SAS PARTNERSHIP, ETC. v. Schafer

653 P.2d 834, 200 Mont. 478, 1982 Mont. LEXIS 949
CourtMontana Supreme Court
DecidedOctober 4, 1982
Docket82-109
StatusPublished
Cited by13 cases

This text of 653 P.2d 834 (SAS PARTNERSHIP, ETC. v. Schafer) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
SAS PARTNERSHIP, ETC. v. Schafer, 653 P.2d 834, 200 Mont. 478, 1982 Mont. LEXIS 949 (Mo. 1982).

Opinion

MR. JUSTICE HARRISON

delivered the opinion of the Court.

This is a contract dispute on appeal from the Eleventh Judicial District in and for the County of Flathead. At the District Court the seller, SAS Partnership, sought to require the buyers, Fred and Gail Schafer, to pay an accelerated debt under a contract for deed. The District Court entered judgment against SAS. From that judgment SAS appeals. We reverse and remand.

On December 27, 1978, three parties entered into a real estate exchange agreement; SAS Partnership, the Schafers, and Paul M. Jackson. Mr. Jackson is not a party to this action. SAS sold 3,000 feet of undeveloped lakefront property to Mr. Jackson who traded the property for other real estate then owned by the Schafers. Under the terms of the contracts, the Schafers were to pay SAS a total of $1.4 million; $350,000 as a downpayment, the balance to be paid in annual installments over a period of nine years at 8 !4 percent interest. At or before the closing the Schafers paid the $350,000 down payment and took possession to the present time. Within the first year the Schafers expended over $76,000 in improvements.

The first installment payment of $100,471 became due on December 27, 1979. The Schafers were unable to make the payment. On January 14, 1980, SAS sent a notice of default to the Schafers, and failing to receive payment, SAS sent another notice on February 26, 1980, demanding payment plus a penalty charge of $10,047. The Schafers could not meet their obligation and on March 14, 1980, SAS gave notice of default and an intent to accelerate the entire unpaid balance. On May 13,1980, the Schafers tendered the sum of $110,853 which represented the installment payment, the penalty charge, attorney’s fees, and an escrow charge. SAS refused Schafer’s tender and on May 22 filed the complaint with the District Court for specific performance; praying for *481 judgment of the entire balance of $1,050,000 plus interest, for the penalty of $10,047 plus interest, and for attorney’s fees and costs of suit. During the pendency of this action the second installment became due on December 27, 1980. No payment was made and SAS again sent default and acceleration notices.

The central issue at the District Court involved interpretation of the contract’s default clause. More specifically, as sub-issues, was SAS entitled to accelerate the payments, forcing the Schafers to immediately pay the outstanding balance of over $1,000,000; and, if SAS was within its contractual rights by demanding the entire balance, did it comply with the notice requirements of the contract?

The District Court found against SAS; however, the judgment ordered the Schafers to tender the 1979 and 1980 installments plus penalties and interest. The Schafers’ obligation to make tender under the judgment was conditional; if SAS made any post-trial motions or filed an appeal, the obligations would not attach. Accordingly, to the present time no installment payments have been made.

The appellant raises the following issues for our consideration:

1. Whether the District Court erred in consideration of principles of contract interpretation?

2. Whether the District Court erred by concluding that acceleration may be tantamount to forfeiture and since courts look with disfavor on forfeitures, the contract must be construed in favor of the Schafers?

3. Whether the District Court erred in concluding that the default notices were vague and premature?

4. Whether the District Court erred by not making findings and conclusions on various instances of default?

5. Whether the District Court erred in awarding attorney’s fees to the Schafers?

The first two issues are overlapping in that they question the District Court’s interpretation of the contract. We choose to discuss them as a single issue.

*482 Initially, we note that our scope of review is such that we may consider the contract language independently. It is true that contract ambiguities are questions of fact; Dooling v. Casey (1968), 152 Mont. 267, 448 P.2d 749; S-W Company v. Schwenk (1977), 173 Mont. 481, 568 P.2d 145. This Court stated in McNussen v. Graybeal (1965), 146 Mont. 173, 186, 405 P.2d 447, 454, “where there is a conflict of testimony as to what were the intentions of the parties toward the use of the ambiguous word, determination of the true meaning is one of fact. . .” Thus, we would ordinarily be limited to the “clearly erroneous” standard of review. Rule 52(a), M.R.Civ.P. However, it is also well settled that the initial determination of whether or not an ambiguity exists is one of law. McNussen, supra. “It is a question of law for the [District] Court to determine first as to whether there exists ambiguity sufficient to submit the question of intention to the trier of fact.” Schell v. Peters (1966), 147 Mont. 21, 27, 410 P.2d 152, 155. Thus, the determination by the District Court that the default clause was ambiguous is a conclusion of law freely reviewable by this Court. Martin v. United States (9th Cir. 1981), 649 F.2d 701; United States Fidelity v. Newman (9th Cir. 1981), 656 F.2d 457. We do not find ambiguity in the contract and rely on our own interpretation.

The entire case revolves around the default clause. The pertinent language reads:

“2. DEFAULT: In the event Purchaser fails or neglects to make any of the payments of principal or interest when due, or fails or neglects to perform any of the convenants Purchaser has agreed to perform, then Seller may, at their option, give a written Notice of Default, to Purchaser setting forth the default claimed by Seller. The Notice shall be sufficient if it describes the default in general terms.

“(a) If within 60 days of the date of service of said Notice of Default, the Purchaser corrects and makes good the payments and obligations then in default as set forth in said Notice, then Purchaser’s rights under this contract shall be *483 fully reinstated and this contract shall continue the same as if no default had occurred. Purchaser agrees to reimburse Seller for all legal expenses incurred by Seller in giving and serving the Notice of Default. The amount of such expense shall be specified in said Notice of Default and shall be paid by Purchaser at the time of correcting such default.

“(b) However, if the Purchaser fails or neglects to pay, correct, or make good such default, as set forth in said Notice, within 60 days from the date of service of said Notice, then, upon giving a further notice of 60 days, the Seller may.

“(1) Declare the entire unpaid balance due on the contract, including principal and interest, immediately due and payable.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kaufman Bros. v. Home Value Stores, Inc.
2012 MT 121 (Montana Supreme Court, 2012)
Hillabrand v. McDougal Trust
2004 MT 83N (Montana Supreme Court, 2004)
In Re the Marriage of Mease
2004 MT 59 (Montana Supreme Court, 2004)
Henderson v. Estate of Henderson
2002 MT 56N (Montana Supreme Court, 2002)
Pennington's Inc. v. Brown-Forman Corp.
785 F. Supp. 1412 (D. Montana, 1991)
Smith v. Johnson
798 P.2d 106 (Montana Supreme Court, 1990)
Felska v. Goulding
776 P.2d 530 (Montana Supreme Court, 1989)
Aveco Properties, Inc. v. Nicholson
747 P.2d 1358 (Montana Supreme Court, 1987)
Maxwell v. Sisters of Charity of Providence
645 F. Supp. 937 (D. Montana, 1986)
Schmidt v. Colonial Terrace Associates
694 P.2d 1340 (Montana Supreme Court, 1985)
Madsen v. Anderson
667 P.2d 44 (Utah Supreme Court, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
653 P.2d 834, 200 Mont. 478, 1982 Mont. LEXIS 949, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sas-partnership-etc-v-schafer-mont-1982.