This text of 2 Pa. D. & C. 525 (Seibert v. Glasser Hosiery Co.) is published on Counsel Stack Legal Research, covering Pennsylvania Court of Common Pleas, Berks County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Seibert v. Glasser Hosiery Co., 2 Pa. D. & C. 525, 1922 Pa. Dist. & Cnty. Dec. LEXIS 341 (Pa. Super. Ct. 1922).

Opinion

WAGNER, J.,

The plaintiffs filed a mechanic’s lien against the defendant’s property for the sum of $3029.10. The defendant asks that it be stricken off for two reasons. The first reason is that the claim is defective upon its face, in that it affirmatively appears therein that the principal item of the claim is for the furnishing and installing of a certain Webster vacuum system of steam heating, and that said system was installed by the said claimant under a certain conditional sales agreement bearing date of July 24, 1920, wherein and whereby the claimant retained title to the right of possession to the same until fully paid for in cash, and not upon the faith and credit of the structure or building, as is formally averred in the statement.

The part of the agreement referred to is: “The title and right of possession to the machinery remains in the vendor and shall be deemed personal property until the same has been fully paid for in cash. The purchaser agrees to do all acts necessary to perfect and maintain the above title and right.”

There is no allegation that the materials furnished and the work done were not in accordance with the* claim as filed. Therefore, “it is presumed that the materials were furnished or the work was done on the credit of the building, and the burden is upon the defendants to show that this was not the case:” Green & Co. v. Thompson et al., 172 Pa. 609, 610.

The defendant contends that because plaintiffs have retained title in accordance with the clause in the agreement under which the material was furnished and the work done, this in itself rebuts the presumption that the material was furnished and the work done on the credit of the building.

It has been repeatedly decided that the taking of notes or of a bond is not a waiver of the right to file a lien: Kinsley v. Buchanan, 5 Watts, 118; Jones v. Shawhan, 4 W. & S. 257; Guckert v. Hacke et al., 159 Pa. 303; Dougherty & Co. v. Bash, 167 Pa. 429; Scott Manuf. Co. v. Morgan, 217 Pa. 367. In American Car and Foundry Co. v. Water Co., 221 Pa. 529, 537, we have: “As a general principle, the taking of the notes of the contractors for the amount due to the materialmen would not of itself effect a relinquishment of the right to file a lien. This was decided in Kinsley v. Buchanan, 5 Watts, 118, where it was said (page 119): 'Additional securities are in their nature cumula[526]*526tive; nor, where the parties have not expressly or impliedly so stipulated, is there any reason why the one should be a relinquishment of the other. Accordingly, it has been determined in one of the eases cited that acceptance of a bond is not an abandonment of a mechanic's lien. The case is in point and rules the present.’ To the same effect are Jones v. Shawhan, 4 W. & S. 257; Odd Fellows’ Hall v. Masser, 24 Pa. 507; Shaw v. Church, 39 Pa. 226; Noar v. Gill, 111 Pa. 488.” In 27 Cyc., 276, the principle is stated: “The fact that one who furnishes materials for improvements on land retains the ■ title to the materials until they are paid for does not deprive him of the right to a mechanic’s lien.” In The Pearl, 189 Fed. Repr. 540, we have (page 542): “It is settled that the retention of title to the engine until the debt was paid does not prevent the statutory lien from attaching. In C. & A. R. R. Co. v. Union Rolling Mills Co., 109 U. S. 702, 721, 3 Sup. Ct. 594, 27 Law Ed., 1081, this contention was made. The court quotes with approval this language from the Supreme Court of Illinois in Clark v. Moore, 64 Ill. 270: ‘The lien (statutory lien) attaches to and incumbers the property, to improve which the material is furnished, and the effort to acquire a more specific and exclusive lien thereon in no wise manifests an intention to release the property from all liens and look to other security for payment; but it shows the very opposite intention; an intention to hold, if possible, the property liable for the payment of their claim:’ 20 Am. & Eng. Ency. of Law, 500; 27 Cyc., 276; The Thomas Morgan (D. C.), 123 Fed. Repr. 781.” Also, in M. A. Phelps Lumber Co. v. McDonough Manuf. Co., 202 Fed. Repr. 445, a case of a mechanic’s lien, we have (pages 447 and 448): “It is contended that the appellee waived the right to claim a mechanic’s lien by inserting in the contract the condition that the machinery and property supplied should remain its property until fully paid for. To sustain their contention, counsel cite authorities to the proposition that by agreement between the parties personal property may be made to retain its character as such, notwithstanding that it be attached to the realty, and that such an agreement may be implied from a conditional sale, and decisions are cited which determine the respective rights of the contracting parties and third persons as to property so conditionally sold and attached to real estate. Those authorities are all aside from the question which is before us. The question here is whether the appellee’s right to claim a mechanic's lien has been waived by the terms of the contract. The authorities are uniform in holding that such a condition in a contract is but additional security to the vendor, and does not in any way affect his right to claim a mechanic’s lien upon the machinery and the property to which it may have become attached as part thereof: Hooven, Owens & Rentschler Co. v. John Featherstone’s Sons, 111 Fed. Repr. 81, 49 C. C. A. 229; Salt Lake Hardware Co. v. Chainman Min. & Elec. Co. (C. C.), 128 Fed. Repr. 509; Case Manuf. Co. v. Smith (C. C.), 40 Fed. Repr. 339, 5 L. R. A. 231; C. & A. R. R. Co. v. Union Rolling Mill Co., 109 U. S. 702, 3 Sup. Ct. 594, 27 Law Ed., 1081; Cooper v. Cleghorn, 50 Wis. 113, 6 N. W. Repr. 491.”

The plaintiffs, by the insertion in the clause of their agreement to retain title to the machinery, cannot, prima facie, be said to have waived their right to file a mechanic’s lien.

The second reason assigned by defendant why the lien be stricken off is that the claim is defective upon its face, in that it affirmatively appears therein that the only new erection by the defendant was a three-story brick factory building having a frontage of 100 feet, with a uniform width of 40 feet, while the lien is claimed and filed not only against this new structure and the lot of ground immediately appurtenant thereto, but against the fol[527]*527lowing additional older buildings, namely, a three-story brick building, 61 feet by 86 feet 6 inches; a three-story brick building, 16 feet by 20 feet; a one-story iron building, 21 feet by 21 feet 6 inches; a two-story frame building, 14 feet by 18 feet; a one-story brick building, 12 feet by 84 feet, and a one-story brick building, 20 feet by 60 feet.

The mechanic’s lien filed shows that all of these buildings are upon a lot of ground on Thirteenth Street, Reading, Pa., having a frontage on Thirteenth Street of 141 feet and a depth eastward along Muhlenberg Street of 180 feet, more or less. The claim also specifically states that this new brick building, three stories in height, 110 feet in length and 40 feet in width, is used, in connection with the other buildings of the defendant company, as an entire hosiery plant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chicago & Alton Railroad v. Union Rolling Mill Co.
109 U.S. 702 (Supreme Court, 1884)
Lauman's Appeal
8 Pa. 473 (Supreme Court of Pennsylvania, 1848)
Odd Fellows' Hall v. Masser
24 Pa. 507 (Supreme Court of Pennsylvania, 1855)
Nelson v. Campbell
28 Pa. 156 (Supreme Court of Pennsylvania, 1857)
Shaw & Leigh v. First Associated Reformed Presbyterian Church
39 Pa. 226 (Supreme Court of Pennsylvania, 1861)
Noar v. Gill
4 A. 552 (Supreme Court of Pennsylvania, 1886)
Short v. Miller & Co.
14 A. 374 (Supreme Court of Pennsylvania, 1888)
Short v. Ames
15 A. 607 (Supreme Court of Pennsylvania, 1888)
Linden Steel Co. v. Imperial Ref. Co.
20 A. 867 (Supreme Court of Pennsylvania, 1890)
Linden Steel Co. v. Rough Run Mfg. Co.
27 A. 895 (Supreme Court of Pennsylvania, 1893)
Guckert v. Hacke
28 A. 249 (Supreme Court of Pennsylvania, 1893)
H. D. Dougherty & Co. v. Bash
31 A. 729 (Supreme Court of Pennsylvania, 1895)
N. Green & Co. v. Thompson
33 A. 702 (Supreme Court of Pennsylvania, 1896)
Scott Manufacturing Co. v. Morgan
66 A. 566 (Supreme Court of Pennsylvania, 1907)
American Car & Foundry Co. v. Alexandria Water Co.
70 A. 867 (Supreme Court of Pennsylvania, 1908)
Todd v. Gernert
72 A. 249 (Supreme Court of Pennsylvania, 1909)
Wirsing v. Pennsylvania Hotel & Sanitarium Co.
75 A. 259 (Supreme Court of Pennsylvania, 1910)
Schively v. Radell
76 A. 209 (Supreme Court of Pennsylvania, 1910)
Union Savings & Building Ass'n v. Vahle
84 A. 407 (Supreme Court of Pennsylvania, 1912)
Kinsley v. Buchanan
5 Watts 118 (Supreme Court of Pennsylvania, 1836)

Cite This Page — Counsel Stack

Bluebook (online)
2 Pa. D. & C. 525, 1922 Pa. Dist. & Cnty. Dec. LEXIS 341, Counsel Stack Legal Research, https://law.counselstack.com/opinion/seibert-v-glasser-hosiery-co-pactcomplberks-1922.