Wheels Mechanical Contracting & Supplier, Inc. v. West Jefferson Hills School District

156 A.3d 356
CourtCommonwealth Court of Pennsylvania
DecidedFebruary 28, 2017
DocketWheels Mechanical Contracting and Supplier, Inc. v. The West Jefferson Hills SD - 1803, 1827 and 1828 C.D. 2016
StatusPublished
Cited by4 cases

This text of 156 A.3d 356 (Wheels Mechanical Contracting & Supplier, Inc. v. West Jefferson Hills School District) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wheels Mechanical Contracting & Supplier, Inc. v. West Jefferson Hills School District, 156 A.3d 356 (Pa. Ct. App. 2017).

Opinion

OPINION BY

JUDGE WOJCIK

In these consolidated appeals, the West Jefferson Hills School District (District), Nello Construction (Nello) and Laborers’ District Council of Western Pennsylvania (Laborers) (collectively, Appellants), appeal from an order of the Court of Common Pleas of Allegheny County (trial court), which granted a preliminary injunction in favor of Wheels Mechanical Contracting and Supplier, Inc. (Wheels) and halted construction of a new high school. 1 Significantly, the trial court determined that the installation of storm sewers, sanitary sewers and water service lines constituted “plumbing branch work,” as opposed to “site work,” that should have been included in the plumbing prime contract and that District violated Section 751 of the Public School Code of 1949 (School Code) 2 and Section 1 of the act commonly referred to as the Separations Act 3 by including this work in the general construction prime contract. Appellants argue that the trial court erred or abused its discretion by granting the preliminary injunction where the relief sought by Wheels was barred by the doctrine of laches; Wheels did not meet the requisite elements for .a preliminary injunction; and, the trial court lacked subject matter jurisdiction. In addition, Nello claims the trial court erred or abused its discretion by precluding it from presenting evidence on its cross-claim. Upon determining Wheels’ action is barred by the doctrine of laches, we reverse the trial court’s preliminary injunction order and remand for further proceedings.

I. Background

The Project is a $100-million construction project to build the Thomas Jefferson High School (Project) in the Borough of West Jefferson Hills. The Project’s location is a reclaimed strip mine, consisting of 160 acres.

In December 2015, the District solicited bids for electrical, plumbing, heating and ventilating, and general construction. Of relevance here, the specifications assigned all sanitary line, storm line, and water line installations inside the building and up to five feet outside of the building to the plumbing prime contractor. All site sanitary, site storm, and site waterline installation more than five feet from the building was assigned to the general prime contractor as “site utility” work because of the significant trenching and backfilling required. The District received bids and awarded contracts in January 2016. The District awarded the plumbing prime contract to Wheels and the general construction prime contract to Nello.

On June 1, 2016, Wheels filed a complaint in equity as well as a motion for a preliminary injunction against the District and Nello to stop certain work on the Project. Wheels asserted the District violated Section 751 of the School Code and *359 Section 1 of the Separations Act by failing to include in the plumbing prime contract all “plumbing branch work,” namely, work in connection with the installation of sanitary sewer, storm sewer and water service lines (also referred to as the “disputed work”). Laborers intervened in support of the District and Nello, and Plumbers Union intervened in support of Wheels.

On October 26, 2016, after a three-day evidentiary hearing, the trial court entered an order granting injunctive relief. Although the term plumbing is not defined by the Separations Act or School Code, or by any case law interpreting those statutes, the trial court found that the installation of sanitary sewers, storm sewers and water service lines outside of a public building is “plumbing branch work” that must be included in the contract awarded to the plumbing prime contractor. In so finding, the trial court applied the definitions of plumbing work contained in Section 201 of the International Plumbing Code, 2009 (IPC) edition. 4 Trial Court Preliminary Injunction Order, 10/26/16, at 3, ¶ 3. The trial court further observed that the Allegheny County Plumbing Code (ACPC), which incorporated and adopted the IPC 2009, provides:

No person, other than a licensed master plumber, a licensed journeyman plumber in the employ of a licensed master plumber, a registered plumbing apprentice in the employ of a licensed master plumber, or a bonafide owner presently occupying an existing single family building shall install, alter, or make connections with any sewer, water, drain, or any pipe connected therewith; or alter the location of any existing plumbing fixtures, water distribution piping system or sewer drainage system.

Id. (quoting Section 106.5.8 of the ACPC). 5 Thus, the trial court determined that the bid specifications and contracts awarded clearly violated Section 751 of the School Code, and Section 1 of the Separations Act because the plumbing prime contract did not include all plumbing work. On this basis, the trial court found Wheels established a clear right to relief.

In addition, the trial court found that Wheels satisfied the other criteria necessary for a preliminary injunction. Specifically, the trial court found that the violation of the School Code and Separations Act constituted irreparable harm per se, and that greater harm will result from denying the relief because the harm of the violation will continue unabated. Granting the relief will restore the status quo by reversing the violations of the School Code and the Separations Act and requiring future compliance with the law. The issuance of a stay will not harm public interest, which has a profound interest in having its elected bodies adhere to the law.

Further, the trial court rejected Appellants’ laches argument. The trial court explained Wheels was under no duty to recognize the illegality of the bid and, at the time Wheels filed suit, “no actual work had commenced on the exterior plumbing work.” Trial Court Preliminary Injunction Order at 5-6, ¶ 10.

Thus, the trial court granted Wheels’ motion for a preliminary injunction and ordered:

(a) The School District is enjoined from including in the scope of the prime general contractor’s work, any plumbing *360 work, including the installation of storm sewers, sanitary sewers and water service lines, and shall include such work in the scope of work of the prime plumbing contractor, in this matter, Wheels Mechanical;
(b) The School District is enjoined from permitting any continued work on the exterior plumbing, including the sanitary sewers, storm sewers and water lines by the general construction prime contractor, or its subcontractor, Macson, as of the date of this Order;

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
156 A.3d 356, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wheels-mechanical-contracting-supplier-inc-v-west-jefferson-hills-pacommwct-2017.