Santa Monica Baykeeper v. City of Malibu

193 Cal. App. 4th 1538, 124 Cal. Rptr. 3d 382, 41 Envtl. L. Rep. (Envtl. Law Inst.) 20137, 2011 Cal. App. LEXIS 388
CourtCalifornia Court of Appeal
DecidedApril 5, 2011
DocketNo. B222776
StatusPublished
Cited by36 cases

This text of 193 Cal. App. 4th 1538 (Santa Monica Baykeeper v. City of Malibu) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Santa Monica Baykeeper v. City of Malibu, 193 Cal. App. 4th 1538, 124 Cal. Rptr. 3d 382, 41 Envtl. L. Rep. (Envtl. Law Inst.) 20137, 2011 Cal. App. LEXIS 388 (Cal. Ct. App. 2011).

Opinion

Opinion

EPSTEIN, P. J.

Santa Monica Baykeeper (Baykeeper), a nonprofit corporation, appeals from the denial of its petition for writ of mandate. Its suit challenged the City of Malibu’s (City) adoption of an environmental impact report (EIR) and approval of the Legacy Park project in Malibu, California. The suit was brought pursuant to the California Environmental Quality Act. (Pub. Resources Code, § 21000 et seq.; CEQA.) Baykeeper argues the EIR failed to adequately analyze (1) construction-related water quality impacts; (2) the impact of using treated effluent from the adjoining Malibu Lumber Yard project on the project site; and (3) the cumulative groundwater impacts of the project.

City argues that the appeal is moot and should be dismissed on that ground. We agree that it is moot as to Baykeeper’s challenge regarding construction-related impacts because the project was completed during the pendency of this appeal and no recognized exception to the mootness doctrine applies to warrant discretionary review of that issue. The other issues in the appeal are not moot. But the conclusions in the final EIR regarding the [1542]*1542impact of using treated effluent from the adjoining Lumber Yard project are supported by substantial evidence, and as to these, Baykeeper has failed to demonstrate a prejudicial abuse of discretion warranting reversal. We also find substantial evidence supporting City’s conclusion that the Legacy Park project reduces rather than creates groundwater impacts and therefore no cumulative groundwater impacts analysis was required. The judgment is affirmed.

FACTUAL AND PROCEDURAL SUMMARY

A. Project Description

Malibu Creek is the primary drainage artery of a 110-square-mile watershed. It is subject to water quality impairments caused by stormwater runoff, dry-weather runoff, animal waste, and the potential that onsite wastewater treatment systems (OWTS) may fail. Malibu Creek, Malibu Lagoon, and Surfrider Beach are on the Clean Water Act of 1977’s1 list of impaired water bodies for bacteria and nutrients. After a number of studies and risk assessments conducted starting in 2000, the City decided to address water quality problems associated with urban stormwater runoff and the potentially failing onsite wastewater systems in the civic center area (340 acres in the central part of the City). The Legacy Park project site (site) is described in the final EIR as 15 acres in the Malibu Civic Center (Civic Center), “at the terminus of the Malibu Creek watershed where Malibu Creek drains into Malibu Lagoon, which periodically discharges to Surfrider Beach when the berm separating the Lagoon from the ocean is breached.”2

The Malibu Lumber Yard commercial project is on the eastern side of the site. It was approved in August 2007 and included construction of an 85,600-square-foot dispersal field within the Legacy Park site to which treated wastewater effluent from the Lumber Yard was to be discharged.3 There were no challenges to the Lumber Yard project approvals. As part of the Legacy Park project, for 10 months of the year all of the Lumber Yard effluent is expected to be used to irrigate vegetation at Legacy Park. During [1543]*1543December and January, it is anticipated that excess treated Lumber Yard effluent not needed for Legacy Park irrigation will be discharged directly to Malibu Creek. A key issue in this appeal is whether this use of the Lumber Yard treated effluent will have an impact on groundwater as a result of its use for irrigation of Legacy Park.

As originally conceived, the Legacy Park project had four primary elements: “1) stormwater detention and treatment, 2) habitat restoration, 3) public park, and 4) wastewater treatment and reuse.” The draft EIR explained: “Although different drivers exist for each of the four elements for the proposed project, the overall purpose of the proposed project is to provide an integrated plan for the Civic Center area that would protect water quality at nearby beaches and the Lagoon from nitrogen and pathogenic degradation and provide opportunities for restoration of native/sensitive habitats and public recreation.”

The stormwater treatment element of the project includes collection of stormwater in an eight-acre-foot detention pond which occupies three to four acres of the Legacy Park site. The pond would be lined with clay to prevent infiltration into the groundwater. The detention pond would operate in conjunction with a preexisting stormwater treatment facility. It will hold 2.6 million gallons of stormwater. If a rainstorm occurs and the pond is full, excess stormwater will flow from the pond to the treatment plant. If it continues to rain after treatment is complete, the water will be discharged to Malibu Creek, but will meet the bacteria TMDL.4 If the rain stops, the flow will go from the pond to the treatment plant and back to the pond to irrigate the park. The plan is to drain the top four acre feet quickly, treat it, and discharge it into the creek. The bottom four acre feet would either be drained, treated and discharged, or treated and used for irrigation of the park. The detention pond would allow the City to achieve water quality that is, on average, five times greater than that required by the standards for bacterial contamination (bacteria TMDL), and is expected to reduce the number of exceedances to three per year.

The park element includes both the primary Legacy Park site and a 20-foot strip of land just north of Civic Center Way, designated “Linear Park.” Legacy Park would allow passive recreation with meandering trails and pathways through various habitats. Educational centers and interpretative areas would be provided. Linear Park would include vegetation and drainage improvements to collect stormwater and convey it to Legacy Park for detention. The habitat restoration element includes coastal prairies, coastal' bluffs, Southern California native woodlands, and riparian/wetland habitat. The goals for these habitats are to increase the amount of wetland, increase [1544]*1544the amount of regionally rare habitat, provide biodiversity support, contribute to “habitat mosaic/connectivity,” provide sustainable natural habitat, replace original habitats, and increase regional biodiversity.

As we shall discuss, the original element of a wastewater system was eliminated when further investigation established the site could not accommodate that plan.

B. Administrative Process

Preparation of the project began in January 2007. In conformity with the requirements of section 15063 of the State CEQA Guidelines5 (Cal. Code Regs., tit. 14), a notice of preparation was prepared and distributed in late 2007. This notice presented a description of the proposed project, potential environmental effects, instructions on how to comment, and notice of a public scoping meeting. The public review period for the notice of preparation ended on December 13, 2007. The public scoping meeting was held at Malibu City Hall on December 5, 2007, where an overview and history of the project was provided with a description of CEQA requirements. A number of potentially significant impacts were identified, and it was determined that an EIR would be appropriate to address these potential impacts.

A draft EIR was prepared and circulated for public review and comment from May through July 2008.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vichy Springs Resort, Inc. v. City of Ukiah
California Court of Appeal, 2024
Marriage of Inna and Roman A. CA2/3
California Court of Appeal, 2022
Torres v. City of Visalia CA5
California Court of Appeal, 2022
Dept. of Water Resources Cases
California Court of Appeal, 2021
Villanueva v. Becerra CA5
California Court of Appeal, 2021
Amgen Inc. v. Health Care Services
California Court of Appeal, 2020
Living Rivers Council v. State Water Res. Control Bd.
223 Cal. Rptr. 3d 703 (California Court of Appeals, 5th District, 2017)
Residents Against Specific Plan 380 v. County of Riverside
9 Cal. App. 5th 941 (California Court of Appeal, 2017)
Save Atascadero v. City of Atascadero CA2/6
California Court of Appeal, 2014

Cite This Page — Counsel Stack

Bluebook (online)
193 Cal. App. 4th 1538, 124 Cal. Rptr. 3d 382, 41 Envtl. L. Rep. (Envtl. Law Inst.) 20137, 2011 Cal. App. LEXIS 388, Counsel Stack Legal Research, https://law.counselstack.com/opinion/santa-monica-baykeeper-v-city-of-malibu-calctapp-2011.