Mays v. Stegeman

280 S.W. 464, 213 Ky. 60, 1926 Ky. LEXIS 449
CourtCourt of Appeals of Kentucky (pre-1976)
DecidedFebruary 12, 1926
StatusPublished
Cited by6 cases

This text of 280 S.W. 464 (Mays v. Stegeman) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky (pre-1976) primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mays v. Stegeman, 280 S.W. 464, 213 Ky. 60, 1926 Ky. LEXIS 449 (Ky. 1926).

Opinion

Affirming.

In this action appellants, who are general contractors, seek to enforce a claimed mechanic's lien against appellee's property located in Fort Thomas, Kentucky, and from a judgment granting them less than the relief prayed for, they appeal.

The facts are these: Appellee in the winter of 1922 bought an old house and lot from his brother-in-law for the sum of $14,000.00. The property was very much run down and needed a good deal of work done upon it in order to put it in a salable condition. As appellee had bought the house to sell it, he employed an architect to make some sketches of the needed repairs and changes. This the architect did. Appellee submitted these sketches to the appellants in the early part of January, 1923, with the request that they make an estimate of what the work would cost. The appellants made a bid on this work of $4,335.00. Appellee, however, decided to have more work done than called for by these sketches, and so he had his architect to draw some other plans, and these, together with the specifications for the work covered by them, he submitted to the appellants in February, 1923. The appellant, J.K. Mays, on February 26th agreed for his firm in writing to do the work shown in these plans and specifications for "about $6,400.00," and appellee told him to go ahead with the job. It is admitted that the work, which was started on March 15, 1923, had barely been begun when appellee and his wife started making changes in the plans and specifications theretofore agreed upon, and it is not seriously contended by either *Page 62 side that these original plans, specifications and bid were not in fact abandoned. Appellants in their petition aver that the work which they did was performed under "an express oral contract direct" with the appellee, whereby they were to perform the labor and furnish the materials in the alteration and repair of the property in question at a cost to the appellee "of the actual cost to plaintiffs (appellants) of the labor and material so performed, furnished and delivered, plus a fair and reasonable profit thereon to plaintiffs and plus the cost to plaintiffs of premiums for workmen's compensation insurance for workmen upon said job." Appellee, however, denies that any such agreement as this was entered into, but says that when the changes in the plans and specifications were made from time to time an outside price in each instance was agreed upon for such changes so directed, the appellants agreeing to do the work for less if possible, but in no event to exceed this outside figure. Appellant J.K. Mays admits that in the spring of 1923, after a number of changes had been made, he told the appellee that the work was going to cost about $8,000.00. Appellee says that Mays said the cost would not exceed $8,000.00. Mays further admits that in July, 1923, he told appellee that the work with the changes then ordered would cost about $11,500.00, which figure, the next day, he increased to $12,500.00. Appellee's version again is that Mays agreed at this time that the cost of the work should not exceed $11,500.00. In the early part of November, 1923, the architect made a demand upon appellee for his architect's fee, which was based on the cost of the work done, which he estimated at that time to be about $16,000.00. Appellee was astounded on hearing this figure because, as he says, he had been relying on the agreement of Mays that the cost should not run over $11,500.00. He at once called Mays into consultation. He says that Mays first contended that the architect was mistaken in his figures, but that he insisted that the matter had gone by the joking stage and that he wanted to know exactly where matters stood. He says that he reminded Mays that the latter had in the previous July agreed that the outside price for this work should be $11,500.00, and he now wanted to know what the bills totaled. Mays promised to get these bills together. On November 6, 1923, the parties had another conference. Appellee inquired of Mays what was the verdict and Mays replied that the architect was right. Appellee was amazed. He then *Page 63 said: "We have got to thrash this thing out right now, and we are going to come to a final understanding of the cost of this house. There is no scratch of the pen between us." Accordingly all the bills for labor and material furnished by appellants and those of subcontractors for work they had done were gone over and added up. After this was done, according to the appellee, who is supported in toto by one other witness and partially by a second, appellants then agreed to finish the work yet remaining to be done, including the grading of the yard, for a sum not exceeding $19,000.00 for the whole job. Appellants' version of this transaction, however, is that appellee asked Mays if the work was going to cost him $19,000.00, and Mays answered: "Yes, and more, too." Mays flatly denies that he agreed to complete the job at a cost not to exceed $19,000.00. However, on this question as to what occurred on this occasion, the commissioner to whom this case was referred and the chancellor who tried it on exceptions to the commissioner's report, both found against the appellants. Not only is their finding entitled to weight by this court on appeal, but it is also in accord with the preponderance of the evidence. It is admitted by both sides that the work on the house was approximately seventy-five per cent complete at the time of this conference and that it was finished with the exception of a few minor details, including the grading of the yard, which has never been done, in the early part of December. Just before Christmas appellants sent to appellee a bill for the work done on the house amounting to $29,294.86, subject to credits of $18,603.94, leaving a balance claimed to be due of $15,690.92. This bill was made up of claims for labor and material, performed and furnished, and subcontractors paid, amounting to $26,446.91; workmen's compensation insurance, $203.25; and ten per cent profit, $2,644.60. Appellee was flabbergasted on the receipt of this bill. He had bought the property for $14,000.00 for the purpose of resale. It is admitted by appellant J.K. Mays that he tried to sell the property for appellee just about the time the work was completed for $35,000.00. It seems to be conceded that this is the best price this house will bring. Appellee, who had made all of his plans, relying, as he says, on the figures given him by Mays and the agreements made by him as to the outside price the work was costing, was absolutely unable to understand appellant's bill, and so he at once sought an interview *Page 64 with J.K. Mays. On account of the latter's illness at that time, it was not until January that the two got together. Appellee and Mays each insisted on their respective versions of what took place on November 6th, and the interview was fruitless of result. Appellants then brought this suit to enforce their claim above set out. Appellee filed his answer setting out his side of the transaction and pleading certain counterclaims for defective work claimed to have been done. These counterclaims were not allowed by the lower court, and as there is no cross-appeal we need not further consider them. The case was referred to the commissioner and after elaborate proof, in which the appellants satisfactorily showed that they had paid on this work the sum of $26,446.91 for labor and material furnished by them and for work done by subcontractors, the commissioner found on the turning point in this case that on November 6, 1923, the appellants agreed to furnish all the labor and material for the alteration and repair of appellee's property, including the grading of the yard, for $19,000.00.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McDowell Welding & Pipefitting, Inc. v. United States Gypsum Co.
149 P.3d 173 (Court of Appeals of Oregon, 2006)
Eagle Industries, Inc. v. Thompson
900 P.2d 475 (Oregon Supreme Court, 1995)
Washington v. Heid
504 P.2d 745 (Oregon Supreme Court, 1972)
Olympic Realty Co. v. Kamer
141 S.W.2d 293 (Court of Appeals of Kentucky (pre-1976), 1940)
Barret v. Clarke
9 S.W.2d 1091 (Court of Appeals of Kentucky (pre-1976), 1928)

Cite This Page — Counsel Stack

Bluebook (online)
280 S.W. 464, 213 Ky. 60, 1926 Ky. LEXIS 449, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mays-v-stegeman-kyctapphigh-1926.