SAM RODGERS PROPERTIES, INC. v. Chmura

61 So. 3d 432, 2011 Fla. App. LEXIS 5943, 2011 WL 1565446
CourtDistrict Court of Appeal of Florida
DecidedApril 27, 2011
Docket2D10-1260
StatusPublished
Cited by12 cases

This text of 61 So. 3d 432 (SAM RODGERS PROPERTIES, INC. v. Chmura) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
SAM RODGERS PROPERTIES, INC. v. Chmura, 61 So. 3d 432, 2011 Fla. App. LEXIS 5943, 2011 WL 1565446 (Fla. Ct. App. 2011).

Opinion

PER CURIAM.

After a nonjury trial, Sam Rodgers Properties, Inc. (SRP), appeals an amended final judgment entered in favor of Linda Lan Chmura in the amount of $355,742.55, plus interest. We affirm the portion of the amended final judgment that complies with our prior mandate in Chmura v. Sam Rodgers Props., Inc., 2 So.3d 984 (Fla. 2d DCA 2008), which orders that the previous foreclosure sale and certificate of title be vacated and set aside. However, because we find that there was a legally binding written contract between the parties and both a valid original claim of lien and amended claim of lien, we reverse the award of damages to Mrs. Chmura and remand with directions for the trial court to enter judgment in favor of SRP on its breach of contract and lien foreclosure claims.

I. Facts

This entire case is about a $10,000 dispute in the base contract price to construct a home. SRP is a home builder and the developer of a community called Pelican Pointe Golf & Country Club. In February 2004, Mrs. Chmura signed a set of contracts 1 with SRP to purchase lot 31 in Pelican Pointe and to have a house built on *435 that lot. The parties’ dispute arose over the base price of the house to be built on the lot. However, it is undisputed that Mrs. Chmura signed a contract dated February 28, 2004, to build a “Monterey” model on lot 31 for a base price of $246,700. The trial court was also presented with a copy 2 of a second contract dated May 29, 2004, reflecting that Mrs. Chmura agreed to build a “Monterey” on lot 31 for a base price of $256,700, allegedly due to an increase in the model’s base price. To explain the discrepancy between the two contracts, SRP conceded that, at some point after February 2004, the $246,700 price for the Monterey model on lot 31 was “whited out” and changed to $256,700 on the first page of the construction contract. 3 Sam Rodgers failed to obtain Mrs. Chmura’s initials or signature on the page that had changed the base price for the house or on any other document specifically acknowledging her consent to the $10,000 increase in the base price. Nevertheless, SRP claimed that Mrs. Chmura orally agreed to the price increase, 4 something she vehemently denied.

At trial, Mrs. Chmura claimed she did not realize the base price of the house had been increased without her consent until September or October 2005. Thereafter, she sent letters to SRP questioning the price discrepancy, but she took no affirmative action to cause SRP to halt construction of the house or to repudiate the first contract. It is apparent from Mrs. Chmu-ra’s testimony and the evidence presented at trial that she did not want to terminate the contract; she simply wanted to correct what she perceived to be an error in pricing. During this time frame, she attended preconstruction meetings with SRP’s representatives.

In late January 2006, SRP began construction of a Monterey model on lot 31. After the slab was poured and the roof was dried in, SRP asked Mrs. Chmura to make the next two “draw” payments on the house. Mrs. Chmura did not make the payments, and construction stopped on March 10, 2006, although subcontractors who were in the middle of tasks were allowed to complete those tasks. On April 26, 2006, SRP recorded a claim of lien in the amount of $169,926 for “furnished labor, services, or materials consisting of home construction” that allegedly remained unpaid out of a total of $339,853. 5 On June 13, 2006, it filed a lawsuit against Mrs. Chmura asserting claims for construction lien foreclosure and breach of contract. Mrs. Chmura counterclaimed for rescission.

In July 2006, SRP performed additional work on the house, alleging that the work was necessary to protect the structure from the elements. On August 30, 2006, it *436 recorded an amended claim of lien to reflect these additional sums, totaling an additional $10,213. This amount represented services rendered after the original work had stopped, as well as payment of taxes and insurance on the property. It then amended the complaint to recover these additional amounts.

Subsequently, SRP obtained a final judgment of foreclosure and bought the house and lot at a foreclosure sale. For reasons explained in our prior opinion, this court reversed the final judgment of foreclosure and remanded for a new trial. Chmura, 2 So.3d at 987.

On remand, SRP proceeded to a second nonjury trial, seeking foreclosure on its claim of lien and damages for breach of contract. Its main argument was that the parties had a valid contract to build a Monterey model on lot 31 for $256,700. The trial court rejected that claim, finding “Exhibit 10, the Contract upon which [SRP] sued[,] was changed by white out. It appeared that the date of the Contract, as well as the purchase price[,] was changed.... It is undisputed that Linda Chmura did not sign the changed Contract.” The trial court also concluded that SRP had begun construction of the house without any valid contract at all, finding that there had been “no meeting of the minds” and “no signed contract to prove otherwise.”

Regarding SRP’s claim for foreclosure of construction liens, the trial court concluded that the amended claim of lien is “void as a matter of law as it was filed 168 days after the last work was performed pursuant to the' [contract.” The trial court found that the additional work reflected in the amended claim of lien was “done to protect [SRP’s] interests, not pursuant to the [c]ontract or for the benefit of Linda Chmura,” after SRP had filed suit to foreclose the original lien. It conclusor-ily found that the amended lien sought to recover for additional work not performed pursuant to the contract and that Mrs. Chmura had suffered “great prejudice.” The trial court therefore found the amended claim of lien fraudulent and unenforceable.

The trial court then: (1) vacated and set aside the foreclosure sale in which SRP had bought the subject property, “unless the parties agree otherwise”; 6 and (2) entered judgment in favor of Mrs. Chmura in the amount of $355,742.55, plus interest. It seems that the trial court sought to compensate Mrs. Chmura for construction costs, money she paid to purchase lot 31, and her expenses related to its purchase. The inexplicable effect of this final judgment was to award Mrs. Chmura lot 31, with the partially completed house on it, and a money judgment reimbursing her all of the money she paid to buy lot 31 and to construct the partially built house. 7 As discussed below, this windfall for Mrs. Chmura is not supported by competent and substantial evidence.

II. Analysis

A. Breach of contract

SRP argues that the final judgment is erroneous because even if the May 2004 contract to build a Monterey model on lot 31 for $256,700 was unenforceable, Mrs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

FARREY'S WHOLESALE HARDWARE CO., INC. v. COLTIN ELECTRICAL SERVICES, LLC
263 So. 3d 168 (District Court of Appeal of Florida, 2018)
Best Drywall Services, Inc. v. Blaszczyk
207 So. 3d 271 (District Court of Appeal of Florida, 2016)
Gator Boring & Trenching, Inc. v. Westra Construction Corp.
210 So. 3d 175 (District Court of Appeal of Florida, 2016)
Massey Asphalt Paving, Inc. v. Lee Land Development, Inc.
203 So. 3d 1271 (Court of Civil Appeals of Alabama, 2016)
IberiaBank v. Coconut 41, LLC
984 F. Supp. 2d 1283 (M.D. Alabama, 2013)
Hancock v. American Telephone & Telegraph Co.
701 F.3d 1248 (Tenth Circuit, 2012)
Stock Building Supply of Florida, Inc. v. Soares Da Costa Construction Services, LLC
76 So. 3d 313 (District Court of Appeal of Florida, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
61 So. 3d 432, 2011 Fla. App. LEXIS 5943, 2011 WL 1565446, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sam-rodgers-properties-inc-v-chmura-fladistctapp-2011.