§ 16-1804 — Retainage; release of retainage; incomplete work; alternate security; failure to pay

Kansas·Ch. 16 CONTRACTS AND PROMISES·Art. 18 KANSAS FAIRNESS IN PRIVATE CONSTRUCTION CONTRACT ACT
(a)Retainage shall not exceed 5% of the value of the contract or subcontract unless the owner or contractor determines that a higher rate of retainage is required to ensure performance of the contract. Retainage, however, shall not exceed 10% of the value of the contract or subcontract.
(b)If the contractor or subcontractor has failed to meet the terms of the contract, is not performing according to schedule or there is a problem with workmanship or other issues, the owner may increase retainage up to 10%.
(c)An owner shall release all remaining retainage on any undisputed payment due to a contractor on a construction project within 30 days after substantial completion of the project; however, if any contractor or subcontractor is still performing work on the project, an owner may withh

Free access — add to your briefcase to read the full text and ask questions with AI

Kansas § 16-1804 (Retainage; release of retainage; incomplete work; alternate security; failure to pay) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Monarch Build v. DLH Holdings
567 P.3d 831 (Court of Appeals of Kansas, 2025)
1 case citations

Legislative History

L. 2005, ch. 156, § 4; L. 2010, ch. 128, § 2; July 1.