Sarvis v. Cooper

665 N.E.2d 119, 40 Mass. App. Ct. 471, 1996 Mass. App. LEXIS 299
CourtMassachusetts Appeals Court
DecidedMay 23, 1996
DocketNo. 94-P-91
StatusPublished
Cited by13 cases

This text of 665 N.E.2d 119 (Sarvis v. Cooper) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sarvis v. Cooper, 665 N.E.2d 119, 40 Mass. App. Ct. 471, 1996 Mass. App. LEXIS 299 (Mass. Ct. App. 1996).

Opinion

Perretta, J.

On January 2, 1989, the plaintiff, Robert H. Sarvis, commissioned Able Marine Services, Inc. (AMS), to build a racing yacht, the Nantucket Splinter (Splinter).2 During construction of the Splinter, Able Marine Inc. (AMI), purchased AMS. AMI completed construction of the Splinter [472]*472and delivered it to Sarvis. On August 20, 1989, while in the final leg of her first race, the Splinter’s ballast keel parted from her hull. The yacht capsized and slowly turned upside down. The crew and Sarvis were rescued. Pursuant to his boat construction agreement with AMS, Sarvis submitted his claim to an arbitrator whose finding was to be final and binding. The arbitrator determined that the damage to the Splinter was the direct result of negligence in its construction and that there had been a breach of warranty. Before a judgment was entered in Superior Court against AMI on the arbitrator’s decision, AMI filed for bankruptcy. Sarvis purchased AMI’s indemnity rights under its purchase and sale agreement with AMS from the bankruptcy trustee and then, standing in AMI’s shoes, brought this action seeking indemnification from the defendants.3 On cross motions for summary judgment, a Superior Court judge concluded that AMI, and hence Sarvis, was entitled to be indemnified under a clause of the agreement which is subject to an aggregate limit of $100,000. On the parties’ cross appeals, we conclude that although the Superior Court judge, as matter of law, correctly construed the agreements between AMS and AMI, Sarvis is entitled to recover only if it is determined that, as matter of fact, the Splinter’s failure was caused by an act or omission of AMS. We, therefore, reverse the judgment.

1. The contract between Sarvis and AMS. It was agreed between the parties that AMS would construct the Splinter “in accordance with yacht building standards,” that the price was to be determined on a “cost plus basis,”4 that Sarvis would make periodic progress payments upon receipt of invoices, and that AMS would pay a penalty charge of $10,000 in the event work had not been completed by July 1, 1989. The parties further agreed that the drawings and designs for the Splinter were Sarvis’s sole property, as were certain reusable fixtures, tools, molds and other equipment constructed for the specific purpose of building the Splinter. As previously stated, disputes and claims relating to the work under the contract [473]*473were to be resolved by an arbitrator whose determination would be final and binding upon the parties.

2. The arbitrator’s decision. The arbitrator found that a failure to install floor timber bolts during the construction of the yacht caused the Splinter’s ballast keel to separate from her hull. He awarded Sarvis a total of almost $200,000 for the loss of his personal property on board, a tooling rebate, damages and shipment expenses on the yacht, the loss of its use, litigation expenses, and attorneys’ fees.

Although a judgment on the arbitrator’s decision was never obtained as to AMI, presumably because AMI filed for bankruptcy and triggered the automatic stay provision of 11 U.S.C. § 362 (a) (1988), there is a separate judgment confirming the award against AMS. The arbitrator’s decision is, therefore, final and binding upon Sarvis and AMS. See Glenn Acres, Inc. v. Cliffwood Corp., 353 Mass. 150, 156 (1967) (“G. L. c. 251, §§ 11 and 14, contemplate that the finality of an arbitrator’s award is subject to and dependent upon the entry of a judgment or decree by the court”).

3. AMI’s right to be indemnified by AMS. After purchasing AMI’s indemnity rights from its trustee in bankruptcy, Sarvis brought this action against the defendants, see note 3, supra, seeking indemnification under the asset purchase agreement between AMS and AMI, as well as under a side agreement. We take up the asset purchase agreement first. Section 7.2 of that agreement requires AMS to indemnify AMI against any liability resulting from claims set out in six categories, the following two of which are here at issue:

“(i) Any and all obligations or liabilities of any of the Selling Parties which are not, by the express terms hereof, to be assumed by Buyer;
“(vi) Any and all warranty, product liability, personal injury and death claims made against Buyer or related liabilities in connection with any products sold or services provided since the inception of the Business and prior to the Closing” (emphasis supplied).

Section 7.3 of the agreement limited the indemnification provided by § 7.2 (vi) to “$100,000 in the aggregate.”

[474]*474Under the side agreement, AMS warranted that the Splinter would be timely completed so that the $10,000 late-delivery penalty provided for in the contract with Sarvis would not be incurred. AMS also agreed to indemnify AMI up to fifty per cent of any amounts due from Sarvis but compromised by AMI because of budget overruns. Any monies paid by AMS under the side agreement were not to be applied against the $100,000 limit set out in § 7.3 of the asset purchase agreement. Sarvis seeks to exercise AMI’s rights under the side agreement on the basis of his claim that he paid AMI $32,108.80 less than billed on account of the $10,000 penalty due for the late delivery of the Splinter and for budget overruns in the amount of $22,108.80.

The primary issue raised on the cross motions for summary judgment and the cross appeals is whether AMI’s right to be indemnified for the damages and expenses pertaining to the Splinter is found in § 7.2 (i), as Sarvis argues, or in § 7.2 (vi), if at all, as the Coopers contend. The Superior Court judge determined that because AMI expressly had assumed all AMS’s obligations and liabilities in respect to the Splinter, AMI’s right to indemnification was under § 7.2 (vi) as limited by § 7.3. The decision makes no mention of specific claims under the side agreement and the amounts sought thereunder, and Sarvis pursues those claims on his appeal.

4. Interpretation of the asset purchase agreement.5 In concluding that AMI had assumed all the obligations and liabilities pertaining to the Splinter, the Superior Court judge relied upon § 3.4 of the asset purchase agreement which, as relevant, provides:

“Buyer hereby assumes and agrees to pay and perform, promptly when due, all of Seller’s liabilities and obligations under and pursuant to the following:
(a) The Unfilled Orders set forth in the schedule described in Section 4.4 (r);
[paragraphs (b) through (g) omitted].”

Sarvis cannot and does not dispute that the Splinter is [475]*475specifically included in the schedule of unfilled orders set out in § 4.4 (r) of the agreement. He argues, however, that although AMI assumed liability for the Splinter under § 3.4, that assumption was thereafter limited by § 3.5 which states, in pertinent part:

“Notwithstanding anything to the contrary contained in Section 3.4 or otherwise in this Agreement, it is expressly agreed that Buyer will not be required to assume, and is not assuming, at the Closing any obligations or liabilities of Seller not specifically

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Walsh v. Massachusetts Highway Department
26 Mass. L. Rptr. 497 (Massachusetts Superior Court, 2010)
T.T.K., Inc. v. Columbia Speedway Plaza Member, LLC
26 Mass. L. Rptr. 235 (Massachusetts Superior Court, 2009)
Apthorp v. OneBeacon Insurance Group, LLC
25 Mass. L. Rptr. 284 (Massachusetts Superior Court, 2009)
Feldman v. Aspen Technology, Inc.
22 Mass. L. Rptr. 341 (Massachusetts Superior Court, 2007)
Alfeo v. Dinsmore
861 N.E.2d 491 (Massachusetts Appeals Court, 2007)
White City Shopping Center v. PR Restaurants, LLC
21 Mass. L. Rptr. 565 (Massachusetts Superior Court, 2006)
Bina v. Marks
20 Mass. L. Rptr. 434 (Massachusetts Superior Court, 2006)
Kelley v. Dolben
12 Mass. L. Rptr. 509 (Massachusetts Superior Court, 2000)
Dominic Gentile Painting Co. v. Aulson Co.
2000 Mass. App. Div. 19 (Mass. Dist. Ct., App. Div., 2000)
National Lumber Co. v. Fort Realty Corp.
1999 Mass. App. Div. 235 (Mass. Dist. Ct., App. Div., 1999)
Zortman v. Bildman
10 Mass. L. Rptr. 76 (Massachusetts Superior Court, 1999)
Flatte v. Carifio
1997 Mass. App. Div. 89 (Mass. Dist. Ct., App. Div., 1997)
Cambridge Electric Light Co. v. SESCO, Inc.
7 Mass. L. Rptr. 83 (Massachusetts Superior Court, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
665 N.E.2d 119, 40 Mass. App. Ct. 471, 1996 Mass. App. LEXIS 299, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sarvis-v-cooper-massappct-1996.