SCM Corp. v. Deltak Corp.

702 F. Supp. 1428, 1988 U.S. Dist. LEXIS 15324, 1988 WL 143008
CourtDistrict Court, D. Minnesota
DecidedNovember 16, 1988
DocketCiv. 4-88-127
StatusPublished
Cited by12 cases

This text of 702 F. Supp. 1428 (SCM Corp. v. Deltak Corp.) is published on Counsel Stack Legal Research, covering District Court, D. Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
SCM Corp. v. Deltak Corp., 702 F. Supp. 1428, 1988 U.S. Dist. LEXIS 15324, 1988 WL 143008 (mnd 1988).

Opinion

*1429 MEMORANDUM AND ORDER

MacLAUGHLIN, District Judge.

This matter is before the Court on a motion for summary judgment by defendant Deltak Corporation (Deltak). Deltak’s motion initially raises a question of choice of law. Using Minnesota’s conflicts rule, the Court has determined that Minnesota law should govern this case. That decided, the Court then finds that summary judgment is inappropriate at this stage of the proceedings. Therefore, Deltak’s motion will be denied.

FACTS

Deltak is being sued by plaintiff SCM Corporation (SCM) for damages resulting from a defective superheater sold by Del-tak to Chemetics International Company (Chemetics) for use by SCM in a pigment production plant in Bunbury, Western Australia.

In August 1984, SCM contracted with Chemetics, a Canadian corporation headquartered in North York, Ontario, for the purchase of a new converter and super-heater. The contract set forth particular specifications which would result in the superheater being adapted to SCM’s production process and required that the su-perheater be manufactured by either Del-tak or a company named Econotherm. Affidavit of Arthur S. Beeman, Exh. A at 33-34. The contract incorporated form AS 2124-1981, Australian General Conditions of Contract, which includes a clause allowing the parties to make a choice of law in an annex to the contract. Affidavit of Steven K. Champlin, Exh. A, AS 2121-1982, clause 2.1. The parties however, did not execute an annex.

In November 1984, Chemetics informed SCM that Deltak, a Minnesota corporation with its principal place of business in Plymouth, Minnesota, would be manufacturing the superheater. Beeman Aff., Exh. B at 3. At that time, Chemetics also provided SCM with Deltak’s production schedule for the superheater, including start and complete dates for various steps in the manufacturing process. Id.

Chemetics had entered into the contract with Deltak for the manufacture of the superheater in September 1984. Beeman Aff., Exh. C. In designing and manufacturing the superheater, Deltak was to follow the technical specifications provided by Chemetics. Beeman Aff., Exh. D. The specifications included the requirement that Deltak prepare complete fabrication drawings for welding details and that Del-tak document the quality of materials and fabrication by providing material test reports and welder certifications. Beeman Aff., Exh. D at 10-11. The contract between Deltak and Chemetics also incorporated a document titled Chemetics General Conditions No. GC/CO/282 which specified that the agreement shall be governed by the laws of the Province of British Columbia, Canada. Id., Exh. D, GC/CO/282 at par. 19. The same document stated that the vendor’s liability for breach of warranty shall be limited to the price of the defective goods. Id., Exh. D, GC/CO/282 at par. 16.7.

During the period of design and manufacture of the superheater, Chemetics and Deltak exchanged communications about the welds and the welding procedures being used by Deltak. Beeman Aff., Exh. E. Discovery in this case has so far been limited to responses to interrogatories and the production of documents. As a result, the full nature and substance of the communications between Chemetics and Deltak are not known at this time.

Deltak completed the superheater and delivered it to SCM on or about January 11, 1985. The new converter and superheater were placed into operation at the Bunbury plant in April 1985.

On July 28, 1985, SCM discovered that certain tubes to the superheater were leaking, necessitating the shutdown of the converter. The parties’ investigation revealed that the tubes had cracked because of Del-tak’s failure to properly weld and heat-treat the tubes. Beeman Aff., Exh. F, G. Deltak replaced the cracked tubes, at its own expense, on August 21, 1985.

In this suit, SCM alleges that the defective tubes in the superheater breached ex *1430 press warranties that (1) the superheater was designed, fabricated and manufactured with quality materials and workmanship, (2) the superheater was the result of advanced engineering and skilled manufacturing, (3) the superheater was in accordance with the specifications provided by Chemet-ics, and (4) the superheater was fit for the particular purposes of SCM. See, Complaint par. 18-19; Champlin Aff., Exh. C at 13-15. SCM further alleges that the defective tubes breached implied warranties that the superheater was fit for its ordinary purposes and fit for the particular purposes required by SCM. See, Complaint par. 22-25, Champlin Aff., Exh. C at 19-21. SCM claims indirect and consequential damages resulting from the failure of the superheater’s tubes, an amount in excess of $335,381. Complaint par. 26.

DISCUSSION

I. Choice of Law

Deltak’s motion for summary judgment requires, as a preliminary matter, that the Court decide what law governs the warranty claims advanced here. Deltak argues for the application of the law of British Columbia, while SCM contends that Minnesota’s law controls. The parties agree that Australian law should not be applied.

Ordinarily, the federal district courts apply the choice of law rules of the state in which they sit. Klaxon Co. v. Stentor Electric Mfg. Co., 313 U.S. 487, 61 S.Ct. 1020, 85 L.Ed. 1477 (1941). Minnesota’s approach to choice of law is based on the five “choice-influencing considerations” proposed by Professor Robert Leflar: predictability of results, maintenance of interstate and international order, simplification of the judicial task, advancement of the forum’s governmental interests, and application of the better rule of law. Milkovich v. Saari, 295 Minn. 155, 203 N.W.2d 408, 412 (1973). Even though Milkovich involved a tort claim, the language of the court’s opinion made clear that the choice-influencing analysis was to replace all of the old choice of law rules. Since Milkovich, the Minnesota courts have only departed from that analysis in cases involving a conflict of procedural rules. See Davis v. Furlong, 328 N.W.2d 150 (Minn.1983) (forum court should apply its own procedures and practices).

The choice-influencing analysis applies only if the laws which may govern the litigation conflict. Myers v. Government Employees Insurance Co., 302 Minn. 359, 225 N.W.2d 238, 241 (1974). The laws at issue here clearly do conflict. Under the law of British Columbia, privity of contract is required to enforce a warranty claim. 1 See, Affidavit of Rodney L. Hayley, par. 8. Under Minnesota law, a lack of privity does not bar recovery for breach of warranty. Minn.Stat. § 336.2-318.

A. Predictability of Results

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
702 F. Supp. 1428, 1988 U.S. Dist. LEXIS 15324, 1988 WL 143008, Counsel Stack Legal Research, https://law.counselstack.com/opinion/scm-corp-v-deltak-corp-mnd-1988.