SDDS, Inc. v. State

1997 SD 114, 569 N.W.2d 289, 1997 S.D. LEXIS 114, 1997 WL 574586
CourtSouth Dakota Supreme Court
DecidedSeptember 17, 1997
Docket19555
StatusPublished
Cited by25 cases

This text of 1997 SD 114 (SDDS, Inc. v. State) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
SDDS, Inc. v. State, 1997 SD 114, 569 N.W.2d 289, 1997 S.D. LEXIS 114, 1997 WL 574586 (S.D. 1997).

Opinions

KONENKAMP, Justice.

[¶ 1.] In 1988, South Dakota Disposal Systems (SDDS) began the process of founding the Lonetree municipal solid waste landfill in southwestern South Dakota. The plan met with many roadblocks, including citizen resistance, administrative and legislative activity, and court challenges. In 1992, a statewide referendum rejected prior legislative approval for the facility, and SDDS brought a takings action against the State for alleged losses resulting from the adverse vote. The circuit court granted summary judgment for the State, and SDDS appealed to this Court. While this appeal was pending, the Eighth Circuit Court of Appeals issued an injunction barring the State from relitigating key issues in the state court forum. Does this claim preclusion and liability determination mandate we reverse the summary judgment? As we are bound by its ruling, we answer yes, and remand the action to the circuit court consistent with the Eighth Circuit’s decision.

Facts

[¶2.] Nearly a decade ago, SDDS purchased 1200 acres of rangeland near Edge-mont in Fall River County. It was interested in locating and operating a balefill facility (Lonetree) that would receive initially 300,-000 and later over 7.75 million tons of municipal solid waste (MSW). On November 17, 1988, SDDS filed an application with the Department of Water and Natural Resources (Department)1 for a one-year permit, pursuant to SDCL ch 34A-6, to site, construct, and operate the MSW disposal facility. On July 10,1989, the Department published notices in four South Dakota newspapers that it intended to deny a one-year permit and listed six deficiencies in the SDDS application. The recommendation included a notice that aggrieved persons could petition the Board of Minerals and Environment (BME), a division of the Department, for a hearing within thirty days. SDDS filed a petition, and Technical Information Project (TIP), a public interest group, was allowed to intervene in the proceedings. Before the hearing, SDDS sought to cure the six deficiencies in the application by corresponding with the Department; this correspondence was made part of the public file.

[¶3.] Following an evidentiary hearing, the BME issued SDDS a one-year permit (Original Permit) on September 7, 1989, under SDCL 34A-6-1.16.2 TIP appealed to the circuit court, which affirmed the BME’s decision, despite purported errors regarding issuance of an Environmental Impact Statement, ex parte communications about the permit, and alleged deficient findings by the BME. A subsequent appeal was brought to this Court. In re Application of SDDS, Inc. for a Solid Waste Permit, 472 N.W.2d 502 (SD 1991)(RDDR I). On June 26, 1991, we reversed and remanded the decision to the BME for more specific findings to support the Original Permit regarding the public interest in and the environmental safety of the Lonetree dump.3 SDDS I, 472 N.W.2d at [291]*291513-14. Without such findings, the permit was void. Id.

[¶ 4.] While SDDS I was winding through the judicial system, a series of other events transpired. In March of 1990, SDDS petitioned the Department and Board for a five-year Renewal Permit to allow it to dispose of 7.75 million tons of MSW, 90% of which would be imported from other states. During this time, Action for the Environment (ACT),4 the public interest arm of TIP, was collecting petitions to put an Initiative on the November 6,1990 general ballot. The Initiative required legislative approval for solid waste facilities with yearly capacities over 200,000 tons. This Initiative passed on election day, to take effect on November 22, 1990.5 On November 7, 1990, SDDS laid off workers and ceased site preparations. It alleged that up to that time, it had expended over five million dollars in pursuit of the facility.6

[¶ 5.] At this point, the Department had yet to act on the Renewal Permit. On December 7, 1990, however, the Department granted the five-year Renewal Permit to SDDS, following another contested hearing. In January of 1991, SDDS filed suit in the Sixth Judicial Circuit, alleging $100 million in damages for inverse condemnation caused by the Initiative. SDDS voluntarily dismissed the action in the fall of 1991. Also in January 1991, a bill was introduced in the South Dakota Legislature to provide SDDS with the authorization needed to site and operate Lonetree. The bill, Senate Bill 169 (SB 169), passed both houses and was signed by Governor Mickelson in February, to take effect on July 1, 1991. In May, a Referendum petition was filed with the Secretary of State’s office, referring SB 169, seeking to overturn the legislative authorization for Lonetree, and to put the matter to a vote in November 1992. However, in June 1991, SDDS I was issued, reversing the right to develop and site the facility under the one year permit. SDDS I, 472 N.W.2d at 514.

[¶ 6.] In September 1991, the BME held a rehearing on the Original Permit, pursuant to direction from SDDS I. It made additional findings of fact regarding the public interest and environmental safety issues, based on the 1989 record. It issued no orders and no new permit, nor did it reissue the Original Permit. Then, in February 1992, we decided SDDS, Inc. v. State of South Dakota, 481 N.W.2d 270 (SD 1992)(SDDS II). In that case, we held that. SDDS was not authorized to start operations until after the 1992 Referendum vote. In the meantime, the Seventh Judicial Circuit was considering an appeal from the BME’s findings, and, in the spring of 1992, that court concluded we had reversed issuance of the Original Permit by virtue of SDDS II. So, the case was remanded to the BME. On April 16, 1992, the BME declined to reissue the Original Permit, despite the circuit court’s remand, because it wanted to wait until this Court decided the matter.

[292]*292[¶7.] During this time, a constitutional challenge to the Initiative was pending in the Sixth Judicial Circuit. On October 31, 1991, the circuit court upheld the constitutionality of the Initiative in all material respects.7 No appeal followed. The next month, SDDS filed a second takings-inverse condemnation action, having voluntarily dismissed the takings case pending in Hughes County. This time, suit was filed in 'Fall River County (Seventh Judicial Circuit) claiming $100 million in damages arising from both the Initiative and Referendum. The State appealed the venue of this action, and "we ruled in June 1993 that Hughes County, not Fall River County, was the appropriate venue. SDDS, Inc. v. State of South Dakota, 502 N.W.2d 852 (SD 1993)(SDDS III).

[¶ 8.] Still in question at this point was the validity of the Original Permit and the later Renewal Permit. In July 1992, the Seventh Judicial Circuit held that the Original Permit had been revoked by our actions in SDDS I. This was appealed, and we upheld the decision in Matter of 1990 Renewal Application of SDDS, 507 N.W.2d 702 (SD 1993)(SDDS IV). We noted that no permit existed after we remanded it to the BME for more findings in SDDS I. “One thing is absolute: Without proof of public interest, no permit could have been properly issued.” Id. at 703.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stock v. Garrett
2025 S.D. 8 (South Dakota Supreme Court, 2025)
Healy Ranch v. Healy
2022 S.D. 43 (South Dakota Supreme Court, 2022)
Charles Rhines v. Darin Young
899 F.3d 482 (Eighth Circuit, 2018)
Stewart v. Virgin Islands Board of Land Use Appeals
66 V.I. 522 (Supreme Court of The Virgin Islands, 2017)
Farmer v. South Dakota Department of Revenue & Regulation
2010 SD 35 (South Dakota Supreme Court, 2010)
United States v. Mathis Implement, Inc.
405 F. Supp. 2d 1101 (D. South Dakota, 2005)
State v. Schwartz
2004 SD 123 (South Dakota Supreme Court, 2004)
SDDS, Inc. v. State
2002 SD 90 (South Dakota Supreme Court, 2002)
Tri County Landfill Ass'n v. Brule County
2000 SD 148 (South Dakota Supreme Court, 2000)
SDDS, Inc. v. South Dakota
225 F.3d 970 (Eighth Circuit, 2000)
In Re: Sdds, Inc.
225 F.3d 970 (Eighth Circuit, 2000)
Ramos v. Weber
2000 SD 111 (South Dakota Supreme Court, 2000)
Krebs v. Weber
2000 SD 40 (South Dakota Supreme Court, 2000)
Frigaard v. Seffens
1999 SD 123 (South Dakota Supreme Court, 1999)
Hoogestraat v. Barnett
1998 SD 104 (South Dakota Supreme Court, 1998)
Hoogestrat v. Barnett
1998 SD 104 (South Dakota Supreme Court, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
1997 SD 114, 569 N.W.2d 289, 1997 S.D. LEXIS 114, 1997 WL 574586, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sdds-inc-v-state-sd-1997.