Saipem America v. Wellington Underwriting Agencies Ltd.

335 F. App'x 377
CourtCourt of Appeals for the Fifth Circuit
DecidedJune 10, 2009
Docket08-20247
StatusUnpublished
Cited by3 cases

This text of 335 F. App'x 377 (Saipem America v. Wellington Underwriting Agencies Ltd.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Saipem America v. Wellington Underwriting Agencies Ltd., 335 F. App'x 377 (5th Cir. 2009).

Opinion

PER CURIAM. **

The appeal arose from damage caused to an offshore platform while it was being transported from Texas to an offshore location in Israel. The parties presented this dispute to arbitration. The arbitration tribunal found Saipem America, Inc. (“Saipem”) directly liable for negligent misrepresentation, awarded the Underwriters more than $1 million in actual damages and $399,000 in attorneys’ fees, and split the costs of arbitration equally between the parties. Saipem brought suit in federal district court seeking to vacate the arbitration award. The district court affirmed the award. For the reasons discussed herein, we AFFIRM.

I. FACTUAL AND PROCEDURAL BACKGROUND

The underlying facts of this case are not in dispute. Samedan Mediterranean Sea (“Samedan”), later known as Noble Energy Mediterranean, Ltd. (hereinafter “Sam-edan”), contracted with Heerema Marine Contractors Nederland B.V. (“Heerema”) for the transportation and installation of Samedan’s offshore platform from Texas to Israel. The contract between Heerema and Samedan required Heerema to obtain insurance for the load-out, transportation, and installation of the platform. Heerema obtained the required insurance from several underwriters (“Underwriters”), naming Heerema and Samedan as principal assureds.

While in transport in December 2002, the platform received extensive damage when the platform’s main crane broke free from its boom rest. The company responsible for towage and installation of the platform also sustained damages. Heere-ma and Samedan filed insurance claims with the Underwriters for the damage. The Underwriters then made claims *379 against Saipem, asserting that Saipem was liable for the platform damage based on two contracts: one contract was between Saipem and Samedan under which Saipem was to serve as Samedan’s Certified Verification Agent (“CVA”) and the other contract was a marine warranty surveyor subcontract between Saipem and Heerema under which Saipem was to serve as a marine warranty surveyor. Samedan also made claims against Saipem because of the insurance policy’s deductible; Heerema did not bring a claim against Saipem.

The subcontract between Saipem and Heerema (the “Subcontract”) provides the following regarding arbitration:

Any dispute arising out of or in connection with this Subcontract which cannot be amicably settled shall be referred to arbitration in The Hague, The Netherlands, in accordance with the Rules of the International Chamber of Commerce currently in force. Any settlement agreement or arbitral award shall be final and binding upon Parties.

Pursuant to the Subcontract’s arbitration provision, Samedan and the Underwriters requested arbitration. 1 They argued that Saipem’s performance as CVA and marine warranty surveyor was inadequate and breached the contract with Sam-edan and the Subcontract with Heerema. Samedan and the Underwriters sought declarations that Saipem breached its contracts and fiduciary duties with them and with Heerema; that Saipem was negligent, professionally or otherwise; and that Sai-pem was guilty of negligent misrepresentation. The negligent misrepresentation claim was based on Saipem’s issuance of a certificate of approval that the platform could be safely towed from Texas to Israel. All parties sought attorneys’ fees.

The arbitral tribunal concluded that Sai-pem’s contracts with both Samedan and Heerema contain valid indemnity provisions, but the provisions create a “circularity of indemnity” that effectively extinguished the Underwriters subrogation claims against Saipem. The tribunal found that because Saipem had no direct contractual relationship with the Underwriters, the Underwriters could maintain a claim of negligent misrepresentation. The tribunal issued an award finding Saipem liable for damage to the platform. As a result of its finding on the negligent misrepresentation claim, the tribunal found Saipem liable to the Underwriters for actual damages in the amount of $1,110,657, attorneys’ fees and expenses in the amount of $399,000, and 50% of the costs of arbitration in the amount of $105,000. 2 The district court affirmed the award in all respects. Saipem appeals.

II. DISCUSSION

A. Standard of Review

“This court reviews a district court’s confirmation of an arbitration award de novo, using the same standards as the district court.” Am. Laser Vision, P.A. v. Laser Vision Inst., L.L.C., 487 F.3d 255, 258 (5th Cir.2007) (per curiam). Our review of the arbitration award is “ ‘exceedingly deferential,’ ” and the award must be upheld if it “ ‘is rationally inferable from *380 the letter or purpose of the underlying agreement.’ ” Id. (quoting Kergosien v. Ocean Energy, Inc., 390 F.3d 346, 352 (5th Cir.2004) and Nauru Phosphate Royalties, Inc. v. Drago Daic Interests, Inc., 138 F.3d 160, 164-65 (5th Cir.1998)).

This court previously recognized both statutory and common law grounds for vacating an arbitration award. 3 The parties dispute whether the Supreme Court’s recent decision in Hall Street Associates, L.L.C. v. Mattel, Inc., 552 U.S. 576, 128 S.Ct. 1396, 170 L.Ed.2d 254 (2008), forecloses this court’s review of the arbitration award on nonstatutory grounds. After oral argument, a panel of this court addressed that question in Citigroup Global Markets, Inc. v. Bacon, 562 F.3d 349 (5th Cir.2009). In Citigroup Global, the court stated that “manifest disregard of the law as an independent, nonstatutory ground for setting aside an award must be abandoned and rejected.” Id. at 358. The panel in Citigroup Global interpreted Hall Street as restricting grounds for vacatur of an arbitration award under the Federal Arbitration Act (“FAA”), 9 U.S.C. § 1 et seq., exclusively to statutory provisions, and it held that Hall Street effectively overruled Fifth Circuit precedent holding that nonstatutory grounds may support vacatur of an arbitration award. Id. at 350; see id. at 358 (“To the extent that our previous precedent holds that nonstatutory grounds may support the vacatur of an arbitration award, it is hereby overruled.”). Accordingly, we may vacate the arbitration award in this case only if a statutory ground supports the vacatur.

Under 9 U.S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
335 F. App'x 377, Counsel Stack Legal Research, https://law.counselstack.com/opinion/saipem-america-v-wellington-underwriting-agencies-ltd-ca5-2009.