Massey Asphalt Paving, Inc. v. Lee Land Development, Inc.

203 So. 3d 1271, 2016 Ala. Civ. App. LEXIS 56
CourtCourt of Civil Appeals of Alabama
DecidedMarch 4, 2016
Docket2140680
StatusPublished

This text of 203 So. 3d 1271 (Massey Asphalt Paving, Inc. v. Lee Land Development, Inc.) is published on Counsel Stack Legal Research, covering Court of Civil Appeals of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Massey Asphalt Paving, Inc. v. Lee Land Development, Inc., 203 So. 3d 1271, 2016 Ala. Civ. App. LEXIS 56 (Ala. Ct. App. 2016).

Opinion

PITTMAN, Judge.

Massey Asphalt Paving, Inc. (“Massey”), appeals from a judgment of the St. Clair Circuit Court, which determined that Massey did not hold a valid materialman’s lien on property owned by Lee Land Development, Inc. (“Lee Land”). We affirm.

Procedural History

Massey sued Lee Land, alleging that Massey and Lee Land had entered into an agreement pursuant to which Massey was to provide paving materials and to perform paving work in connection with the improvement of two tracts of Lee Land’s real property in St. Clair County known as Lee Gardens and Lee Commercial Park (sometimes hereinafter referred to collectively as “the properties”). Massey alleged further that, although it had provided the materials and had performed the work on the properties as agreed upon, Lee Land had not paid Massey the amount it had agreed to pay. Massey stated causes of action alleging breach of contract, work and labor done, open account, and promissory fraud, and Massey sought to enforce a materialman’s lien on the properties. Along with its complaint, Massey submitted a statement of lien that had been filed in the St. Clair Probate Court on November 12, 2008.

After a nonjury trial, the trial court entered a judgment finding that Lee Land owed Massey for work and materials provided, and it entered a judgment in Massey’s favor in the amount of $35,000. The trial court, however, also found that Massey did not hold a lien on the properties because, the trial court determined, Massey had not timely filed its statement of lien in the probate court pursuant to § 35-11-215, Ala.Code 1975. That Code provision requires Massey to have filed a statement of lien within six months of performing the last item of work, or providing the last item of material, for the paving job. We also note that § 35-11-221, Ala.Code 1975, requires an action to enforce a mate-rialman’s lien to be commenced “within six months after the maturity of the entire indebtedness secured thereby,” although the trial court did not expressly rely on that Code provision in finding that Massey could not enforce a materialman’s lien. Massey appealed from the judgment, arguing that the trial court erred in determining that Massey did not hold a material-man’s lien on the properties.1

Standard of Review

“ ‘ “ ‘[W]hen a trial court hears ore tenus testimony, its findings on dis[1273]*1273puted facts are presumed correct and its judgment based on those findings will not be reversed unless the judgment is palpably erroneous or manifestly unjust.’ ” ’ Water Works & Sanitary Sewer Bd. v. Parks, 977 So.2d 440, 443 (Ala.2007) (quoting Fadalla v. Fadalla, 929 So.2d 429, 433 (Ala.2005), quoting in turn Philpot v. State, 843 So.2d 122, 125 (Ala.2002)). ‘ “The presumption of correctness, however, is rebuttable and may be overcome where there is insufficient evidence presented to the trial court to sustain its judgment.” ’ Wattman v. Rowell, 913 So.2d 1083, 1086 (Ala.2005) (quoting Dennis v. Dobbs, 474 So.2d 77, 79 (Ala.1985)). ‘Additionally, the ore tenus rule does not extend to cloak with a presumption of correctness a trial judge’s conclusions of law or the incorrect application of law to the facts.’ Wattman v. Rowell, 913 So.2d at 1086.”

Retail Developers of Alabama, LLC v. East Gadsden Golf Club, Inc., 985 So.2d 924, 929 (Ala.2007). Our supreme court has indicated that factual issues surrounding the timeliness of the filing of a statement of a materialman’s lien, as well as the timeliness of an action to enforce such a lien, are subject to the ore tenus rule. C & S Family Credit of Alabama, Inc. v. McNairy, 613 So.2d 1232, 1233 (Ala.1992).

Discussion

Timeliness of the Statement of Lien

“Section 35-11-210, [Ala.] Code 1975, is intended to give every mechanic or materialman who performs any work or labor, or furnishes any material for any building or improvement on land by virtue of a contract with the owner thereof, or his agent, contractor, or subcontractor, a lien on the improvements and on the land. Elder v. Stewart, 269 Ala. 482, 114 So.2d 263 (1959).”

Bettinger v. Stephens Wholesale Bldg. Supply, Co., 487 So.2d 1369, 1370 (Ala.Civ.App.1986).

One of the requirements for the perfection of a materialman’s lien, is the filing of a verified statement of lien in the probate court of the county where the real property upon which the lien is to attach is situated. Ala.Code 1975, § 35-11-213. Section 35-11-215, Ala.Code 1975, sets the deadline for filing the statement of lien:

“The lien declared in this division shall be deemed lost unless the statement referred to in Section 35-11-213 shall be filed by every original contractor within six months and by every journeyman and day laborer within 30 days, and by every other person entitled to such lien within four months, after the last item of work or labor has been performed or the last item of any material, fixture, engine, boiler, or machinery has been furnished for any building or improvement on land or for repairing, altering, or beautifying the same under or by virtue of any contract with the owner or proprietor thereof, or his agent, architect, trustee, contractor, or subcontractor.”

(Emphasis added.) It is not disputed that Massey was an “original contractor” as that term is used in § 35-11-215. See generally Southern Sash of Huntsville, Inc. v. Jean, 285 Ala. 705, 710, 235 So.2d 842, 846 (1970) (“ ‘A materialman furnishing materials for a building under contract with the owner is an original contractor.’ ” (quoting Morris v. Bessemer Lumber Co., 217 Ala. 441, 443, 116 So. 528, 529 (1928))). There is a dispute in this case as to the date on which Massey performed “the last item of work” or furnished the “last item of ... material” and, therefore, whether Massey filed its statement of lien within the applicable six-month period.

[1274]*1274Massey filed its statement of lien on November 12, 2008. More than six months earlier, on December 21, 2007, Massey had first performed work and provided materials pursuant to its agreement with Lee Land. Massey submitted an invoice to Lee Land on that same day, and Lee Land paid the amount shown on that invoice.

Massey provided additional materials and performed additional work, and billed Lee Land for the materials and the work, in early April 2008, which also was more than six months before Massey filed its statement of lien. Lee Land initially paid only half of what it owed for the work and materials Massey had provided in April 2008, apparently because Lee Land disputed the amount of materials that Massey had actually provided. Massey’s president testified at the trial that he had agreed to allow Lee Land to delay paying the remaining balance until the area of the paving job could be measured.

In October 2008, principals of Massey and Lee Land met at the job site and measured the amount of paving work that had been completed by Massey on the properties. Massey’s president testified during the trial that the measurements had revealed that Massey actually had provided more materials than it had estimated and for which it had billed Lee Land.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

C & S FAMILY CREDIT OF ALABAMA v. McNairy
613 So. 2d 1232 (Supreme Court of Alabama, 1992)
Madison Highlands Dev. Co. v. DEAN AND SON PLUMBING CO., INC.
415 So. 2d 1129 (Court of Civil Appeals of Alabama, 1982)
Central Coast Electric, Inc. v. Mendell
672 P.2d 1224 (Court of Appeals of Oregon, 1983)
Water Works & Sanitary Sewer Bd. v. Parks
977 So. 2d 440 (Supreme Court of Alabama, 2007)
Tym v. Ludwig
538 N.W.2d 600 (Court of Appeals of Wisconsin, 1995)
Philpot v. State
843 So. 2d 122 (Supreme Court of Alabama, 2002)
Wright v. Turner
351 So. 2d 1 (Supreme Court of Alabama, 1977)
Retail Developers of Alabama, LLC v. East Gadsden Golf Club, Inc.
985 So. 2d 924 (Supreme Court of Alabama, 2007)
Home Federal Savings & Loan Association v. Williams
158 So. 2d 678 (Supreme Court of Alabama, 1963)
Waltman v. Rowell
913 So. 2d 1083 (Supreme Court of Alabama, 2005)
Fadalla v. Fadalla
929 So. 2d 429 (Supreme Court of Alabama, 2005)
Ex Parte Johnson
474 So. 2d 715 (Supreme Court of Alabama, 1985)
Dennis v. Dobbs
474 So. 2d 77 (Supreme Court of Alabama, 1985)
Advertiser Co. v. Hobbie
474 So. 2d 93 (Supreme Court of Alabama, 1985)
Locke v. Wheat
350 So. 2d 451 (Supreme Court of Alabama, 1977)
Druid City Hospital Bd. v. Epperson
378 So. 2d 696 (Supreme Court of Alabama, 1979)
SAM RODGERS PROPERTIES, INC. v. Chmura
61 So. 3d 432 (District Court of Appeal of Florida, 2011)
Morris v. Bessemer Lumber Co.
116 So. 528 (Supreme Court of Alabama, 1928)
Fowler v. MacKentepe
172 So. 266 (Supreme Court of Alabama, 1937)
Otis Elevator Co. v. Sheffield Realty Co.
88 So. 566 (Supreme Court of Alabama, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
203 So. 3d 1271, 2016 Ala. Civ. App. LEXIS 56, Counsel Stack Legal Research, https://law.counselstack.com/opinion/massey-asphalt-paving-inc-v-lee-land-development-inc-alacivapp-2016.