Schillinger Bros. v. Smith

80 N.E. 65, 225 Ill. 74
CourtIllinois Supreme Court
DecidedDecember 22, 1906
StatusPublished
Cited by20 cases

This text of 80 N.E. 65 (Schillinger Bros. v. Smith) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Schillinger Bros. v. Smith, 80 N.E. 65, 225 Ill. 74 (Ill. 1906).

Opinion

Mr. Justice Cartwright

delivered the opinion of the court:

Ernst E. Smith, defendant in error, a brick-layer employed by Schillinger Bros. Company, a corporation, plaintiff in error, while engaged in laying a wall of fireproof tile was injured by the falling of a scaffold provided for him to work upon, and he sued plaintiff in error to recover damages for his injuries. He charged in the various counts of his declaration that the scaffold was unsafe and plaintiff in error was guilty of negligence in furnishing it for his use; that the scaffold was overloaded by other agents and servants of plaintiff in error who were not his fellow-servants, and that he went upon the scaffold by the direction of defendant’s foreman. The plea was the general issue, and upon a trial a verdict of guilty and assessing damages was returned, upon which judgment was entered. An appeal was taken to the Appellate Court for the Second District, where the judgment was affirmed, and a writ of error was then sued out from this court to review .the judgment of the Appellate Court.

The trial court refused to direct a verdict of not guilty, and the refusal is assigned as error. It was proved, and is not now denied, that the defendant was guilty of negligence in the construction of the scaffold. Plaintiff, with others, had been setting tile in the wall, and when the wall became too high to lay the tile from the floor they were laid from a scaffold fifty feet long, with a platform on top five or six feet wide, resting on wooden horses. The scaffold, at the time of the accident, was fourteen feet high, and had been raised as the work progressed. The horses were thirteen feet apart, and two of them near the middle section had originally been but ten feet high and had been raised by nailing one-inch boards on the legs at the bottom. The boards were old, rotten and knotty and were unfit for the purpose, and were nailed on the legs with small six-penny nails, which were insufficient for such use. On the morning of the accident plaintiff arrived at the building somewhat late. The other men had placed a large quantity of tile on the platform from the floor above for the brick-layers to work with, and there was a mortar board and three men on the platform. When plaintiff came in, Mueller, one of the tile-setters, said that plaintiff was late and asked him what was the matter. Plaintiff said that he had been telephoning his brother, and after changing his clothes asked Mueller where they were going to start, and Mueller replied, “Right on top here.” Mueller started up a ladder to the platform and plaintiff followed him. Mueller turned one way and the plaintiff the other, and plaintiff reached under the mortar board for his trowel. As he was straightening himself up the scaffold fell and he was injured.

It is contended that the court ought to have directed a verdict of not guilty because the plaintiff knew the condition of the scaffold and the amount of tile upon it, and therefore assumed the risk of its falling, and also for the reason that the proximate cause of the accident was not the insufficiency of the scaffold, but the overloading of it with tile by Mueller, whp is alleged to have been a fellow-servant. When one person enters the service of another he necessarily has in view the risks ordinarily connected with such service, and by his contract of employment he assumes such risks. If he receives an injury from the incidental risks and hazards ordinarily connected with the employment he cannot hold the master responsible. In entering upon the service he has a right to assume that the master will perform the duties imposed upon him, and the original contract of employment does not include any assumption by the servant of risks or dangers due to a failure of the master to perform such duties. Among the personal duties of the master is the duty to use reasonable care to furnish the servant with a reasonably safe place in which to work. The servant may assume that the duty has been performed unless he is chargeable with notice that it has not been. He cannot assume that the place provided for him to work is reasonably safe when he knows the contrary, and if there are defects which are obvious to a person of ordinary intelligence he will be charged with a knowledge of such defects and the risk and danger arising therefrom. In such a case he assumes all risk of injury from the defect by voluntarily continuing in the service. (Chicago and Eastern Illinois Railroad Co. v. Kneirim, 152 Ill. 458; East St. Louis Ice, etc. Co. v. Crow, 155 id. 74; Armour v. Brazeau, 191 id. 117; Browne v. Siegel, Cooper & Co. id. 226.) In this case the defendant had been guilty of negligence in furnishing an unsafe scaffold, and the plaintiff did not assume the risk arising therefrom unless he was chargeable with notice of the unsafe condition of the scaffold and the weight that had been placed upon it. Plaintiff was not at work the previous day when the horses were spliced, and testified that he noticed the scaffold was up and it looked like any other scaffold, and that he was ignorant both of its condition and of the weight upon it. He also testified that he could not see from the floor level how many tile were on the platform, and his testimony must be taken as true on the motion to direct a verdict. If he had examined the boards with which the legs were spliced, he, of course, would have discovered that they were rotten and unfit for the purpose, but he could not have known that the nails were small and insufficient. He pame in late, changed his clothing in a hurry and followed Mueller up the ladder, when the platform immediately fell. The court could not say, as a matter of law, that the plaintiff knew, or ought to have known, that the scaffold was unfit for the use for which it was intended or that it would not support the weight that was on it in safety.

It is next contended that the court ought to have directed a verdict on the ground that the proximate cause of the falling of the scaffold was that it had been overloaded by a fellow-servant. It would make no difference in the liability of the defendant if the negligence of a fellow-servant of the plaintiff combined with the proved negligence of the defendant, and to justify the court in directing a verdict it would have been necessary to first find that the scaffold was fit for the ordinary uses to which it was to be devoted. The court could not have done that, but, on the contrary, the evidence justified the conclusion that the scaffold would not have fallen if it had been fit for the use for which it was intended. Doubtless it would not have fallen if there had been no more weight upon it than such a scaffold would support. Counsel on one side contend that the tile was placed on the platform by Mueller as a fellow-servant, while it is insisted on the other side that Mueller was a vice-principal, for whose acts the defendant was responsible. The evidence for the plaintiff was that Mueller superintended the work and controlled the other laborers, but the evidence for the defendant was that he was not a foreman or vested with any authority over the plaintiff or the other brick-layers. It is clear that he was not a vice-principal in the proper meaning of that term. Although a foreman, superintendent or other superior servant has sometimes been called a vice-principal, there is a clear distinction between the two. The question whether a servant is a vice-principal does not depend in any degree upon his rank or superior position or superintendence or control of other servants, but depends wholly upon the duties which he performs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Smado v. Crawford Manufacturing Co.
111 F.R.D. 415 (N.D. Illinois, 1986)
Geiken v. Chicago Great Western Railroad
6 N.E.2d 690 (Appellate Court of Illinois, 1937)
Craig v. Boudouris
241 Ill. App. 392 (Appellate Court of Illinois, 1926)
First National Bank v. Heeb
188 Ill. App. 194 (Appellate Court of Illinois, 1914)
Schumann v. Mealiff
178 Ill. App. 254 (Appellate Court of Illinois, 1913)
Farrell v. Illinois Tunnel Co.
177 Ill. App. 425 (Appellate Court of Illinois, 1913)
Leyda v. Kelly-Atkinson Co.
173 Ill. App. 115 (Appellate Court of Illinois, 1912)
Keefe v. Armour & Co.
171 Ill. App. 573 (Appellate Court of Illinois, 1912)
Miller v. Kenwood Bridge Co.
169 Ill. App. 404 (Appellate Court of Illinois, 1912)
Casey v. William Grace Co.
168 Ill. App. 488 (Appellate Court of Illinois, 1912)
Zoric v. Chicago City Railway Co.
165 Ill. App. 181 (Appellate Court of Illinois, 1911)
Asplund v. Conklin Construction Co.
165 Ill. App. 44 (Appellate Court of Illinois, 1911)
Bonato v. Peabody Coal Co.
94 N.E. 69 (Illinois Supreme Court, 1911)
Jacobson v. Duffy
154 Ill. App. 505 (Appellate Court of Illinois, 1910)
Bennett v. Chicago City Railway Co.
90 N.E. 735 (Illinois Supreme Court, 1909)
Crowder v. Chicago & Alton Railroad
145 Ill. App. 556 (Appellate Court of Illinois, 1908)
Peebles v. O'Gara Coal Co.
143 Ill. App. 370 (Appellate Court of Illinois, 1908)
Bonato v. Peabody Coal Co.
143 Ill. App. 163 (Appellate Court of Illinois, 1908)
Duffy v. Jacobson
135 Ill. App. 472 (Appellate Court of Illinois, 1907)
Chicago, Milwaukee & St. Paul Railway Co. v. Gill
132 Ill. App. 310 (Appellate Court of Illinois, 1907)

Cite This Page — Counsel Stack

Bluebook (online)
80 N.E. 65, 225 Ill. 74, Counsel Stack Legal Research, https://law.counselstack.com/opinion/schillinger-bros-v-smith-ill-1906.