Sandeep Patel and ERCC Construction Company, LLC v. Warwick Construction, Inc.

CourtCourt of Appeals of Texas
DecidedJanuary 20, 2022
Docket01-20-00208-CV
StatusPublished

This text of Sandeep Patel and ERCC Construction Company, LLC v. Warwick Construction, Inc. (Sandeep Patel and ERCC Construction Company, LLC v. Warwick Construction, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sandeep Patel and ERCC Construction Company, LLC v. Warwick Construction, Inc., (Tex. Ct. App. 2022).

Opinion

Opinion issued January 20, 2022

In The

Court of Appeals For The

First District of Texas ———————————— NO. 01-20-00208-CV ——————————— SANDEEP PATEL AND ERCC CONSTRUCTION COMPANY, LLC, Appellants V. WARWICK CONSTRUCTION, INC., Appellee

On Appeal from the 268th District Court Fort Bend County, Texas Trial Court Case No. 14-DCV-219641

MEMORANDUM OPINION

Appellee Warwick Construction, Inc. sued Sandeep Patel and ERCC

Construction Company, LLC, and others who settled before trial, for unpaid amounts

owed on a contract to build a hospice facility. Warwick also alleged that Patel and

others committed fraud and engaged in a conspiracy to commit fraud. A jury found that ERCC breached the construction contract and violated the Texas Prompt Pay

Act, that Patel and ERCC violated the Texas Construction Trust Fund Act by

misapplying funds and committed fraud against Warwick. The jury found the

following amounts of damages: $463,406.48 for breach of contract; $373,000 for

misapplication of trust funds; $33,000 for fraud, plus $500,000 each against Patel

and ERCC as exemplary damages relating to fraud. The trial rendered judgment on

the jury verdict, awarding Warwick damages for breach of contract, misapplication

of trust funds, fraud, exemplary damages of $200,000 each (the statutory maximum)

against Patel, pre- and post-judgment interest, statutory penalty interest for failing

to promptly pay, and attorney’s fees. The final judgment made ERCC and Patel

“jointly and severally” liable for “$372,000.00 for ERCC’s breach of contract and

for Patel’s [misapplication of trust funds], respectively,” and awarded “an additional

$91,406.48 for ERCC’s breach of contract,” which is the difference between the

jury’s award for breach-of-contract damages and $372,000.

Patel and ERCC appealed, raising seven issues. They assert that the trial court

erred by: (1) assigning joint and several liability for breach-of-contract damages

awarded solely against ERCC; (2) violating the “one satisfaction rule” and awarding

double recovery by rendering judgment on both breach of contract and

misapplication of trust funds; (3) failing to apply settlement credits to the

misapplication of trust funds damages award; (4) rendering judgment on fraud when

2 the contract language allegedly precludes a finding of justifiable reliance;

(5) rendering judgment on fraud when the evidence was legally insufficient and

(6) factually insufficient; and (7) awarding constitutionally excessive exemplary

damages based on legally and factually insufficient evidence.

Because we conclude that the one satisfaction rule applies in this case and that

recovery is not viable on either the claim for misapplication of trust funds or the

claim for fraud, we reverse the trial court’s judgment and render take-nothing

judgment on the misapplication of trust funds claim and the fraud claim, and we

remand to the trial court for entry of judgment consistent with this opinion, including

calculation of prejudgment interest.

Background

Sandeep Patel is the managing member of ERCC. Syed Anwar, Aman Jafar,

and Khurram Ibrihim are the other members of ERCC, which was formed in 2011.1

Patel, Anwar, Jafar, and Ibrihim also had an ownership interest in Altus Sugarland

Realty, L.P. (“Altus”). Patel also owns Sterling Group of Engineering Companies

(“Sterling Engineering”). Stanley Robinson worked for ERCC. Years before

working for ERCC and while working for another company, Robinson hired and

1 Anwar, Jafar, and Ibrihim settled with Warwick before trial, and they are not parties to this appeal. 3 worked with Tony Annan, who founded and remained as the president of Warwick

Construction.

In late October 2013, Altus entered into a contract with ERCC to build the

Altus Hospice Home (“Altus Hospice”), a health care facility to be located in Sugar

Land, Texas. Sterling Engineering was designated as the “architect” for the project.

The contract price was $3,200,000. The contract required ERCC as “contractor” to

provide a payment and performance bond in the amount of $3,200,000. But ERCC,

which had not yet done any construction projects, was unable to obtain a payment

and performance bond.

Robinson invited Annan to bid on the Altus Hospice job, and Warwick

Engineering submitted a bid. Although Annan later testified that he initially believed

that Warwick would be contracting directly with Altus, Annan learned that ERCC

would be contracting directly with Altus. In November 2013, ERCC as “design-

builder” for the project entered into a contract with Warwick, as contractor, for the

construction of Altus Hospice. The contract stated that it “represents the entire and

integrated agreement between the parties hereto and supersedes prior negotiations,

representations or agreements, either written or oral.” The contract price was

$3,200,000. The contract required Warwick to provide a payment and performance

bond in the amount of $3,200,000. The parties later agreed to remove landscaping

from the scope of work contractually assigned to Warwick. Warwick also agreed

4 that $352,000 of its contract price would instead be paid to Sterling Engineering for

project management.

Warwick obtained a payment and performance bond, which Annan personally

guaranteed. The bond was accepted by Altus in lieu of a bond obtained by ERCC.

According to Patel’s trial testimony, ERCC reimbursed Warwick for the cost of

obtaining the payment and performance bond. Construction began, and, in

accordance with the contract, Warwick submitted applications for payment on a

monthly basis. The first five applications for payment were timely paid in full.

According to Annan, the next six or seven applications were not timely paid, but

they were paid by the time of trial. Annan testified that not being promptly paid may

have hurt his relationships with his subcontractors and could harm his business in

the future, but he did not quantify these costs. Annan also testified at trial that ERCC

still owed Warwick $463,406.48 for work completed pursuant to change orders,

which are changes to the scope of the construction project due to engineering

requirements or owner choices.

Warwick filed a mechanic’s and materialman’s lien and a constitutional lien

against Altus Hospice, and later Warwick filed suit to foreclose the liens. Warwick

amended its petition, adding various claims against ERCC, Patel, and Sterling

Engineering. Warwick settled with Altus, and Sterling Engineering declared

bankruptcy. Warwick removed the case to the bankruptcy court, and when Sterling

5 Engineering’s bankruptcy was finally resolved, the case was remanded to state court

for disposition of Warwick’s remaining claims against ERCC and Patel.

In response to interrogatories, and prior to the settlement with Anwar, Jafar,

and Ibrihim, Warwick stated:

After all just and lawful offsets, payments, and credits have been allowed, Warwick remains unpaid in the amount of $870,302.03 for the labor, materials, and equipment it provided to the Defendants for which it has not been paid, plus $352,000 which was fraudulently withheld from its contract based on the fraudulent misrepresentations that [Sterling Engineering] would act as the Project Manager in exchange for such funds.

The trial court held a pretrial hearing on the parties’ motions in limine at which

Warwick raised the issue of settlements.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Grant Thornton LLP v. Prospect High Income Fund
314 S.W.3d 913 (Texas Supreme Court, 2010)
Utts v. Short
81 S.W.3d 822 (Texas Supreme Court, 2002)
Lively v. Carpet Services, Inc.
904 S.W.2d 868 (Court of Appeals of Texas, 1995)
Star Houston, Inc. v. Shevack
886 S.W.2d 414 (Court of Appeals of Texas, 1994)
Mobil Oil Corp. v. Ellender
968 S.W.2d 917 (Texas Supreme Court, 1998)
Stewart Title Guaranty Co. v. Sterling
822 S.W.2d 1 (Texas Supreme Court, 1992)
DRC Parts & Accessories, L.L.C. v. VM Motori, S.P.A.
112 S.W.3d 854 (Court of Appeals of Texas, 2003)
First Title Co. of Waco v. Garrett
860 S.W.2d 74 (Texas Supreme Court, 1993)
Thigpen v. Locke
363 S.W.2d 247 (Texas Supreme Court, 1962)
Waite Hill Services, Inc. v. World Class Metal Works, Inc.
959 S.W.2d 182 (Texas Supreme Court, 1998)
Madison Ex Rel. M.M. v. Williamson
241 S.W.3d 145 (Court of Appeals of Texas, 2007)
Lundy v. Masson
260 S.W.3d 482 (Court of Appeals of Texas, 2008)
Birchfield v. Texarkana Memorial Hospital
747 S.W.2d 361 (Texas Supreme Court, 1987)
Tony Gullo Motors I, L.P. and Brien Garcia v. Nury Chapa
212 S.W.3d 299 (Texas Supreme Court, 2006)
Charles Saden v. Brian Smith
415 S.W.3d 450 (Court of Appeals of Texas, 2013)
National Property Holdings, L.P. v. Westergren
453 S.W.3d 419 (Texas Supreme Court, 2015)
TMRJ Holdings, Inc. v. Inhance Techs., LLC
540 S.W.3d 202 (Court of Appeals of Texas, 2018)
Jpmorgan Chase Bank, N.A. v. Orca Assets G.P., L. L.C.
546 S.W.3d 648 (Texas Supreme Court, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Sandeep Patel and ERCC Construction Company, LLC v. Warwick Construction, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/sandeep-patel-and-ercc-construction-company-llc-v-warwick-construction-texapp-2022.