Seacoast Anti-Pollution League v. Nuclear Regulatory Commission

598 F.2d 1221, 9 Envtl. L. Rep. (Envtl. Law Inst.) 20384, 13 ERC (BNA) 1243, 1979 U.S. App. LEXIS 14343
CourtCourt of Appeals for the First Circuit
DecidedMay 30, 1979
Docket78-1172
StatusPublished
Cited by2 cases

This text of 598 F.2d 1221 (Seacoast Anti-Pollution League v. Nuclear Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Seacoast Anti-Pollution League v. Nuclear Regulatory Commission, 598 F.2d 1221, 9 Envtl. L. Rep. (Envtl. Law Inst.) 20384, 13 ERC (BNA) 1243, 1979 U.S. App. LEXIS 14343 (1st Cir. 1979).

Opinion

598 F.2d 1221

13 ERC 1243, 9 Envtl. L. Rep. 20,384

SEACOAST ANTI-POLLUTION LEAGUE and Audubon Society of New
Hampshire, Petitioners,
v.
NUCLEAR REGULATORY COMMISSION and United States of America,
Respondents,
Public Service Company of New Hampshire et al., Intervenors.

No. 78-1172.

United States Court of Appeals,
First Circuit.

Argued Oct. 6, 1978.
Decided May 30, 1979.

Robert A. Backus, Manchester, N. H., with whom Lawrence R. Hott, and O'Neill, Backus & Spielman, Manchester, N. H., were on brief, for petitioners.

Stephen S. Ostrach, Atty., U. S. Nuclear Regulatory Commission, Washington, D. C., with whom Peter R. Steenland, Jr., Chief, App. Section, James L. Kelley, Acting Gen. Counsel, Stephen F. Eilperin, Sol., and Jacques B. Gelin, Atty., App. Section, Land and Natural Resources Div., U. S. Dept. of Justice, Washington, D. C., were on brief, for respondents.

Thomas G. Dignan, Jr., Boston, Mass., with whom John A. Ritsher, R. K. Gad, III, and Ropes & Gray, Boston, Mass., were on brief, for intervenor, Public Service Company of New Hampshire.

Harrison A. Fitch, Boston, Mass., on brief, for New Hampshire Voice of Energy, as amicus curiae.

Before COFFIN, Chief Judge, CAMPBELL and BOWNES, Circuit Judges.

LEVIN H. CAMPBELL, Circuit Judge.

This petition for review of a decision of the Nuclear Regulatory Commission (NRC or "Commission"), 28 U.S.C. § 2342(4); 42 U.S.C. § 2239, questions whether the Commission's inquiry into possible alternative sites for the nuclear electric generating plant now being constructed at Seabrook, New Hampshire, was far ranging enough to comply with the National Environmental Policy Act (NEPA), 42 U.S.C. §§ 4321-4361.

In 1973, the Public Service Company of New Hampshire and others (PSCO) initiated proceedings before the Nuclear Regulatory Commission to obtain permits to construct a nuclear facility with once-through cooling at Seabrook, a town in coastal New Hampshire.1 Part of the agency process, which is outlined in our recent opinion in New England Coalition on Nuclear Pollution v. United States Nuclear Regulatory Commission, 582 F.2d 87, 93-96 (1st Cir. 1978), involved preparing a Final Environmental Statement (FES), which had to include a satisfactory statement on "alternatives to the proposed action." See National Environmental Policy Act (NEPA), 42 U.S.C. §§ 4332(2)(C)(iii), 4332(2)(E).2 While examining alternatives has been called the "linchpin" of NEPA's mandate, Monroe County Conservation Council, Inc. v. Volpe, 472 F.2d 693, 697-98 (2d Cir. 1972), there is no single rule for determining how many and what kinds of alternatives to study in a given case; as the Supreme Court stated in Vermont Yankee Nuclear Power Corp. v. NRDC, 435 U.S. 519, 551, 98 S.Ct. 1197, 1215, 55 L.Ed.2d 460 (1978), "Common sense . . . teaches us that the 'detailed statement of alternatives' cannot be found wanting simply because the agency failed to include every alternative device and thought conceivable by the mind of man." At issue here is whether the Commission should have compared the site at Seabrook, on which PSCO sought permission to build, with more alternative sites than it did. The Commission and PSCO, joined by the New Hampshire Voice of Energy, insist that the number of sites investigated more than met the NRC's NEPA obligations. Petitioners Seacoast Anti-Pollution League and Audubon Society of New Hampshire deny this. They say, in particular, that the Commission evaded NEPA in terminating an inquiry launched in 1976 into certain southern New England sites which, though outside PSCO's own service area, are within the region that will receive power generated by the proposed nuclear facility.

In the decision under review here, the Commission ruled, by a 2-1 vote, that, assuming once-through cooling was allowed at Seabrook, a sufficient inquiry into alternate sites had been made and additional sites in southern New England need not be considered further. Public Service Company of New Hampshire (Seabrook Station, Units 1 & 2), CLI-78-14, 7 N.R.C. (June 30, 1978). This decision was reached while the Environmental Protection Agency (EPA) was still considering PSCO's request for permission to use once-through cooling. The practical effect of the Commission's decision was to signal that the Seabrook plant could be completed if EPA allowed once-through cooling which, a month later, it did.3

The Commission's termination of the alternative sites inquiry came after approximately twenty-eight sites had been identified as possible alternatives to Seabrook. The Atomic Safety and Licensing Appeal Board (ALAB) had found that nineteen of these were not "obviously superior" to Seabrook with once-through cooling, apparently had considered six not to require in-depth study, and had asked the Commission to decide whether the remaining three should be investigated further.4

The Commission's decision emerged after a tortuous administrative history during which PSCO was allowed at times to proceed with construction at the Seabrook site even though the licensing process was incomplete. The tenor of the opinion, and of Commissioner Kennedy's and Bradford's separate opinions, illustrates that Seabrook's byzantine history has been a matter of concern to everyone; Commissioner Kennedy sees government bureaucracy as chiefly responsible for the on again-off again aspects of the proceeding; Commissioner Bradford, who would have required further examination of the southern sites, sees what has taken place as an object lesson in the dangers of building before an impartial NEPA survey is completed. The events preceding this decision under review may be recapitulated as follows:

In 1976 the Atomic Safety and Licensing Board (the Licensing Board) authorized the issuance of construction permits for a nuclear facility with once-through cooling at Seabrook, having found, Inter alia, that none of the nineteen alternative sites discussed in the FES was superior to Seabrook. Public Service Company of New Hampshire (Seabrook Station, Units 1 & 2), LBP-76-26, 3 N.R.C. 857, 907-11 (1976). The FES had considered possible northern New England sites for the PSCO facility, including Seabrook and other sites on or near the New Hampshire and Maine seacoasts, two offshore sites, and six inland New Hampshire sites. A Draft Environmental Statement (DES) covering similar ground had been released for public comment in 1974. None of the comments filed during the comment period had suggested that the NRC consider additional alternative sites in southern New England.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Valley Citizens for a Safe Environment v. Aldridge
695 F. Supp. 605 (D. Massachusetts, 1988)
Kunaknana v. Clark
742 F.2d 1145 (Ninth Circuit, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
598 F.2d 1221, 9 Envtl. L. Rep. (Envtl. Law Inst.) 20384, 13 ERC (BNA) 1243, 1979 U.S. App. LEXIS 14343, Counsel Stack Legal Research, https://law.counselstack.com/opinion/seacoast-anti-pollution-league-v-nuclear-regulatory-commission-ca1-1979.