Schreiner Excavating, Inc. v. Smith & Loveless, Inc.

CourtCourt of Appeals of Kansas
DecidedAugust 29, 2025
Docket127688
StatusUnpublished

This text of Schreiner Excavating, Inc. v. Smith & Loveless, Inc. (Schreiner Excavating, Inc. v. Smith & Loveless, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Schreiner Excavating, Inc. v. Smith & Loveless, Inc., (kanctapp 2025).

Opinion

NOT DESIGNATED FOR PUBLICATION

No. 127,688

IN THE COURT OF APPEALS OF THE STATE OF KANSAS

TODD SCHREINER EXCAVATING, INC., Appellant,

v.

SMITH & LOVELESS, INC., Appellee.

MEMORANDUM OPINION

Appeal from Johnson District Court; RHONDA K. MASON, judge. Oral argument held May 20, 2025. Opinion filed August 29, 2025. Affirmed.

Terry A. Iles, of Law Office of Terry A. Iles, of Topeka, for appellant.

Dan Crane Sanders, of Monaco, Sanders, Racine, Powell & Reidy, LLC, of Leawood, for appellee.

Before WARNER, C.J., CLINE and COBLE, JJ.

CLINE, J.: This case arises from a construction dispute between two Kansas contractors over a project in Texas. Smith & Loveless, Inc. (S&L) contracted with Todd Schreiner Excavating, Inc. (Schreiner) to perform work on the project, but a disagreement arose before the work was completed. S&L hired another contractor to finish the job and Schreiner sued for unpaid work on the project. The district court entered judgment for Schreiner for part of the damages sought and denied its claim for attorney fees and prejudgment interest under the Kansas Fairness in Private Construction Contract Act

1 (KFPCCA), K.S.A. 16-1801 et seq., after finding the amounts sought were disputed. Schreiner appeals the district court's decision denying relief under the KFPCCA.

After reviewing the record, we see no error in the district court's ruling. The KFPCCA only provides for interest and attorney fees related to undisputed requests for payment, and Schreiner did not establish the amounts it sought were undisputed or that S&L wrongfully withheld retainage owed to Schreiner. See K.S.A. 16-1803; K.S.A. 16- 1804; K.S.A. 16-1806.

FACTUAL AND PROCEDURAL BACKGROUND

In 2018, S&L was hired to perform work at a petrochemical facility in Point Comfort, Texas. S&L then subcontracted with Schreiner to perform part of this work. The parties entered "lump sum" contracts for two projects: Project 229 (the three tanker project) and Project 225 (the dirty tanker project). Each contract provided for installment or "progress" payments due after Schreiner's completion of described stages of work. Both contracts allowed S&L the discretion to condition payment to Schreiner on Schreiner signing a partial lien release or final lien release, with forms for each release attached as addendums to the contracts.

Schreiner began work on both projects and received progress payments for each. At first, S&L did not condition payment for work on the three tanker project on Schreiner's execution of a lien release. The parties also agreed to two change orders for additional work on the three tanker project. S&L did not condition payment for the change order work on Schreiner's execution of a lien release. But Schreiner signed partial lien releases before receiving progress payments on the dirty tanker project and the three tanker project.

2 After completing work on the dirty tanker project but before the three tanker project was completed, the parties disagreed over whether Schreiner was owed payment on change orders it submitted on the dirty tanker project. Under the contract, any additional work outside the scope of the contract and the cost for such work required prior written approval by S&L. S&L contended Schreiner did not obtain the required approval for this change order work and its charges for the change order work were excessive. While Schreiner claimed an S&L project manager had approved the change orders, S&L disputed this claim and said the manager had no authority to approve change orders—only the company president did.

The parties met to try to resolve their dispute. At this meeting, S&L agreed to pay part of the change order amount sought by Schreiner ($14,000) along with the final retainage payment of $7,450. Schreiner admitted it agreed to accept the negotiated change order amount as final payment on the dirty tanker project but later claimed the payment was supposed to be made that day.

Around this time, Schreiner submitted an invoice to S&L for a progress payment related to demolition work on the three tanker project in the amount of $62,782.50. But it then submitted a letter to the project owner claiming it was owed $85,000 plus $8,500 for retainage for this work. At this same time, it submitted other letters to the owner claiming it was owed $61,500 plus $6,150 for retainage for interconnecting piping work and $10,463 for an additional 10% retainage owed upon completion of the three tanker project, and $7,450 for the final 10% retainage and $22,097.67 for change order work on the dirty tanker project.

S&L sent Schreiner a partial lien release for execution as a condition for the $62,782.50 payment due on the three tanker project and a final lien release for execution as a condition for sending Schreiner the $21,450 it had agreed to pay to close out the dirty tanker project. At that point, the parties reached an impasse on payments for both

3 projects. Schreiner refused to sign any lien releases before it was paid and demanded payment of the amount in the notices it had sent the owner. S&L explained to Schreiner that the releases would not become effective until payment was made, per the language of the releases, and that the contract required the signed releases be submitted before payment could be processed. S&L also pointed out that the notices Schreiner sent to the owner were incorrect because they included claims for work that was not yet done, retainage that was not yet due, and the amount of the change order claim on the dirty tanker project was more than what the parties had agreed S&L would pay for that work.

A few weeks later, Schreiner's counsel sent a demand letter to S&L seeking payment of the amounts in the notices sent to the owner and claiming Schreiner was filing a lien on the project. Schreiner eventually sued and, in its complaint, alleged two counts of breach of contract as well as claims for promissory estoppel, quantum meruit, negligence, and violation of the KFPCCA. S&L counterclaimed for amounts it claimed it had to pay another contractor to finish the work on the three tanker project. Schreiner ultimately withdrew its promissory estoppel and negligence claims.

After a three-day bench trial, the district court ruled for Schreiner on its breach of contract claims, awarding a total of $29,738.26 for the dirty tanker project and $104,846.25 for the three tanker project. It dismissed Schreiner's quantum meruit claim and ruled in favor of Schreiner on S&L's counterclaim. The court denied Schreiner's claim for prejudgment interest and attorney fees under the KFPCCA because it found the payment amounts were disputed. It also noted the KFPCCA states a contract may require a subcontractor to provide a lien waiver or release as a condition for payment. The only portion of that decision which Schreiner raises on appeal is whether the district court erred in finding its damages were disputed and therefore the KFPCCA did not apply.

4 REVIEW OF SCHREINER'S APPELLATE CHALLENGE

Schreiner first argues the district court erred by finding that the damages were disputed, which was the court's basis for concluding Schreiner was not entitled to prejudgment interest and attorney fees under the KFPCCA.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tucker v. Hugoton Energy Corp.
855 P.2d 929 (Supreme Court of Kansas, 1993)
Cosgrove v. Young
642 P.2d 75 (Supreme Court of Kansas, 1981)
In Re the Estate of Broderick
191 P.3d 284 (Supreme Court of Kansas, 2008)
Trear v. Chamberlain
425 P.3d 297 (Supreme Court of Kansas, 2018)
Becker v. The Bar Plan Mut. Ins. Co.
429 P.3d 212 (Supreme Court of Kansas, 2018)
Casper v. Kansas Dept. of Revenue
442 P.3d 1038 (Supreme Court of Kansas, 2019)
State v. Espinoza
462 P.3d 159 (Supreme Court of Kansas, 2020)
Roll v. Howard
480 P.3d 192 (Court of Appeals of Kansas, 2020)
State v. Rhoiney
501 P.3d 368 (Supreme Court of Kansas, 2021)
Bruce v. Kelly
514 P.3d 1007 (Supreme Court of Kansas, 2022)
In re the Marriage of Bradley
899 P.2d 471 (Supreme Court of Kansas, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
Schreiner Excavating, Inc. v. Smith & Loveless, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/schreiner-excavating-inc-v-smith-loveless-inc-kanctapp-2025.