Second Church of Christ, Scientist v. Spencer

88 So. 2d 810, 230 La. 432, 1956 La. LEXIS 1431
CourtSupreme Court of Louisiana
DecidedJune 11, 1956
Docket42321
StatusPublished
Cited by17 cases

This text of 88 So. 2d 810 (Second Church of Christ, Scientist v. Spencer) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Second Church of Christ, Scientist v. Spencer, 88 So. 2d 810, 230 La. 432, 1956 La. LEXIS 1431 (La. 1956).

Opinion

*435 SIMON, Justice.

The Second Church of Christ, Scientist, a nonprofit religious corporation organized under the laws of Louisiana and domiciled in the city of New Orleans, instituted this suit against defendant Charles B. Spencer, individually, and against defendant Olympia Roofing Company, Inc., .a corporation organized under the laws of Louisiana and domiciled in the city of New Orleans, in solido, for damages in the sum of $5,837, the cost of repairing plaintiff’s church organ, allegedly damaged as the result of the failure of defendants to protect it against rain during the course of extensive repairs made by them on the church premises under their respective contracts. -

Defendant Spencer denied liability and alleged that defendant Olympia was solely liable for having negligently failed to take ■proper precautions to prevent rain from entering the interior of the church building while said Olympia was reconstructing the roof. Defendant Spencer also filed a third party complaint praying that in the event an adverse judgment should be rendered against him that defendant Olympia be condemned to pay to him a like amount, together with interest and costs.

Upon its exception of no right or cause of action being overruled, Olympia answered and denied liability. Exceptions of no right or cause of action, prescription, and an answer denying liability were filed by defendant Olympia to the third-party complaint.

After trial on the merits the district court rendered judgment in favor of plaintiff and against defendant Spencer in the sum of $5,837, together with interest from judicial demand until paid, reserving to the plaintiff any claim it might have against the surety on the building contract between plaintiff and defendant Spencer. Defendant Olympia was absolved from all liability.

Appeals have been perfected by plaintiff and by Spencer, the former contending that it is entitled to a judgment in solido against both defendants; the latter contending that the damages complained of were caused solely through the negligence of the employees of Olympia and that therefore the-judgment of the lower court should be reversed so as to cast Olympia alone.

There is no dispute as to the nature and extent of the damage to the organ, its. cause or the cost of the repairs, the sole-issue being whether either or both defendants are responsible therefor.

Hence we see that the issue involves no principle of law but one purely of fact. Under such circumstances, an analytical! disposition of the facts and the conclusion reached by the trial judge should not be disturbed in the absence of manifest error. Holmes v. Triggs, 214 La. 1083, 39 So.2d 739; Nalty v. Nalty, 222 La. 911, 64 So.2d 216; Rosenthal v. Gauthier, 224 La. 341, 69 So.2d 367; Olivier v. Abunza, 226 La. 456, 76 So.2d 528; McMahon v. Manufacturers Casualty Insurance Co., 227 La. 777, *437 80 So.2d 405; Sunseri v. Westbank Motors, 228 La. 370, 82 So.2d 43.

The controlling fact's disclosed by the record are as follows:

On May 25, 1953, plaintiff and defendant 'Spencer entered into a general contract for the remodeling and renovation of plaintiff’s ■church edifice. In addition to the terms of the agreement, its general conditions, •drawings and specifications, the contract further stipulated that,

“The contractor shall continuously maintain adequate protection of all his work from damage, and shall protect the owner’s property from injury ■ or loss arising in connection with this • contract.”

•In accordance with the plans and specifi■cations for the installation of the roof, .Spencer subcontracted with Olympia, the latter agreeing to be bound to Spencer by all of the terms of the agreement between him and the owner and to assume toward .Spencer all the contractual obligations flowing in favor of the plaintiff.

Pursuant to the general contract Spencer ■commenced work on the church edifice on June 9, 1953. He removed the skylight forming a part of the roof, an operation requiring about three days. As a result thereof, this area was left open and unprotected for approximately thirty hours before the joists were installed across the ■open space and wooden sheathing laid in preparation for the installation of the roof by Olympia.

In preparing. the skylight area for' the roofers, Spencer left an opening approximately 10' x 10' in about the center of the roof to afford a means through which roofing materials and equipment could be raised and lowered. Two openings were also cut for use by the airconditioning contractor. The removal of the skylight and the installation of the joists and sheathing was completed, though not watertight, during the week prior to the entrance on the premises by Olympia.

On August 3, Olympia delivered its roofing materials to the job. It began laying the roof on August 4 and allegedly completed a watertight roof on August 11, 1953.

On August 25 the damaged condition of the organ and the organ chamber was discovered. The center section of the ceiling of the chamber was soaking wet and had fallen. The back wall of the building, which is the back wall of the organ chamber, was wet, and water dropped therefrom and from the area over the entrance to the doorway. There was considerable water on the floor. There was an accumulation of water that damaged and affected the organ proper, necessitating the extensive repairs made.

Testimony of the witnesses as well as local climatological data issued by the U. S. Department of Commerce, Weather Bureau, established that during the period from August 4 to August 11 >there was no rainfall. On August 3, 1953, there was rainfall of .04" at 4 p. m., and .01" at 7 p. m. *439 On August 12, 1953, there was a trace of rainfall at 10 a. m.; 1.98", or almost 2", at 1 p. m., and .04" at 2 p. m.

Hence we see that the issue is whether a waterproof roof was completed immediately prior to the torrential rain on August 12, 1953.

Olympia contends that the so-called felt or roofing paper had been laid, the flashing incidental to the laying of the felt was completed, and the roof made waterproof during the period from August 4 to August 11, leaving to be done only the final spread of tar and gravel thereon. Spencer contends, however, that the roofing was not complete and waterproof on that date, basing his contention on the fact that Olympia’s employees worked on the premises subsequent to that date.

It is undisputed that the roof in question had a slope of about two feet, being two feet higher in the front than in the back of the building and that the roofing operation was started on the higher part of the roof and gradually descended to the lower part where there was a cricket to divert any water running down on the roof to side drain pipes.

That part of the church organ which was damaged by rainwater was located in a small room at the rear of the church and under that area where the roof cricket was situated.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Thomas v. Highlands Ins. Co.
617 So. 2d 877 (Supreme Court of Louisiana, 1993)
Stansbury v. Hover
366 So. 2d 918 (Louisiana Court of Appeal, 1978)
Washington v. Degelos
312 So. 2d 918 (Louisiana Court of Appeal, 1975)
Green v. Taca International Airlines
304 So. 2d 357 (Supreme Court of Louisiana, 1974)
Jayco Sales and Service, Inc. v. Smith
303 So. 2d 554 (Louisiana Court of Appeal, 1974)
McCroskey v. Branch
208 So. 2d 8 (Louisiana Court of Appeal, 1968)
Dick v. Phillips
205 So. 2d 766 (Louisiana Court of Appeal, 1967)
Hebert v. Blankenship
187 So. 2d 798 (Louisiana Court of Appeal, 1966)
Harness v. Toye Brothers Yellow Cab Company
170 So. 2d 737 (Louisiana Court of Appeal, 1965)
Emmons v. Bertucci
163 So. 2d 814 (Louisiana Court of Appeal, 1964)
Carter v. Harris
144 So. 2d 472 (Louisiana Court of Appeal, 1962)
Todd Shipyards Corp. v. Commercial Iron & Metal Co.
142 So. 2d 51 (Louisiana Court of Appeal, 1962)
Vicknair v. Rapides Parish School Board
128 So. 2d 821 (Louisiana Court of Appeal, 1961)
Martin v. Massachusetts Bonding & Insurance
121 So. 2d 527 (Louisiana Court of Appeal, 1960)
Sill v. Clanton Electric Co.
109 So. 2d 64 (Supreme Court of Louisiana, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
88 So. 2d 810, 230 La. 432, 1956 La. LEXIS 1431, Counsel Stack Legal Research, https://law.counselstack.com/opinion/second-church-of-christ-scientist-v-spencer-la-1956.