Sanderson v. Trump Manufacturing Co.

102 N.E. 2, 180 Ind. 197, 1913 Ind. LEXIS 108
CourtIndiana Supreme Court
DecidedMay 27, 1913
DocketNo. 21,593
StatusPublished
Cited by20 cases

This text of 102 N.E. 2 (Sanderson v. Trump Manufacturing Co.) is published on Counsel Stack Legal Research, covering Indiana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sanderson v. Trump Manufacturing Co., 102 N.E. 2, 180 Ind. 197, 1913 Ind. LEXIS 108 (Ind. 1913).

Opinion

Cox, J.

The St. Joseph and Elkhart Power Company was organized and incorporated in this State in 1900 for the purpose of building and maintaining a dam across .the St. Joseph river east of Mishawaka, at a point known as Twin Branch, and erecting and maintaining in connection therewith a power house with hydraulic and electrical machineiy for the purpose of generating and selling electrical current. Thereafter this company let the contract for all the work of construction to the Union Construction Company, a Connecticut corporation, which in turn sublet the work to appellants, engineers and contractors of New York City, doing business in the firm name of Sanderson and Porter. Appellants thereupon went into the open market to buy materials for building and equipping the dam and power house. They received from appellee, a corporation of Springfield, Ohio, engaged in the business of manufacturing water turbines, a written proposal to furnish certain described water wheels or turbines required in the equipment of the plant. Appellants met this proposal by a writing [201]*201denominated specifications for waterturbines. These writings -with accompanying blue prints were mutually accepted and, it is agreed, became the contract between the parties on July 19, 1902. The contract was for two different classes of turbines known respectively as “exciter line turbines,” and “generator line turbines”. This controversy involves only the latter class. Five of these turbines were to be set on a horizontal shaft so attached that they would operate in unison to turn the shaft which was to be coupled to a generator to produce the electric current. Each set of five turbines so set on a single shaft was termed a unit. They were to be installed in the power house of the power company by appellants. Four of these units were ordered by appellants at different times and furnished by appellee under the contract and installed by appellants as received in the power house of the St. Joseph and Elkhart Power Company as the parties contemplated when the contract for them was made. Payments were made by appellants from time to time, when, claiming that the turbines had failed, in actual work, to produce the power and efficiency guaranteed by appellees, they refused to make further payments and this action was brought by appellee to recover the balance claimed to be due, with interest.

The complaint was in four paragraphs. The first declared on an oral contract. The second sought to recover the value of the machinery without reference to a contract. The second paragraph was taken out of the case by a voluntary dismissal by appellee. The first paragraph is not of importance as it is agreed by the parties, and the court found, that the contract ivas in writing. The third paragraph, after allegations of the making of the contract and referring to it as an exhibit made a part of the complaint, is as follows: “That under the terms of said contract the plaintiff sold to the aforesaid defendants two exciter line turbines and four generator line turbines, to be made by plaintiff and delivered to the said defendants f. o. b. ears at plaintiff’s [202]*202factory in Springfield in the State of Ohio, for all of which the said defendants, by the terms of said contract promised and agreed to pay to plaintiff the sum of $32,420; payable in installments as in said contract provided; and plaintiff further avers that under the terms of said contract, and at the special instance and request of said defendants, it furthermore furnished materials and performed labor, for which said defendants undertook and agreed to pay this plaintiff the reasonable value thereof; and that the reasonable value of such additional materials furnished and labor performed is $318.50; that said defendants from time to time made payments under said contract for said turbines and said additional materials furnished and labor performed amounting in all to $22,792.77, a bill of particulars of all of which is filed herewith and made a part hereof, and marked exhibit ‘JB’; and plaintiff further avers that it did deliver said turbines f. o. b. cars at their factory in Springfield, Ohio, to the said defendants; and that this plaintiff has fully performed all of the terms and conditions of said contract by it to be performed, and that said defendants have received and accepted said property, but have failed to pay plaintiff according to the terms of said contract; that there is now due and unpaid the residue of $9,945.73; that of said residue $2,516.25 was due and payable on or before May 26,1905, — and $7,429.48 was due and payable on or before June 26, 1905; that there has accrued on said unpaid balance, interest at six per cent per annum, amounting to $1,355.27; and that there is now due plaintiff from said defendants under said contract, and wholly unpaid, the sum of $11,301. Wherefore plaintiff sues and demands judgment for twelve thousand ($12,000) dollars, and for its costs herein, and for all other proper relief. ’ ’

The fourth paragraph is not different in legal effect from the third. It alleges the sale and delivery to appellants of two “exciter line turbines” and two “generator line turbines” under the contract at the contract price at one [203]*203time and two additional “generator line turbines” at a later time by a later written order referred to as another exhibit. Otherwise the allegations and the demand are the same as in the third.

Appellants answered the complaint in five paragraphs. The first is á general denial and the second a plea of payment. The third paragraph sets up certain guaranties and conditions relating to the power and efficiency of the turbines and alleges their failure, after installation, to meet these requirements as to power and efficiency, for which failure appellee’s right to recover anything is denied. This paragraph of answer is conceded by appellants’ counsel to be merely an argumentative general denial.

The fourth paragraph of answer is pleaded as a counterclaim and in it the execution of the contract shown by the exhibits, which are made a part of the complaint and a part of this counterclaim by reference. It is then alleged that pursuant to that contract appellee did furnish to appellants, together with the other turbines and materials not in controversy in this appeal, the four units of “generator line turbines” in question; that by the terms of the contract appellee warranted that each of these units could and would, under ordinary conditions, generate 1,750 horse power under a working head of 18 feet and under such conditions would make 120 revolutions per minute; that appellee further warranted that each of these units would furnish 1,200 horse power under a working head of 15 feet and under such conditions maintain a speed of 120 revolutions per minute; that all of these turbines were furnished by appellee and received by appellants under an express warranty in the particulars named. It is then alleged that these units will not furnish 1,750 horse power each under a working head of 18 feet and make 120 revolutions per minute as warranted but, on the contrary, will not furnish over 1,200 horse power each; that they will not furnish 1,200 horse power each under a working head of 15 feet, but, on the contrary, will not furnish [204]*204over 800 horse power under the working head of 15 feet.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Eagle Signal Controls v. Midwestern Electric, Inc.
521 N.E.2d 967 (Indiana Court of Appeals, 1988)
State v. Humphreys, Jr.
245 A.2d 40 (New Jersey Superior Court App Division, 1968)
State v. Blanca
241 A.2d 647 (New Jersey Superior Court App Division, 1968)
Marranca v. Harbo
197 A.2d 865 (Supreme Court of New Jersey, 1964)
Jakubowski v. Minnesota Mining and Manufacturing
193 A.2d 275 (New Jersey Superior Court App Division, 1963)
McAndrew v. Mularchuk
162 A.2d 820 (Supreme Court of New Jersey, 1960)
US PIPE, ETC. v. United Steelworkers of Am.
157 A.2d 542 (New Jersey Superior Court App Division, 1960)
Collopy v. Newark Eye and Ear Infirmary
141 A.2d 276 (Supreme Court of New Jersey, 1958)
Lokar v. Church of the Sacred Heart
133 A.2d 12 (Supreme Court of New Jersey, 1957)
Pratico v. Rhodes
108 A.2d 97 (New Jersey Superior Court App Division, 1954)
Eggers v. Kenny
104 A.2d 10 (Supreme Court of New Jersey, 1954)
Parker v. Niagara Fire Ins. Co.
105 A.2d 677 (New Jersey Superior Court App Division, 1953)
Danek v. Hommer
100 A.2d 198 (New Jersey Superior Court App Division, 1953)
State v. Salernitano
99 A.2d 820 (New Jersey Superior Court App Division, 1953)
Miller v. Domanski
97 A.2d 641 (New Jersey Superior Court App Division, 1953)
Reimann v. Monmouth Consolidated Water Co.
87 A.2d 325 (Supreme Court of New Jersey, 1952)
Baker Manufacturing Co. v. Hall
175 P. 304 (Washington Supreme Court, 1918)
Muncie Electric Light Co. v. Joliff
109 N.E. 433 (Indiana Court of Appeals, 1915)
John Kindler Co. v. First National Bank
109 N.E. 66 (Indiana Court of Appeals, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
102 N.E. 2, 180 Ind. 197, 1913 Ind. LEXIS 108, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sanderson-v-trump-manufacturing-co-ind-1913.