Day & Zimmermann, Inc. v. Blocked Iron Corp. of America

15 Pa. D. & C.2d 251, 1958 Pa. Dist. & Cnty. Dec. LEXIS 296
CourtPennsylvania Court of Common Pleas, Philadelphia County
DecidedAugust 6, 1958
Docketno. 156
StatusPublished
Cited by1 cases

This text of 15 Pa. D. & C.2d 251 (Day & Zimmermann, Inc. v. Blocked Iron Corp. of America) is published on Counsel Stack Legal Research, covering Pennsylvania Court of Common Pleas, Philadelphia County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Day & Zimmermann, Inc. v. Blocked Iron Corp. of America, 15 Pa. D. & C.2d 251, 1958 Pa. Dist. & Cnty. Dec. LEXIS 296 (Pa. Super. Ct. 1958).

Opinion

Waters, J.,

An appeal having been taken in the above-captioned matter, this opinion is filed in accordance with the mandate set forth in Supreme Court rule 43.

On October 11, 1957, plaintiff filed a mechanic’s lien against the interest of defendant as lessee of land occupied by defendant’s plant for the production of blocked iron. The lien purported to cover the plant as well as the land. Notice of the filing of the lien was given on October 14, 1957, by plaintiff to H. Francis DeLone, Esq., as attorney for defendant, and that notice was formally accepted by defendant’s counsel by letter dated November 1, 1957. On February 11, 1958, defendant filed a petition to strike the mechanic’s lien based on the fact that plaintiff did not file an affidavit of acceptance of notice of claim as required by [252]*252section 21 of the Mechanic’s Lien Act. of June 4, 1901, P. L. 431, as amended by.the Act of April 5, 1917, P. L. 42, sec. 1, 49 PS §131.

On February 17, 1958, without prejudice to its position that no affidavit was required by law, plaintiff filed an affidavit of acceptance of notice of mechanic’s lien setting forth the fact that notice was accepted by defendant’s attorney. On February 24, 1958, plaintiff also filed a petition for leave to file an amended statement of claim of mechanic’s lien.

It is unnecessary for us to further set forth the factual background and contract between the parties which formed the basis of this dispute, because we were of the opinion that the court was required to strike the lien as a result of plaintiff’s failure to file an affidavit of service as required by the Mechanic’s Lien Act.

Prior to 1917, section 21’of the Mechanic’s Lien Act provided as follows:

“Within one month after the filing of the claim, the claimant shall serve a notice upon the owner of the fact of the filing of the claim, giving the court, term and number and the date of filing thereof, and shall file of record in said proceedings an affidavit, setting forth the fact and manner of such service. A failure to serve such notice and file an affidavit thereof within the time specified, shall be sufficient ground for striking off the claim.”

In O’Kane v. Murray, 252 Pa. 60 (1916), the court discussed the requirements of section 21 of the Act of 1901. In that case, the operative fact was to the effect that no notice of the filing of a mechanic’s lien was served upon the owner but that notice was accepted by the owner’s attorneys. There was filed of record a copy of the notice of the filing of the lien with an endorsement of the acceptance of service by the owner’s attorneys. Mr. Justice Mestrezat stated on behalf of a unanimous, court the following, at pages 67-69:

[253]*253■ “Section 21, of .the Act .of 1901, requires the claimant within one month after the filing of the claim to serve a notice upon the owner of the fact of the filing of the same, .and to file of record in the proceedings an affidavit, setting forth the fact and manner of such service.- This section also provides that a failure to serve the notice and file the affidavit within the specified time shall be sufficient ground for striking off the claim..The notice of the filing of the claim was not given to Murray, but service of the notice was accepted by his attorneys. The plaintiff contends that a substantial conformance with this section of the statute is all that is required, and that the section will not be construed to be mandatory unless it would be inequitable to allow the lien to remain. This contention entirely overlooks the well established rules applicable to the interpretation of mechanic’s liens. The language of the provision is clearly mandatory and if the claimant fails to serve the notice and file the required affidavit, within one month after the filing of the claim, it is ground for striking off the claim. A compliance with the provision is a prerequisite to the validity of the lien, and the failure to observe it invalidates the lien. The purpose of the provision is apparent. It is to protect the owner by furnishing him an opportunity while the facts are accessible to ascertain if the claim is correct, if the labor and materials were furnished as set forth in the lien, and if the claim has been properly and legally entered so as to bind his real estate. In -a large building operation there may be many parties entitled to file claims, and it is important to the owner that the several claimants give him the notice required by the statute. The manifest importance of the provision clearly shows that the legislature intended it- should be mandatory, and the failure to comply with it should invalidate the lien. The right to file' a mechanic’s lien, as has been' uni[254]*254formly held by all the courts, is of statutory origin. No such right existed at common law. It is class legislation and, therefore, must be strictly construed. If a party desires to avail himself of it, he must comply strictly with the provisions of the statute conferring the right. Nothing is presumed in favor of the lien: Schively v. Radell, 227 Pa. 434, 443. When the act of assembly directs specifically that a particular thing shall be done in order to establish a claim, substantial conformity will not answer; there must be a compliance with the requirement: Westmoreland Guarantee Bldg. & Loan Assn. v. Connor, 216 Pa. 543, 549. The notice directed to be given by this section of the statute is equally as important as the notice of an intention to file the lien required by Section 8 of the act, and in the recent case of Merrit v. Poli, 231 Pa. 611, 617, we held that ‘service of this notice must be made in the manner prescribed by the statute, and failure to do so defeats the right to recover upon the claim filed.’ Where service of the scire facias on the claim and to revive the judgment on the claim cannot be made personally, the act provides specifically the manner in which it may be otherwise made. The statute is explicit as to service of notice on the owner and directs that within the statutory period notice shall be given him, and that an affidavit shall be filed of record setting forth the fact and the manner of service of the notice. The penalty for failing to observe the command of the statute is, as the act provides, avoiding or striking off the lien and thereby depriving the claimant of the special provision made by the act for enforcing the claim. The act might have provided that notice be given the owner, his agent or attorney, or that notice might be served upon the owner by leaving a copy at his residence, or that service of notice might be accepted by his agent or attorney, as provided in serving the scire facias, but the only department of the government, [255]*255having the authority to enact the legislation, has not seen proper to make such provision for service of the notice to the owner of property encumbered by the lien, and that is conclusive as to our right to determine that the notice shall be given otherwise than is specifically directed in the statute. We can have no concern with the wisdom or propriety of this or any other provision of the statute; that is solely for the legislative department of the government.

“Analogous provisions in statutes of other states authorizing the filing of mechanic’s claims have received a like construction: Street Lumber Co. v. Sullivan, 201 Mass. 484; Gross v. Butler, 72 Ga. 187; Conway & Co. v. Crook, 66 Md. 292; Peck v. Hinds, 68 Ill. App. 391; Ryan v. Kelly, 9 Mo. App. 396; Hannah & Lay Mercantile Co. v. Mosser, 105 Mich. 18.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Day & Zimmermann, Inc. v. Blocked Iron Corp. of America
147 A.2d 332 (Supreme Court of Pennsylvania, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
15 Pa. D. & C.2d 251, 1958 Pa. Dist. & Cnty. Dec. LEXIS 296, Counsel Stack Legal Research, https://law.counselstack.com/opinion/day-zimmermann-inc-v-blocked-iron-corp-of-america-pactcomplphilad-1958.