Schindler Elevator Corp. v. Long Property Holdings, L.L.C.

182 So. 3d 233, 2015 La. App. LEXIS 2284, 2015 WL 7280622
CourtLouisiana Court of Appeal
DecidedNovember 18, 2015
DocketNo. 50,199-CA
StatusPublished
Cited by11 cases

This text of 182 So. 3d 233 (Schindler Elevator Corp. v. Long Property Holdings, L.L.C.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Schindler Elevator Corp. v. Long Property Holdings, L.L.C., 182 So. 3d 233, 2015 La. App. LEXIS 2284, 2015 WL 7280622 (La. Ct. App. 2015).

Opinion

CALLOWAY, J., Pro Tempore.

.. |, Schindler Elevator Corp. (“Schindler”) appeals a judgment denying its claim for breach of contract against Long Property Holdings, LLC, a business entity whose sole member is Michael D. Long (both generally referred to together hereafter as “Long”), and ordering it to pay Long’s attorney fees as required by a prevailing party clause in the contract between the parties. Long answers the appeal to assert error as‘to the trial court’s denial of its reconventional demand for rescission of the contract 'and other relief. Long also seeks additional attorney fees for the appeal. Finding no error and for the reasons explained infra, we affirm the trial court’s judgment and pretermit consideration of Long’s answer, 'except to award additional attorney ‘ fees for this appeal.

FACTS

In December 2008, Long purchased a two-story office building in Marshall, Texas. The building was equipped with a two-stop, Dover hydraulic elevator. Schindler was under contract with the building’s pri- or owner, D.H. Snyder (“Snyder”), to provide periodic preventive maintenance for the elevator. The- Schindler-Snyder contract was for a five-year term from June 1, 2005,- through May 31, 2010, and it contained the following clause:

5/ You will ’assign this Agreement to your successor in interest, should your interest in the premises cease prior to the initial or any ’renewal termination date. If this Agreement is terminated prematurely for any reason, other than • our default, including failure to assign to a: successor in interest as required above, you’will pay as liquidated damages (but not penalty) one/half the remaining amount due under this Agreement.

[236]*236UUpon the sale of the property, Snyder forwarded to Long the quarterly invoice in the amount of $561.97 for Schindler’s services from December 1, 2008, through February 28, 2009. Long paid the invoice.

On February 10, 2009, Long wrote to Larry Hammond (“Hammond”), Schindler’s branch manager, .asking him to update Schindler’s records to reflect the change in the building’s ownership. The fetter included 'Long’s contact information. It also identified David Little (“Little”) as the new property manager for the building, included' Little’s cell phone number, and stated that he would be Schindler’s “contact for onsite service visits.”

Hammond forwarded Long’s, letter to Ryan Gold, a Schindler sales representative and account manager, who then contacted Long for the purpose of having him sign a new contract. In an email on February 13, 2009, Gold forwarded a proposal for a new elevator maintenance agreement. Gold’s email refers to the proposal as being “the same in scope as what is currently in effect.” The only difference mentioned was a small decrease in price with Long paying quarterly installments of $590.19 per month, whereas Snyder paid $591.72. It appears from the email that the proposed contract was attached. Long replied that he would get back with -Gold after reviewing “this.”. He also requested a service history for the elevator, which Gold forwarded along with an explanation of Schindler’s “ScoreCard,” an online tool that provides 12 months of service history for Schindler customers’.

Long emailed Gold on February 16, 2009, because he noticed that the contract forwarded by Gold was -missing the third page; this was the pagel «that set forth the term of the contract. Gold replied that the pages must have stuck together, and he ■ sent- the complete contract. Long signed the contract on February 17, 2009. Although the Schindler-Snyder contract had been for a term of five years,, the contract signed by .Long was for a 10-year term.

■ In July 2009, Long reported a problem with the elevator door. John Dixon, a Schindler technician,- corrected the problem on- July 31, 2009, and Little signed the work report on behalf of Long. Thén, in August 2009,: Long noticed that the permit for the elevator had expired. In an email on August 25, 2009, Long asked Gold, “Is an inspection required 'to get a current permit or what is the procedure?” Gold' sent the following reply on August 26, 2009: ⅝.

In Texas every elevator is required to be tested annually and certified by a state inspector and the state issues the certificate. The inspector will contact us to let us know, when he’ll be in the area to do testing. -We’ll coordinate with him to do the testing while he’s present. Upon completion (if the elevator passes) you can purchase a certificate from the inspector.
In short, don’t worry about the certificate. Once the inspector get ’ [sic] in touch with us[,] we’ll make sure to inform you and well be able to go from there.

The elevator was finally inspected in December 2010, when Long made the arrangements after Schindler failed to do as stated in Gold’s email.

After paying Schindler’s December 2010 quarterly invoice in the amount of $638.98, Long discussed with Gold his dissatisfaction with Schindler’s services and told Gold in February 2011 that its relationship with Schindler was over. Gold did not object. Long ceased further payments. Schindler continued to send invoices to Long, and then sent him a default letter on August 11, 2011. The letter stated that Long was in ^default for nonpayment of invoices in [237]*237the amount of $1,346.46, and that the contract would be canceled 10 days from receipt of the letter. Referring to the liquidated damages provision, Schindler offered to. settle the matter for payment of pne-half due under the contract ,($11,517.47) in lieu of legal action. Schindler sent a second default letter on October 19,2011.

On March 14, 2013, Schindler filed suit against Long in Shreveport City Court seeking a balance of $11,563,85, plus interest, costs, and attorney fees as provided for in the contract. The suit was transferred to the First Judicial District Court on Long’s motion. In answer, Long asserted numerous affirmative defenses and a multi-count reconventional demand seeking rescission of the contract, damages, and attorney fees. Long asserted that the parties had agreed to a five-year term for the contract but that Schindler inserted a 10-year term in the final version, that Schindler failed to take care of the elevator inspection after saying it would do so, that Schindler misled it to believe there was no time left tinder Snyder’s contract, and that Schindler falsely claimed to have been providing maintenance services. In an amended answer, Long asserted that Schindler’s claim for stipulated damages was barred because the parties had terminated the contract.

In answer to Long’s reconventional demand, Schindler asserted that Long made a reasonable business decision to enter a new contract at a more favorable rate, rather than to assume the Snyder contract, and that Long was aware of the 10-year term as indicated by his initiating the page containing the term and signing the contract.

|KAt trial, the court heard testimony from Long; Ryan Bollinger (“Bollinger”), a Schindler service technician; Hammond; and William Calhoun, Bollinger’s supervisor at Schindler. In lieu of live testimony, the depositions of Gold, Little, and Stephen Jones (“Jones”), the property manager of the building prior ,to its purchase by Long, were entered.into evidence.

Regarding how Long came to enter a new contract with Schindler, Long claimed he did not know he could continue under the Schindler-Snyder contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
182 So. 3d 233, 2015 La. App. LEXIS 2284, 2015 WL 7280622, Counsel Stack Legal Research, https://law.counselstack.com/opinion/schindler-elevator-corp-v-long-property-holdings-llc-lactapp-2015.