEI prevailing on about 70% of its claims, and L-3, which had sought about $4,400,000 in lost profits and revenue (D.I. 31 at 5, failing on 100%) of its claims. (D.I. 33 at 20).

L-3 has not paid the award. On February 18, 2011, SEI filed a Petition to Confirm International Arbitration Award in this Court. (D.I. 1). SEI filed the Renewed Petition on July 25, 2011, seeking enforcement of the award plus interest. (D.I. 28). L-3 responded on August 1, 2011. (D.I. 35).

PARTIES’ CONTENTIONS

In opposing enforcement of the award, L-3 argues the arbitrator erred by finding a novation1 of the contract between the parties with regard to who was to bear the costs of certification. L-3 claims the novation nullified a contractual limitation of L-3’s overall liability. (D.I. 35 at 5). L-3 also argues the arbitrator erred by finding SEI terminated for L-3’s nonperformance, rather than nondelivery, and awarding damages for nonperformance that the Purchase Order did not contemplate. (D.I. 35 at 6). Third, L-3 argues the arbitrator erred in not applying the force majeure provision to relieve L-3 of liability. (D.I. 35 at 7). Fourth, L-3 argues that SEI’s alleged statements to French authorities, outside the arbitration, that L-3 was not at fault comprise prior admissions that should have nullified the award. (D.I. 35 at 17-18). L-3 concludes that these four errors constitute three defenses against confirmation of the award: a) manifest disregard [512]*512for the governing Swiss law, b) violations of public policy, and c) actions beyond the scope of arbitration.

SEI argues that the arbitrator did not err. SEI argues the novation addressed only the costs of qualification, not damages under the contract as a whole; that SEI terminated for nonperformance; and that the force majeure provisions did not excuse L-3’s nonperformance. (D.I. 28-1 at 8-11). SEI argues that manifest disregard for the law is not a defense to an international arbitration award; that even if the arbitrator did err, such error does not violate public policy; and that the award falls within the scope of arbitration as defined by the parties’ agreements. (D.I. 28-1 at 6-7; 12-18).

DISCUSSION

A. Legal Standard

Section 201 of Title 9 of the United States Code states that “[t]he Convention on the Recognition and Enforcement of Foreign Arbitral Awards of June 10, 1958 [hereinafter “the New York Convention,” or “Convention”], shall be enforced in United States Courts in accordance with this chapter.” Article I of the Convention states that it “shall apply to the recognition and enforcement of arbitral awards made in the territory of a State other than the State where the recognition and enforcement of such awards are sought, and arising out of differences between people, whether physical or legal.”

United States courts must confirm foreign arbitral awards falling under the Convention except in very limited circumstances. Section 207 of Title 9 of the United States Code states:

Within three years after an arbitral award falling under the Convention is made, any party to the arbitration may apply to any court having jurisdiction under this chapter for an order confirming the award as against any other party to the arbitration. The court shall confirm the award unless it finds one of the grounds for refusal or deferral of recognition or enforcement of the award specified in the said Convention.

The “grounds for refusal or deferral of recognition or enforcement of the award” allowable under Article V of the New York Convention are:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
843 F. Supp. 2d 509, 2012 U.S. Dist. LEXIS 116566, 2012 WL 523526, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sei-societa-esplosivi-industriali-spa-v-l-3-fuzing-ordnance-systems-ded-2012.