Sanford Construction Co. v. S & H CONTRACTORS, INC.

443 S.W.2d 227, 1969 Ky. LEXIS 242
CourtCourt of Appeals of Kentucky (pre-1976)
DecidedJune 6, 1969
StatusPublished
Cited by46 cases

This text of 443 S.W.2d 227 (Sanford Construction Co. v. S & H CONTRACTORS, INC.) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky (pre-1976) primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sanford Construction Co. v. S & H CONTRACTORS, INC., 443 S.W.2d 227, 1969 Ky. LEXIS 242 (Ky. 1969).

Opinions

STEINFELD, Judge.

Appellant, Sanford Construction Company, Inc. (hereafter Sanford) was engaged as general contractor to develop land and construct a shopping center thereon. Sanford contracted with S & H Contractors, Inc. (hereinafter S & H) to excavate and grade the land. Claiming that Sanford fraudulently induced S & H to enter into the contract at a grossly inadequate price S & H sued Sanford and others for $125,000.00 damages in what S & H described as an “action in deceit” and as “founded on a tort involving misrepresentations as to the nature and extent of underlying rock at the shopping center site.” All defendants below except Sanford escaped liability, but on trial a jury returned a verdict against it in the amount of $75,-000.00. Motions for a new trial and for judgment notwithstanding the verdict were overruled and judgment was entered pursuant to the verdict. Sanford appeals.1 We affirm.

Forest City Enterprises, Inc., the owner, and Sanford engaged licensed experts to prepare plans and specifications for improvements of the site and construction of the building. A booklet entitled “Site Improvement Specifications for Bowling Green Mall at Bowling Green Kentucky” with the plans was delivered by David Wakser (an officer of Sanford) to various companies, including S & H, as an invitation to bid on the various phases of the project. The booklet and plans were prepared by Keeva J. Kekst and Ernest Ross, architects for Forest City Enterprises, Inc. and Sanford Construction Co. Among other things, the booklet contained a section entitled “Information to Bidders” which included the following:

“Bidders are required to satisfy themselves by personal examination of the contract documents and investigation at the site of the work as to the condition existing and the difficulties likely to be encountered in the construction of the work.
“No plea of ignorance of conditions that exist or that may hereafter exist, or of conditions or difficulties that may be encountered in the execution of the work as a result of failure to make such examination and investigation will be accepted as an excuse for any failure or omission on the part of the contractor to fulfill in every respect, all the requirements of the contract, nor will the same be accepted as a basis for any claim whatsoever for extra compensation, or for an extension of time.
“Bidders are required to verify all data to their satisfaction and to satisfy themselves as to the character of the material and conditions to be encountered. Owners and Engineers will not assume responsibility for exactness or interpretation of any subgrade data furnished.”
* * * * * *
“Neither the general contractor nor the Project Superintendent are to be responsible if, upon the completion of the work, the actual quantities are found to be greater or less than the estimated quantities. The Sub-Contractor shall make no claim for anticipated profits or loss of profits because of a difference between the actual and estimated quantities.”

Under the heading of general conditions two sections read:

“6 — RESPONSIBILITY OF THE CONTRACTOR
The Contractor shall take all responsibility for the work, shall bear all losses [230]*230resulting to him on account of the amount or character of the work, or from any unforeseen obstructions or difficulties which may be encountered, or because the nature of the land in or on which the work is done is different from what is assumed or was expected, or on account of the weather, floods or other causes; then he shall assume the defense of, and indemnify and save harmless the Owner from all claims of any kind arising from the performance of the Contract.”
“18 — ESTIMATED AND ACTUAL QUANTITIES
The estimated quantities of the various classes of work to be done under this Contract are approximate, and are for the purpose of comparing, on a uniform basis, the bids offered.
Neither the Owner nor the Engineer are to be held responsible if, upon the completion of the work, the actual quantities are found to be greater or less than the estimated quantities. The Contractor shall make no claim for anticipated profits or loss of profits because of a difference between actual and estimated quantities.”

“Detail provisions” stated: “If the bidder desires to obtain information as to soil conditions, the Owner will afford him an opportunity, at his own expense, to make borings or to dig test pits on the site of the work.” A section relating to “Grading and Excavating” provided:

“b. Sub-surface soil data: Subsurface investigations have been made and the results shown on the drawings. This information was obtained primarily for use in preparing the Foundation design, but the Grading Contractor may draw his own conclusions therefrom. No responsibility is or will be assumed by the Owner, General Contractor or Engineer for subsoil quality or conditions other than at the locations and at the time the exploration was made. No claim for extra compensation, or for extension of time, will be allowed on account of subsurface conditions inconsistent with the data shown, except as may be permitted elsewhere herein.”

Dallas Sandlin and Ray Hanser, officers of S & H, received the material from Wak-ser between Christmas 1965 and March 1966. They testified that as he handed it to them he stated: “ * * *. The plans and specifications have been spelled out for you; you got the borings indicating your rock elevations; you got a complete picture of the work to be done, and this is all you need to complete the job. We would like a price on it at your convenience.” At the same time he said: “ * * * that all the information that [S & H] needed to calculate any subsoil rock that was to be encountered could be calculated from the plans, in fact, was all [S & H] needed to calculate the job.” Also “Here’s the plans and specifications to do the Bowling Green Mall by. You boys will not have nothing to worry about. Everything will be all laid out for you to do the job by.” The plans indicated that boring had been made over only part of the land and in a grid pattern at 100 foot intervals. The soil profile lines of the area explored showed the depth of the borings. No tests had been made in certain areas where there were visible rock outcroppings but the plans required that cuts be made at those places.

From those plans S & H originally estimated for Sanford that it could do the work for $94,000.00. Later it began a site investigation which included a ground inspection of the entire area during which it observed rock outcroppings. It used a backhoe for exploration purposes in the area which the plans showed had not been bored and possibly in other areas. With a rod it probed in various places. It discovered larger quantities of subsurface rock than it had anticipated. On May 18, 1966, it contracted to do the work for $104,000.00 agreeing that: “S & H has thoroughly examined the plans and specifications and the site has been visually ex[231]*231amined to corroborate if there are any deviations between the prints, specifications and the actual site. Any deviations have been included in the contract price.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Grant Thornton, LLP v. Martha A. Yung
Kentucky Supreme Court, 2018
William J. Yung v. Grant Thornton, LLP
Kentucky Supreme Court, 2018
Yung v. Grant Thornton, LLP
563 S.W.3d 22 (Missouri Court of Appeals, 2018)
Norwich v. Norwich
459 S.W.3d 889 (Court of Appeals of Kentucky, 2015)
Randall Waldman v. Ronald Stone
599 F. App'x 569 (Sixth Circuit, 2015)
In Re Classicstar Mare Lease Litigation
823 F. Supp. 2d 599 (E.D. Kentucky, 2011)
West Hills Farms, LLC v. ClassicStar, LLC
823 F. Supp. 2d 599 (E.D. Kentucky, 2011)
Gresh v. Waste Services of America, Inc.
738 F. Supp. 2d 702 (E.D. Kentucky, 2010)
Flegles, Inc. v. Truserv Corp.
289 S.W.3d 544 (Kentucky Supreme Court, 2009)
United States Achievement Academy, LLC v. Pitney Bowes, Inc.
458 F. Supp. 2d 389 (E.D. Kentucky, 2006)
Vinson v. Ford Motor Credit Corp.
56 F. App'x 220 (Sixth Circuit, 2003)
Sallee v. Fort Knox National Bank, N.A.
286 F.3d 878 (Sixth Circuit, 2002)
Wells v. Huish Detergents, Inc.
19 F. App'x 168 (Sixth Circuit, 2001)
Auto Channel, Inc. v. Speed Vision Network, LLC
144 F. Supp. 2d 784 (W.D. Kentucky, 2001)
Craig v. Keene
32 S.W.3d 90 (Court of Appeals of Kentucky, 2000)
United Parcel Service Co. v. Rickert
996 S.W.2d 464 (Kentucky Supreme Court, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
443 S.W.2d 227, 1969 Ky. LEXIS 242, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sanford-construction-co-v-s-h-contractors-inc-kyctapphigh-1969.