Secretary of Labor v. Twentymile Coal Co.

411 F.3d 256, 366 U.S. App. D.C. 280, 2005 U.S. App. LEXIS 10797, 2005 WL 1364691
CourtCourt of Appeals for the D.C. Circuit
DecidedJune 10, 2005
Docket04-1292, 04-1312
StatusPublished
Cited by11 cases

This text of 411 F.3d 256 (Secretary of Labor v. Twentymile Coal Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Secretary of Labor v. Twentymile Coal Co., 411 F.3d 256, 366 U.S. App. D.C. 280, 2005 U.S. App. LEXIS 10797, 2005 WL 1364691 (D.C. Cir. 2005).

Opinion

Opinion for the Court filed by Circuit Judge SENTELLE.

SENTELLE, Circuit Judge.

This case comes before us on cross-petitions for review of an order of the Federal Mine Safety and Health Review Commission wherein the Commission ruled that Twentymile Coal Co. (“Twentymile”) violated the mandatory training standard set forth at 30 C.F.R. § 48.7(c) (2002), but that the proposed penalty assessment was not issued within a reasonable time. Sec’y of Labor v. Twentymile Coal Co., 26 F.M.S.H.R.C. 666 (Aug. 12, 2004) (“Commission Order ”). Because we agree with the Commission that Twentym-ile did violate the mandatory training standard, we deny Twentymile’s petition for review. But because we disagree with the Commission and hold that the proposed penalty assessment was issued within a reasonable time, we grant the Secretary of Labor’s petition for review, vacating the order of the Commission and remanding the matter to the Commission for further proceedings not inconsistent with this opinion.

*258 I. Background

A. The Accident & Investigation

Twentymile operates the Foidel Creek Mine (“the mine”), a large underground coal mine in Colorado. Among its three hundred miners was Kyle Webb, who had worked on the crew of Matthew Winey for more than four years. 26 F.M.S.H.R.C. at 668. Winey, in turn, worked under Kevin Olson, acting shift supervisor. Id.

The geological conditions at the mine required that rock sometimes be extracted with the coal. The rock-coal mix was transported away from pure coal extract to prevent accidental commingling. A chute was designed to facilitate the process. The 45-to-50-foot chute, five feet square, was placed in a vertical shaft twelve feet in diameter. The rock-coal mix was dumped into the chute from a conveyer belt, where it fell from one level of the mine to the level below. Id at 667. The chunks falling through the chute ranged in diameter from one to eight inches; baffles slowed the fall of the chunks and prevented damage to the box or conveyer belt at the lower level. Miners could maintain the chute by climbing the ladder, alongside the chute and opening one of four doors that accessed the inside of the chute. Id.

This particular chute was a new addition to the mine at the time of the accident, and differed from pre-existing chutes in that it was “slightly slanted ... instead of [ ] completely] vertical,” ALJ Tr. 171 (May 29, 2002), but the clearing of chutes in general was nothing new to Twentymile. Other chutes clogged. According to one mine employee, the clogging of chutes was a “recurring problem,” happening every four to six months. 26 F.M.S.H.R.C. at 677.

On June 6, 2000, after only ten days of operation, the vertical chute in the mine clogged. Id. at 667. Olson assigned Wi-ney to unplug the chute; at some point after this team began working to clear the chute, Webb climbed the ladder and attempted to unclog it. Id. at 668. Neither Winey nor beltman Rick Fadely instructed Webb to climb the ladder, and Winey did not ask Webb what he was doing. Id.

The material in the chute began to move; Webb fell from the ladder and landed on a platform, and the chute’s rock-coal mixture fell upon him. Id. Webb was airlifted to a local hospital where he was treated for “serious, but non-fatal, head injuries.” Id.

R. Lincoln Derick, the mine’s safety manager, was apprised of the incident: he contacted MSHA Inspector Philip Gibson. Both went to the mine with various law-enforcement and mine officials. Id. Following a week’s investigation, Gibson issued an order, pursuant to Mine Act section 104(g)(1), 30 U.S.C. § 814(g)(1), charging Twentymile with a violation of 30 C.F.R. § 48.7(c), which provides that “[m]iners assigned a new task ... shall be instructed in the safety and health aspects and safe work procedures of performing such task.” Six months later, on January 4, 2001, MSHA issued an accident investigation report. After another seven months had passed, on July 31, 2001, the report and an accompanying assessment report were sent to the U.S. Department of Labor’s Assessment Office. On November 9, 2001, MSHA proposed a specific penalty assessment and the case proceeded to trial before an administrative law judge (“ALJ”). 26 F.M.S.H.R.C. at 669-70.

B. Proceedings Before the ALJ

Twentymile filed a notice of contest; on August 1, 2000, the contest was stayed pending issuance of the penalty assessment. Once MSHA issued its proposed penalty assessment in November 2001, the *259 stay was lifted. See Commission Order, 26 F.M.S.H.R.C. at 670.

The ALJ held that the clearing of the rock chute constituted a “new task” under 30 C.F.R. § 48.7(c) such that the mine was required to train the workers for the matter prior to engaging the chute. Twentymile Coal Co. v. Secretary of Labor, 25 F.M.S.H.R.C. 373 (July 14, 2003) (“ALJ Order ”). The clearing of the chute was a “task” under section 48.7(c) because it fit the definition provided at section 48.2(f): A “task” is “a work assignment that includes duties of a job that occur on a regular basis and which requires physical abilities and job knowledge.” 30 C.F.R. § 48.2(f). The ALJ held that the clearing of the chute was a matter that would occur on a “regular” basis even though it had not occurred previously at that ten-day-old chute and was not subject to a fixed schedule. See Commission Order, 26 F.M.S.H.R.C. at 670; ALJ Order, 25 F.M.S.H.R.C. at 383-84.

The violation was deemed “significant and substantial” based on the ALJ finding that there was a reasonable likelihood that the hazard would result in an injury or severe illness. ALJ Order, 25 F.M.S.H.R.C. at 385-86. The ALJ ordered a penalty despite the seventeen-month span of time between the Inspector’s June 16, 2000 order and the November 9, 2001 MSHA penalty assessment. Id. at 386-88. He held that the reasons for delay — to wit, a shift in personnel in MSHA offices and “a failure by the new employee to understand his duties” — were “understandable” and that Twentymile suffered no prejudice from the delay. Id. at 387-88. The ALJ reduced the proposed $6,000 penalty to $1,500. Id. at 389.

C. Proceedings Before the Commission

Twentymile appealed the ALJ’s decision to the Commission. Before the Commission, Twentymile again argued, inter alia,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tilden Mining Company, Inc. v. Secretary of Labor
832 F.3d 317 (D.C. Circuit, 2016)
United States v. Akinyoyenu
199 F. Supp. 3d 106 (District of Columbia, 2016)
Ambrose v. United States
106 Fed. Cl. 152 (Federal Claims, 2012)
American Nurses Association v. Leavitt
District of Columbia, 2009
AMERICAN NURSES ASS'N v. Leavitt
593 F. Supp. 2d 126 (District of Columbia, 2009)
Biovail Corp. v. U.S. Food & Drug Administration
519 F. Supp. 2d 39 (District of Columbia, 2007)
International Center for Technology Assessment v. Johanns
473 F. Supp. 2d 9 (District of Columbia, 2007)
Secretary of Labor v. Twentymile Coal Co.
456 F.3d 151 (D.C. Circuit, 2006)
Mistick PBT v. Chao, Elaine
440 F.3d 503 (D.C. Circuit, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
411 F.3d 256, 366 U.S. App. D.C. 280, 2005 U.S. App. LEXIS 10797, 2005 WL 1364691, Counsel Stack Legal Research, https://law.counselstack.com/opinion/secretary-of-labor-v-twentymile-coal-co-cadc-2005.