Sedor v. West Mifflin Area School District

713 A.2d 1222, 1998 Pa. Commw. LEXIS 553, 1998 WL 344301
CourtCommonwealth Court of Pennsylvania
DecidedJune 30, 1998
DocketNo. 897 C.D. 1998
StatusPublished
Cited by4 cases

This text of 713 A.2d 1222 (Sedor v. West Mifflin Area School District) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sedor v. West Mifflin Area School District, 713 A.2d 1222, 1998 Pa. Commw. LEXIS 553, 1998 WL 344301 (Pa. Ct. App. 1998).

Opinion

RODGERS, Senior Judge.

Erin D. Sedor (Sedor), a taxpayer, appeals from an order of the Court of Common Pleas of Allegheny County (trial court) that denied Sedor’s Motion for Special Relief and /or Preliminary Injunction. The trial court also refused to hold a hearing on the motion, concluding that the doctrine of laches barred Sedor’s claim. We reverse and remand.

The following recitation of facts was gleaned from the averments contained in Sedor’s Complaint in Equity and her Motion for Special Relief and/or Preliminary Injunction. On December 15,1997 the West Mifflin Area School District (School District) issued an advertisement for bid for electric work in connection with additions and renovations to the West Mifflin Area High School. Sealed bids were to be submitted to the School District containing two base bids, one to include a construction manager and the other without a construction manager. The School District had not decided whether to proceed with electrical work on a swimming pool and, therefore, required bids in the original bid form to include a base bid for the entire project including the swimming pool as well as an alternate bid that was an amount to be deducted from the base bid if the District decided not to proceed with the work on the swimming pool.

The School District then amended its advertisement for bid requiring that the responsive base bids not include any work for the swimming pool, changing its alternative to an add, meaning that work related to the swimming pool was to be added to the base bid in the event the School District decided to proceed with that work. A revised bid form was included in the addendum.

Vern’s Electric, Inc. (Vern’s Electric) was one of six bidders for the electrical work. On a proper form Vem’s Electric’s base bid with a construction manager was $2,545,517 [1224]*1224and its alternative relating to the swimming pool was $134,454. Vern’s Electric’s base bid for the work without a construction manager was also $2,545,517 and its alternative relating to the swimming pool was also $134,454. However, this bid without the construction manager was submitted on an improper form, so that instead of including the swimming pool work as an addition to the base bid that amount was deducted from the base bid.. Apparently, the School District decided that it would proceed without a construction manager and with the swimming pool work. This was the form of the project for which Vern’s Electric’s bid was submitted on the incorrect form.

Sedor alleged that after the bids were opened and the addition/deduetion error (wrong form) was discovered, the School District allowed Vern’s Electric to withdraw its bid. However, Vem’s Electric agreed to perform all electric work including the swimming pool work for the base bid minus the $134,454, resulting in Vem’s Electric’s agreement to perform the electrical work for $268,908 less than it had actually intended. Sedor also alleged that she believed that Vern’s Electric would not have been the lowest responsible bidder if the proper form had been used, i.e., the cost of the swimming pool work would have been added to the base bid and another bid would have been lower. Se-dor also contended that the discussion between the School District and Vern’s Electric following the opening of the bids was unlawful, was not the type of ■ irregularity that could be waived by the School District and did not overcome the requirement that bids be responsive to the specifications. As a result of the awarding of the bid to Vem’s Electric on February 23, 1998, Sedor contended that she and other taxpayers suffered irreparable harm in that the purpose of competitive bidding exists not solely to secure work or supplies at the lowest possible price, but to guard against favoritism, fraud or corruption.1 Sedor requested that the court issue an injunction preventing the awarding of the contract to Vern’s Electric and declaring that any contract signed by the parties be considered void.

Sedor’s Complaint in Equity and Motion for Special Relief and/or Preliminary Injunction were both filed on March 23, 1998, a month after the bid was awarded to Vem’s Electric. When the parties appeared before the trial court, the attorney representing Se-dor indicated to the court that he believed no testimony was required because the parties essentially agreed to the facts. Sedor’s attorney then presented the arguments outlined above, further contending that Vern’s Electric’s bid if submitted correctly would not have been the lowest responsible bid. After hearing arguments on Sedor’s motion, the trial court denied the request for preliminary injunction and refused to grant a hearing date. The trial court explained that its refusal to take evidence on the day the motion was presented or to schedule a hearing date for the taking of evidence was controlled by the doctrine of laches.2

The trial court explained that although no pre-set limitations period existed when applying the laches doctrine, a court must examine whether there is and to what extent there is harm to the opposing party. Based on the following “undisputed” facts, the trial court held that laches barred Sedor’s claim:

Plaintiff knew on or before February 23, 1998 that Vern’s Electric had in fact been awarded the bid. By the time Plaintiff came into Court on March 25, 1998, a month had passed. At oral argument on Plaintiff’s demand for an immediate injunction (which, under Rule 1531, in appropriate cases, can be granted pending a hearing within five days), Defendants pointed out that the contract had been signed, materials bought and other actions taken by the successful bidder, Vern’s Electric, Inc., to perform the contract, and the work, on a school, was scheduled to begin on April 1, 1998, seven days later. (Plain[1225]*1225tiff did not dispute this or even suggest that it was unlikely to be true.) Plaintiffs delay in attacking the winning bid by filing the instant action was explained only by the fact that it took the unsuccessful bidder several weeks to find a taxpayer, Plaintiff, to complain of the bidding process.

(Trial court’s opinion, p. 5). Thus, having decided that the doctrine of laches applied, the trial court concluded that “no evidentiary hearing was needed to determine whether the other prerequisites for the grant of a preliminary injunction had been met.” Id.

On appeal to this Court,3 Sedor raises the following issues: 1) whether the award of the contract violated the principles of competitive bidding and caused irreparable harm to the taxpayers, and 2) whether the trial court erred in refusing to schedule á hearing on the motion for preliminary injunction.

A portion of Sedor’s argument rests on her contention that no facts of record support a finding of laches. “For laches to apply, there must be a lack of due diligence in pursuing a cause of action and resulting prejudice to the other party.” In re General Election for District Justice, 543 Pa. 216, 231, 670 A.2d 629, 636 (1996). The party asserting laches, here the School District and Vern’s Electric, must establish that they are prejudiced by the period of inordinate delay by the other party, here Sedor. United Brotherhood of Carpenters and Joiners of America, Local 261 v. Pennsylvania Human Relations Commission,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fenton v. Balick
821 F. Supp. 2d 755 (E.D. Pennsylvania, 2011)
Setzer v. Mercer County
55 Pa. D. & C.4th 57 (Mercer County Court of Common Pleas, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
713 A.2d 1222, 1998 Pa. Commw. LEXIS 553, 1998 WL 344301, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sedor-v-west-mifflin-area-school-district-pacommwct-1998.