Safety Insurance Company v. Marlette Homes, Inc.

CourtDistrict Court, D. Massachusetts
DecidedDecember 3, 2021
Docket1:19-cv-12012
StatusUnknown

This text of Safety Insurance Company v. Marlette Homes, Inc. (Safety Insurance Company v. Marlette Homes, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Safety Insurance Company v. Marlette Homes, Inc., (D. Mass. 2021).

Opinion

UNITED STATES DISTRICT COURT DISTRICT OF MASSACHUSETTS

_______________________________________ ) SAFETY INSURANCE COMPANY, ) as subrogee of WALTER NEAS, ) ) Plaintiff, ) Civil Action No. ) 19-12012-FDS v. ) ) MARLETTE HOMES, INC. and ) CMH MANUFACTURING, INC., ) ) Defendants. ) _______________________________________)

MEMORANDUM AND ORDER ON DEFENDANT’S MOTION FOR SUMMARY JUDGMENT

SAYLOR, C.J.

This is a lawsuit arising from a fire that occurred in a manufactured home. Plaintiff Safety Insurance Company, as subrogee of Walter Neas, alleges that defendants Marlette Homes, Inc. and CMH Manufacturing, Inc., were negligent and breached the warranty of merchantability because an allegedly faulty electrical connection started a fire in the home. Jurisdiction is based on diversity of citizenship. Defendant CMH has moved for summary judgment on the grounds that plaintiff’s claims are foreclosed by the Massachusetts statute of repose, Mass. Gen. Laws ch. 260, § 2B, or, alternatively, that plaintiff has failed to put forth sufficient facts concerning the origins of the fire. Because the statute of repose applies to the claims, the motion will be granted. I. Background A. Factual Background The following facts are stated as set forth in the record and are undisputed except as noted. Pine Hill Estates is a manufactured-home park in Raynham, Massachusetts. Pine Hill Estates, Inc., is the management company that operates the park. It collects rent, pays the park’s bills, maintains common areas, and keeps the streets in repair. (Bumila Dep. at 15, ECF No. 35-

5). Residents of Pine Hill Estates lease a plot of land and then purchase a manufactured home to put on the property. (Id. at 15). Those purchases are made through June Sales, LLC, which is a retailer of manufactured homes for Pine Hill Estates. (Id. at 17). June Sales purchases the structure from CMH, which then adapts one of its model homes in accordance with any customized features requested by the purchaser. (Weldy Dep. at 122-24, ECF No. 35-4; Bumila Dep. at 46-47). The homes are manufactured at CMH’s facility in Lewistown, Pennsylvania. Prior to leaving the facility, the structure is inspected to ensure it meets the National Manufactured Home Construction and Safety Standards and complies with other regulations promulgated by the Department of Housing and Urban Development. (Weldy Dep. at 145, 148-49; Bumila Dep. 75-

76). The structure at issue in this matter was manufactured and shipped in two sections. When such a structure arrives on site from the factory, construction is nearly complete—all plumbing and electrical wiring is installed and the interior trim is finished. (Bumila Dep. at 31). All that remains is for subcontractors hired by June Sales to join the pieces of the structure together and connect the utilities; June Sales finishes the driveway and landscaping. (Id. at 30). The residents then occupy the new home as owners of the structure and leaseholders of the underlying property. (Id. at 15). In 2004, Walter Neas purchased a home through June Sales known as a “Marlette Schult Smart Buy II Sectional, Model No. 6828-316,” which he customized in a variety of different ways. (Ex. 3 at 1-2, ECF No. 35-3). Among other things, he picked the flooring, the appliances, and the slope of the roof. (Id.). He chose a home designed to be suitable for New England weather, with a roof capable of withstanding 30 pounds of snow per square foot and thermal

insulation sufficient to withstand low temperatures. (See id.). CMH then manufactured the home according to the requested specifications and shipped it in two pieces to Pine Hill Estates. (Id. at 4; Bumila Dep. at 26-31). The two pieces were then joined together by subcontractors into a completed building. At some point thereafter, Walter and his wife Angela took up residence in their new home. (Ex. 6 at 4, ECF No. 35-6). On August 17, 2016, a fire occurred at the Neas’s home. (Ex. 7 at 2, ECF No. 35-7). The Raynham Fire Department responded to the incident; notes from the day of the fire indicated that the fire was unintentional and identified “electrical wiring” as the “equipment involved in ignition.” (Id. at 4). Peter Bumila, the president of Pine Hill Estates and the manager of June Sales, also visited the home on the day of the fire. (Bumila Dep. at 64). He reported that the

structure had “heavy smoke damage” and that there was charred wood underneath it at the “source of the electrical problem” and “source of the fire.” (Id. at 64-65). He noted charring near an electrical connector located along the wall where the two segments of the structure were joined during installation. (Id. at 65-66). The connectors complete the electrical circuits, allowing for power to flow between the two halves of the building. (See Weldy Dep. at 50-55). Each half of a connector is installed by stripping insulation from the end of a conductor cable, separating the conductor wires within that cable, pressing each wire into an assigned slot in one half of a plastic assembly, and then sealing the assembly covers together. (Ex. 13, ECF No. 37-2; Weldy Dep. at 61-63; Morse Report at 16- 18, ECF No. 35-9).1 The mating end of that sealed plastic assembly connects with the other half of the connector, which is assembled in the same fashion. (Morse Report at 16). The connector halves were installed by members of defendant’s electrical team at the factory so that the two halves could be easily connected by the on-site contractors. (See Weldy Dep. at 57-64; Bumila

Dep. at 87-88). Experts for both Safety Insurance Company and CMH agree that the fire originated at the electrical connector. (See Williams Report at 31, ECF No. 35-8; Morse Dep. at 57-58, ECF No. 37-1). However, they disagree as to the fire’s cause. CMH’s expert opines that the connector overheated at the point of connection between the two halves of the device. (Morse Report at 21). His report states that “[t]he specific mechanism that caused the overheating of the subject connector is undetermined.” (Id. at 22). Safety Insurance’s expert opines that the fire originated in one of the connector halves due to “physical damage . . . during factory assembly.” (Williams Report at 33). After the fire, in accordance with the insurance policy, Safety Insurance paid for the

damages to the structure and personal property. (Compl. ¶ 11). It then brought this action as a subrogee of Walter Neas. B. Procedural Background On August 19, 2019, Safety Insurance filed this action in Massachusetts Superior Court. On September 25, 2019, defendant CMH removed the action to this Court, alleging diversity jurisdiction under 28 U.S.C. § 1332. The complaint alleges that CMH was negligent in the manufacture of the electrical connection device and the wiring of the home. The complaint also

1 The plastic assembly is called a Molex “Self-Contained Power Connector.” (Ex. 13 at 2, ECF No. 37-2). alleges that CMH breached its warranty of merchantability. (Compl. ¶¶ 12-43). 2 On May 10, 2021, CMH moved for summary judgment on all counts. II. Legal Standard The role of summary judgment is “to pierce the pleadings and to assess the proof in order to see whether there is a genuine need for trial.” Mesnick v. Gen. Elec. Co., 950 F.2d 816, 822

(1st Cir. 1991) (quoting Garside v. Osco Drug, Inc., 895 F.2d 46, 50 (1st Cir. 1990)). Summary judgment shall be granted when “there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” Fed. R. Civ. P.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Yee v. City of Escondido
503 U.S. 519 (Supreme Court, 1992)
Milissa Garside v. Osco Drug, Inc.
895 F.2d 46 (First Circuit, 1990)
Samuel Mesnick v. General Electric Company
950 F.2d 816 (First Circuit, 1991)
Patrick J. O'COnnOr v. Robert W. Steeves
994 F.2d 905 (First Circuit, 1993)
Frankenmuth Mutual Insurance v. Marlette Homes, Inc.
573 N.W.2d 611 (Michigan Supreme Court, 1998)
Conley v. Scott Products, Inc.
518 N.E.2d 849 (Massachusetts Supreme Judicial Court, 1988)
Burnham v. Mark IV Homes, Inc.
441 N.E.2d 1027 (Massachusetts Supreme Judicial Court, 1982)
Ellis v. Board of Assessors of Acushnet
265 N.E.2d 491 (Massachusetts Supreme Judicial Court, 1970)
McDonough v. Marr Scaffolding Co.
591 N.E.2d 1079 (Massachusetts Supreme Judicial Court, 1992)
Parent v. Stone & Webster Engineering Corp.
556 N.E.2d 1009 (Massachusetts Supreme Judicial Court, 1990)
Sullivan v. Iantosca
569 N.E.2d 822 (Massachusetts Supreme Judicial Court, 1991)
Klein v. Catalano
437 N.E.2d 514 (Massachusetts Supreme Judicial Court, 1982)
Agri-Mark, Inc. v. Niro, Inc.
214 F. Supp. 2d 33 (D. Massachusetts, 2002)
Stearns v. Metropolitan Life Insurance Co.
117 N.E.3d 694 (Massachusetts Supreme Judicial Court, 2019)
Greenfield Country Estates Tenants Ass'n v. Deep
666 N.E.2d 988 (Massachusetts Supreme Judicial Court, 1996)
Rosario v. M.D. Knowlton Co.
767 N.E.2d 1126 (Massachusetts Appeals Court, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
Safety Insurance Company v. Marlette Homes, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/safety-insurance-company-v-marlette-homes-inc-mad-2021.