Vicknair v. Rapides Parish School Board

128 So. 2d 821, 1961 La. App. LEXIS 2025
CourtLouisiana Court of Appeal
DecidedApril 17, 1961
DocketNo. 66
StatusPublished
Cited by7 cases

This text of 128 So. 2d 821 (Vicknair v. Rapides Parish School Board) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vicknair v. Rapides Parish School Board, 128 So. 2d 821, 1961 La. App. LEXIS 2025 (La. Ct. App. 1961).

Opinion

HOOD, Judge.

Plaintiff instituted this suit against the Rapides Parish School Board for the sum of $2,497.50, representing the balance alleged to be due under a contract entered into between plaintiff and defendant. Defendant answered admitting that it owes plaintiff $404.50 under the contract, which amount was tendered and deposited in the registry of the court, but denying that it is indebted to plaintiff for any additional sums. Defendant specially pleads compensation and setoff as to the balance of the sum originally claimed by plaintiff, and, in the alter[822]*822native, it reconvenes for judgment against plaintiff for that same amount.

After trial of the case on its merits, the trial court rendered judgment in favor of plaintiff for the amount which had been deposited in the registry of the court. Judgment further was rendered in favor of plaintiff for the additional sum of $2,-093, but under defendant’s reconventional demand judgment for a like amount was rendered in favor of defendant and against plaintiff, plaintiff being condemned to pay all costs of the suit. From this judgment plaintiff has appealed.

The trial judge has accurately stated the facts and in our opinion has correctly disposed of the issues presented here in the following well-written opinion, which we adopt as our own:

“On June 25, 1958 the plaintiff entered into a written contract with the defendant for the removal of the old roof and instalation of a new roof on the Pineville Grammar School, all in accordance with written specifications which are annexed to the contract. In removing the old roof from the building three circular ventilators, each 24" in diameter, were removed. To prevent rain from going through these openings down into the interior of the building and causing damage while the new roof was under construction, the plaintiff testified that he and his crew placed two layers of felt over these openings and stretched it and nailed it down. On July 23, 1958 while the work was still in progress a heavy rain came up and water went down through these ventilator holes into the building causing considerable damage. Mr. James Westgard and Mr. J. C. Ward, both employees of the plaintiff, testified that they were on the roof working and that they rolled out, stretched and nailed down the two layers of felt over these openings and when the rain came up they did what they could to protect against water entering the building. These witnesses, as well as other roofing contractors who testified on behalf of the plaintiff, stated this was the standard procedure for protecting against rain while a roof was in the process of construction. All were of the opinion that the simple falling of the rain itself would not break two layers of felt and that what must have happened in this case was that the felt sagged and water accumulated over the openings and finally broke through the felt and went on down into the building. It is admitted by the plaintiff that no supports were placed over the openings and underneath the felt to support it. The plaintiff himself testified that although this felt would have protected against a light rain, it rained so hard on this occasion that the weight of the water accumulating in the sag over the holes tore the felt open and let the water run down inside the building.

“The damage was discovered immediately and the plaintiff called his insurance agent who sent out an adjustor, Mr. Jack Soden, to inspect the damages. On the same day the plaintiff also notified Mr. David C. Bates, the School Board member who is responsible for this particular building.

“The insurance adjustor, Mr. Soden, apparently led the plaintiff to believe that his policy covered the loss. In due course the plaintiff, Mr. Soden, Mr. David C. Bates, and Mr. Walter E. Price, the architect on the job, all agreed that they would obtain three bids on the repair work necessitated by the water damage, the work to be done by the lowest bidder. It was also agreed by all parties concerned, including the plaintiff, that the School Board would withhold from the amount which might be due to plaintiff under his roofing contract, the sum which was necessary to pay for the water damage, as represented by the lowest bid. The obvious purpose of this arrangement was to protect the School Board in the event plaintiff’s insurance carrier, for any reason, refused to pay the claim.

“The low bid for the repair work was submitted by Mr. T. C. Price, who was paid the sum of $2,093 by the School Board. Then after the plaintiff completed the new roof, his work was accepted and on authorization from the architect the School Board [823]*823paid to plaintiff the sum of $1,547.50. Plaintiff testified that he accepted this amount and that he would receive the rest of his contract price after his liability insurance carrier paid the claim.

“The plaintiff's insurance carrier refused to pay the claim for the water damage and now plaintiff has instituted suit against the School Board for the balance of the contract price. The defendant, School Board, filed an answer in which they plead compensation on the theory that the School Board has an equally liquidated, due and demandable claim against the plaintiff for damages due to breach of contract. In the alternative the defendant pleads a recon-ventional demand for these same damages.

“In its answer, the defendant alleges that the original contract for the roofing was $4,045 of which $1,547.50 has already been paid to the plaintiff and the sum of $2,093 was paid to Mr. Price for the water damage, leaving a balance of $404.50 * * * representing 10% of the contract price which was withheld pending completion of the job all in accordance with the original contract. The defendant has deposited in the registry of the Court this sum of $404.-50 admitting liability to the plaintiff therefor.

“It is the contention of the plaintiff that under the terms of this contract he is responsible for only such damage as might result from his negligence or improper workmanship and that he is not an insurer as to any damage which resulted from removing one roof and applying a new one. The contract contained the following clause:

“ ‘Any damage incurred to the building through the removal of said roofing materials, or in the installation of new roof shall be repaired at the expense of the contractor.’

“Counsel for the plaintiff has cited the case of A. H. White Company v. Burglass [La.App.], 184 So. 225, which interpreted a very similar contractual provision as follows :

“ ‘We feel that this is the proper interpretation of the clause in question and that consequently, the White Company cannot be held responsible for the damage sustained here unless the damage was caused by improper work, or by failure to protect portions of the exposed roof against rainfall. We therefore turn to the evidence to consider this question.’

“The Court is of the opinion that plaintiff’s contention is correct and that he is not responsible in damages unless the damage was caused by his negligence or improper work. We therefore shall consider the next question of whether plaintiff was guilty of negligence or failure to take proper precautions to prevent damage to the interior of the building.

“The plaintiff contends that he took the standard precautions which are usually taken by people in the roofing business and he is therefore free from negligence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Layne v. Schroeder
399 So. 2d 1262 (Louisiana Court of Appeal, 1981)
Victory Oil Company v. Perret
183 So. 2d 360 (Louisiana Court of Appeal, 1966)
Tripod Boats, Inc. v. George Engine Co.
170 So. 2d 238 (Louisiana Court of Appeal, 1964)
Davis v. Le Blanc
149 So. 2d 252 (Louisiana Court of Appeal, 1963)
Yeargain v. Blum
144 So. 2d 756 (Louisiana Court of Appeal, 1962)
Barrett Division, Allied Chemical & Dye Corp. v. Duplantis
141 So. 2d 478 (Louisiana Court of Appeal, 1962)
Crowley Grain Drier, Inc. v. Fontenot
132 So. 2d 573 (Louisiana Court of Appeal, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
128 So. 2d 821, 1961 La. App. LEXIS 2025, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vicknair-v-rapides-parish-school-board-lactapp-1961.