Kansas Statutes

§ 16-1804 — Retainage; release of retainage; incomplete work; alternate security; failure to pay

Kansas § 16-1804
JurisdictionKansas
Ch. 16CONTRACTS AND PROMISES
Art. 18KANSAS FAIRNESS IN PRIVATE CONSTRUCTION CONTRACT ACT

This text of Kansas § 16-1804 (Retainage; release of retainage; incomplete work; alternate security; failure to pay) is published on Counsel Stack Legal Research, covering Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kan. Stat. Ann. § 16-1804 (2026).

Text

(a)Retainage shall not exceed 5% of the value of the contract or subcontract unless the owner or contractor determines that a higher rate of retainage is required to ensure performance of the contract. Retainage, however, shall not exceed 10% of the value of the contract or subcontract.
(b)If the contractor or subcontractor has failed to meet the terms of the contract, is not performing according to schedule or there is a problem with workmanship or other issues, the owner may increase retainage up to 10%.
(c)An owner shall release all remaining retainage on any undisputed payment due to a contractor on a construction project within 30 days after substantial completion of the project; however, if any contractor or subcontractor is still performing work on the project, an owner may withh

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Monarch Build v. DLH Holdings
567 P.3d 831 (Court of Appeals of Kansas, 2025)
1 case citations

Legislative History

L. 2005, ch. 156, § 4; L. 2010, ch. 128, § 2; July 1.

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Kansas § 16-1804, Counsel Stack Legal Research, https://law.counselstack.com/statute/ks/16-1804.