Schnute Holtman & Co. v. Sweeney

125 S.W. 180, 136 Ky. 773, 1910 Ky. LEXIS 541
CourtCourt of Appeals of Kentucky
DecidedFebruary 15, 1910
StatusPublished
Cited by11 cases

This text of 125 S.W. 180 (Schnute Holtman & Co. v. Sweeney) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Schnute Holtman & Co. v. Sweeney, 125 S.W. 180, 136 Ky. 773, 1910 Ky. LEXIS 541 (Ky. Ct. App. 1910).

Opinion

Opinion op the Court by

Judge O’Rear

— Affirming.

F. N. Barnes & Co., contractors, agreed in writing with A. G-. Sweeney on March -22, 1904, to furnish [775]*775for the sum of $4,000 all the labor and material necessary to remodel, build, and complete for him, according to architect’s plans and specifications, two houses on his lot in Owensboro. Appellant Schnute Holtman Company by contract with Barnes & Co. furnished $1,117.46 worth of material, which was used in building the house. Under the agreement between the owner and the contractors, the latter were to be paid as the work progressed 80 per cent, of the estimates of the work as certified to by the architect, and the owner did pay to them from time to time to the amount of $2,750 on the contract price. Certain alterations were made in the plans, which increased the contract price $500 as found by .the circuit court. Barnes & Co. abandoned the work before it was completed, and the owner was compelled to, and did, buy other material and employ labor to finish the job at a cost of $2,470.90. Barnes & Co. paid nothing on their contract with Schnute Holtman Company for material. The latter filed in due season an itemized, verified statement of the account for material, in order to obtain a materialman’s lien on the lots under sections 2463-2468, Ky. Stat. Appellant then brought this suit to enforce its lien, claiming interest on its account from October 1, 1904. Sweeney, before answer, offered to confess judgment for $800 and interest from October 11, 1904, which was declined by the plaintiff. Sweeney then answered, denying that appellant had furnished the material to be used in those buildings, and he set out that he had made the payments above stated, all of which had been used by Barnes & Co. in paying for other material furnished and labor done in building the houses, and that he had paid and would be compelled to pay to complete the work $2,470.40 more [776]*776(found by the court to be $2,395); that these sums exceeded the contract price; and that he should not be compelled to pay plaintiff more that its pro rata of the contract price, measured by the sum of all labor and material furnished by others than Barnes & Co. It is admitted of record that Sweeney paid the sums for labor and material as claimed in his answer.

Assuming that the extra ‘work increased the contract price by $500 as found by the circuit court (and we are not inclined to disturb that finding on this record), the facts are that the contract price'was $4,500, and the owner has paid $5,125 on account of labor and material, not including- labor and material furnished by the contractors Barnes & Go. The sum owing- appellant for material, $1,117.46, brings the total cost up to $6,242.46. The question for decision is: Must the owner pay appellant’s claim of $1,117.-46 in full under the statute, or is it to be prorated with the other claims paid by the owner for the labor and other material? The judgment of the circuit court from which this appeal is prosecuted was based upon the latter proposition. The statute defining- the condition upon which the liens of materialmen and laborers may arise as against the owner of the property is section 2463, Ky. Stat. (Carroll’s). The lien is given to those who perform labor or furnish material for the improvement by erecting structures or machinery upon real estate of another by contract with or by the written consent of the owner, contractor, subcontractor, architect, or authorized agent. The statute contemplates that the owner who contracts for such improvement of his property includes in his contract every person who furnishes any part of the material, or does any part of the labor, whether named or not, and without reference to the actual [777]*777knowledge of the owner that he is so furnishing .the material, or doing some part of the work. This construction of the statute was first given in Hightower v. Bailey, 108 Ky. 198, 56 S. W. 147, 22 Ky. Law Rep. 88, 49 L. R. A. 255, 94 Am. St. Rep. 350, and has been adhered to ever since. The only limitation upon the owner’s liability found in the words of the statute is in this clause of section 2463: “The liens provided for herein shall in no case be for a greater amount in the aggregate than the contract price of the original contractor; and should the aggregate amount of liens exceed the price agreed upon between the original contractor and the owner, then there shall be a pro rata distribution of the original contract price among said lienholders.” There is no express distinction in the letter of the statute between the lien given to the original contractor and that given to materialmen who furnish him material, or laborers who work for him on the building, or subcontractors who perform some of the work. The statute gives each of them a lien on the property as against the owner and under the letter of the proviso quoted above no distinction is suggested between them when the liens are greater in the aggregate than the contract price. But that is only a seeming equality. The original contractor has a lien under the statute against the property to the extent of the contract price for the material and labor he furnishes. The subcontractor, and those who' furnish to the contractor, or subcontractor, labor or material for the building, have liens also, subject to the-terms of the statute. But they have in addition a demand against the one with whom they contracted for the full amount of their claim for services or material irrespective of their liens. The priority is worked [778]*778out upon the .principle of subrogation; that is, those to whom the contractor is indebted for labor or material furnished for the building are not only given a lien upon the property the value of which they have enhanced, but, as between them and the contractor, they have a prior right to be paid out of the property, because the lien is created by their labor or goods, and he has agreed to pay them out of the proceeds. Should he be suffered to share equally with them, he might, as by collecting his pay in advance, defeat a large part of their claims if the contract price be less than the total of the liens. But if the contracts are of equal dignity, as where some perform labor, another furnishes part of the material under a contract with the owner, and another another part, their liens will be of equal rank; or, if the whole contract be let to one contractor, and he sublets the work or some part of it, and buys the materia! from others for the building, his laborers and material-men will share equally in the apportionment' of the contract before he will be allowed to take any part of it. These principles are deducible from the cases following Hightower v. Bailey, supra, which will be noticed below. The statute is read into each contract. The owner is presumed to have engaged to each person employed in work upon or furnishing material for the building to pay him for his work or property out of the contract price, and to take notice not only'of the fact that they have furnished the labor and material, but of the' rank of the priorities among’ them. The owner is protected by the statute, in that his liability is limited to his contract price. He need not pay any of it until protected by having the release of the subcontractors, laborers, and materialmen. The statute makes a short period of [779]*779limitation, after which, if the liens are not then perfected of record, he may safely ignore them.

In Hodges v. Arvidson, 66 S. W. 601, 23 Ky. Law Rep.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Delta Air Lines, Inc. v. August
450 U.S. 346 (Supreme Court, 1981)
Charles White Co. v. Percy Galbreath & Sons, Inc.
563 S.W.2d 478 (Court of Appeals of Kentucky, 1978)
Young v. Porter-Leach Hardware Co., Inc.
148 S.W.2d 718 (Court of Appeals of Kentucky (pre-1976), 1941)
Biehl v. Biehl's Adm'x
93 S.W.2d 836 (Court of Appeals of Kentucky (pre-1976), 1936)
Martin v. Provident Life & Accident Insurance
47 S.W.2d 524 (Court of Appeals of Kentucky (pre-1976), 1932)
Pierce v. J. B. Pierce's Trustee in Bankruptcy
38 S.W.2d 254 (Court of Appeals of Kentucky (pre-1976), 1931)
Mays v. Stegeman
280 S.W. 464 (Court of Appeals of Kentucky (pre-1976), 1926)
Turner's Administrator v. Ward
256 S.W. 389 (Court of Appeals of Kentucky, 1923)
Bennett v. Miller
166 S.W. 805 (Court of Appeals of Kentucky, 1914)
Doll v. Young
149 S.W. 854 (Court of Appeals of Kentucky, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
125 S.W. 180, 136 Ky. 773, 1910 Ky. LEXIS 541, Counsel Stack Legal Research, https://law.counselstack.com/opinion/schnute-holtman-co-v-sweeney-kyctapp-1910.