Schively v. Radell

76 A. 209, 227 Pa. 434, 1910 Pa. LEXIS 680
CourtSupreme Court of Pennsylvania
DecidedFebruary 1, 1910
DocketAppeal, No. 391
StatusPublished
Cited by14 cases

This text of 76 A. 209 (Schively v. Radell) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Schively v. Radell, 76 A. 209, 227 Pa. 434, 1910 Pa. LEXIS 680 (Pa. 1910).

Opinion

Opinion by

Mr. Justice Mestrezat,

March 14, 1910:

This is a scire facias on a mechanic’s lien filed by a subcontractor against two structures erected on the liened premises. The material and controlling facts of the case require us to affirm the judgment for defendant entered by the trial court.

Radell, the defendant, became the owner, by deed recorded May 20, 1907, of a lot or piece of ground, “known and designated as lots Nos. eight and thirty-nine on a certain plan of lots of Glenside Highlands,” in Abington township, Montgomery county. The two lots were adjacent and were situated at the corner of Roberts and Lynwood avenues in the village of Glenside.

On August 10, 1907, Radell entered into a written contract with the Phoenix Wood Working Company for the erection of a dwelling house “on a certain lot or piece of ground situated at the corner of Roberts and Lynwood Avenues in Glenside, County of Montgomery, and State of Pennsylvania;” and a few days thereafter work was begun on the building. The contract was filed of record in the prothonotary’s office of Montgomery cohnty on August 14,1907.

Radell entered into a written contract, October 10, 1907, with the Phcenix Wood Working Company for the erection of a stone and frame garage ón a lot or piece of ground described as in the former contract. [437]*437Seliively, the plaintiff, furnished lumber to the general contractor for both the residence and the garage, and filed a claim against the two buildings or structures to enforce payment of a balance of $1,387.82, which he alleges to be due and unpaid. The claim is filed against the house and the garage, describing each separately. The lien avers the garage to be forty feet from the house and that “the real estate, upon which the said buildings or structures have been erected, consists of two certain lots or pieces of land, situate in said village of Glen-side, in the township of Abington, said county, being lots Nos. 8 and 39 on a plan of lots known as the ‘Glenside Highlands,’ which plan is recorded in the office for the recording of deeds, in and for said county, in deed book, No. 456, page 500. Said lots taken together are situate on the southeasterly side of Roberts Avenue, at the intersection of the same with the southwesterly side of Lynwood Avenue, with a front on the said side of Roberts Avenue of one hundred and seventy-eight feet ten and three-eighths inches and with a front or depth on the said side of Lynwood Avenue of one hundred and thirty-six feet three and one-fourth inches.” The materials were furnished between August 23, 1907, and December 12, 1907. Schively gave a written notice to the owner, March 11, 1908, of his intention to file a lien, and the lien was filed May 14, 1908.

The owner contends that the lumber was furnished by the plaintiff to the contractor under two separate and distinct contracts, under one, for the dwelling house, and under the other, for the garage. The learned court below found this fact in accordance with the owner’s contention. The plaintiff denies there were two contracts under which the lumber was furnished to the contractor, and maintains that “there was but one understanding and that all the materials whether for the house or the garage were furnished in pursuance of it.” Of course, if this was an open question and there was testimony to support the contention on both sides, the question should be submitted for the determination of a jury. We think, however, that under the uncontradicted evidence the owner’s contention must be sustained, and that if the question had [438]*438been submitted to a jury the court could not have permitted a different finding. The plaintiff’s own testimony conclusively shows that the lumber was furnished for the buildings under two separate and distinct “arrangements” or contracts.

The contract for the house was let on August 10,1907. It is admitted that the Phoenix Wood Working Company, the general contractor, submitted to the plaintiff a list of the lumber which would be required or desired for the house. The plaintiff bid on this list and on August 19,1907, addressed a letter to the Phoenix Company in which he said: “I will deliver the lumber to Glenside as per your list for $1,462.” This offer was accepted and the lumber for the house was delivered in pursuance of it. ' Plaintiff’s bookkeeper and manager testified that he made a specific contract with the Phoenix company for the lumber which he was to ship to the house for $1,462. The plaintiff admits in his testimony that the written offer to furnish the lumber for the house was accepted, and that in delivering the lumber the list furnished by the Phoenix company was adhered to as nearly as could be. It is, therefore, manifest from the plaintiff’s own testimony, apart from the corroborative testimony of the defendant, that there was a contract between the plaintiff and the contractor by which, for the consideration óf a lump sum, the former agreed to furnish lumber for the house according to the list submitted to the plaintiff by the contractor.

We think it equally clear that there was another and separate “arrangement” or contract between the plaintiff and the contractor by which the former was to furnish to the latter the lumber for the garage. The contract for erecting the garage, it will be observed, was not made until October 10, 1907, two months after the contract for the erection of the dwelling house. During the progress of the work on the house and prior to the contract for the construction of the garage, the contractor wrote the plaintiff a letter relative to the material used in the house which contained, inter alia, the following: “We áre figuring on a garage for Mr. Radell which will require about 8,000 more of them (shingles) besides other lumber. [439]*439Will send you list if we secure the contract.” At that time it is apparent that the Phcenix company had not given the plaintiff an order for the lumber or entered into any contract with him to furnish the lumber for the garage. In fact, the Phcenix company could not have done so as it did not have a contract, at the time, with the owner for the erection of the garage. The letter, however, advised the plaintiff that in the event of the Phcenix company securing the contract for the construction of the garage, it would submit another proposition to him for furnishing lumber for that building. This was done, and on October 10,1907, the date of the contract between the Phoenix company and the owner for the construction of the garage, the company submitted a list of lumber to the plaintiff who agreed to furnish it on the same basis as that upon which the estimate for the house had been made. The plaintiff’s bookkeeper and manager testified that he copied in his books the list of lumber submitted by the Phcenix company and marked the prices that were to be paid the plaintiff by the company which were the same as those charged in the contract for the house. He says that when the list was submitted he informed the parties submitting it that the prices would be the same as those charged for the lumber furnished for the house. There is no dispute as to these facts. They appear from the plaintiff’s own testimony and hence he is not in a position to controvert them. Conceding them to be true, an offer was made to furnish certain lumber at a certain price which was accepted, This constituted a contract between the Phoenix company and the plaintiff, and was entirely separate and distinct from the contract under which the plaintiff furnished lumber for the erection of the dwelling house.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Projects Unlimited, Inc. v. Copper State Thrift & Loan Co.
798 P.2d 738 (Utah Supreme Court, 1990)
Meyers Plumbing & Heating Supply Co. v. Caste
504 A.2d 942 (Supreme Court of Pennsylvania, 1986)
Waite v. Schneider
57 Pa. D. & C.2d 788 (Bucks County Court of Common Pleas, 1972)
Day & Zimmermann, Inc. v. Blocked Iron Corp. of America
15 Pa. D. & C.2d 251 (Philadelphia County Court of Common Pleas, 1958)
Bossen v. Nocella
16 Pa. D. & C.2d 158 (Montgomery County Court of Common Pleas, 1958)
Laird Lumber Co. v. Billioni
13 Pa. D. & C.2d 236 (Mercer County Court of Common Pleas, 1957)
Fotheringham v. McPherson
17 Pa. D. & C.2d 199 (Philadelphia County Court of Common Pleas, 1957)
Oyer v. Coble
71 Pa. D. & C. 293 (Franklin County Court of Common Pleas, 1950)
Rockwell v. Keihl
62 Pa. D. & C. 560 (Franklin County Court of Common Pleas, 1948)
Kiddy's Appeal
143 A. 909 (Supreme Court of Pennsylvania, 1928)
Seibert v. Glasser Hosiery Co.
2 Pa. D. & C. 525 (Berks County Court of Common Pleas, 1922)
O'Kane v. Murray
97 A. 94 (Supreme Court of Pennsylvania, 1916)
Bennett Lumber & Manufacturing Co. v. Hartrick
61 Pa. Super. 456 (Superior Court of Pennsylvania, 1915)
Black v. Hartrick
93 A. 638 (Supreme Court of Pennsylvania, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
76 A. 209, 227 Pa. 434, 1910 Pa. LEXIS 680, Counsel Stack Legal Research, https://law.counselstack.com/opinion/schively-v-radell-pa-1910.