S. Brooke Purll, Inc. v. Vailes

850 A.2d 1135, 2004 D.C. App. LEXIS 270, 2004 WL 1171382
CourtDistrict of Columbia Court of Appeals
DecidedMay 27, 2004
Docket02-CV-1016
StatusPublished
Cited by10 cases

This text of 850 A.2d 1135 (S. Brooke Purll, Inc. v. Vailes) is published on Counsel Stack Legal Research, covering District of Columbia Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
S. Brooke Purll, Inc. v. Vailes, 850 A.2d 1135, 2004 D.C. App. LEXIS 270, 2004 WL 1171382 (D.C. 2004).

Opinion

SCHWELB, Associate Judge:

This case concerns a dispute between S. Brooke Purll, Inc., t/a Purll Construction (the contractor), and Patrick Darrell Vailes (the owner) over the alleged breach of a contract for the renovation of a house belonging to the owner. The trial judge found that the owner had failed to perform certain initial demolition work within the time specified in paragraph 1 of the contract and to make a payment of $7,031.71 as required in paragraph 3. The judge concluded, however, that paragraph 5 of the contract, which the contractor described as a liquidated damages clause, *1136 was unenforceable as a penalty, and she declined to award liquidated damages. The judge also rejected the contractor’s alternative request for damages for lost profits, holding that these losses had not been adequately proved, and that the contractor had, inter alia, failed to mitigate his damages. The judge awarded the contractor a total of only $2,987.48, including counsel fees. 1 The contractor appeals, 2 arguing that the trial judge erred by striking down the liquidated damages clause. 3 We agree and reverse.

I.

THE TRIAL COURT PROCEEDINGS

This case began as a suit by the owner in the Small Claims and Conciliation Branch for return of the $5,000.00 deposit that he had paid to the contractor as an initial payment under the construction contract, which was dated January 30, 2001. The contractor counterclaimed for liquidated damages in the amount of $36,102.04, and also requested an award of counsel fees. He invoked paragraph 5 of the contract, which reads as follows:

The [owner] further agrees that if he shall cancel this Contract for any reason, whatsoever, then he shall pay to the contractor as fixed and liquidated damages, without proof of loss, the sum of money equal to Thirty Five Percent (35%) of the full contract price herein-above stated. Furthermore, if it becomes necessary for the Contractor to file suit or take other legal action on this Contract because of a breach on the part of the party of the second part, the party of the second part agrees to pay reasonable attorney fees and court costs incurred by the Contractor when enforcing the terms of this Contract.[ 4 ]

Paragraph 9 of the contract provided that the full contract price was to be $103,148.71.

A bench trial was held on May 20 and 21, 2002. At the trial, the judge made oral findings from the bench. She found, as we have previously noted, that the owner had committed two material breaches of the contract. 5 With respect to damages, however, the judge ruled as follows:

The Court finds that the liquidated damages requested and stated under the contract is actually a penalty and therefore cannot be awarded in total. First of all, the Court finds that it’s a penalty, because it’s not anywhere close to the *1137 actual damages incurred and that the— if there were lost profits, it would not have been that difficult to present sufficient evidence to the Court on that issue.
The Court finds that the lost profits and the amount requested by the defendant are not supported by sufficient evidence in the record an[d] that the plaintiff did not prove by a preponderance of the evidence that the amount stated in its exhibits were supported by sufficient evidence.
And that therefore, the Court is left in a position to guess and speculate about exactly how much lost profit the defendant actually incurred as a result of the plaintiffs breach.
The Court also recognizes and there was no evidence that, of course, when there is this issue of lost profits, there is also a duty of mitigation. That issue, of course, was not — there was no evidence, of course, in terms of what mitigation efforts were taken or not taken.
Therefore, the Court does not award any lost profits to the defendant. As stated before, the defendant did not meet its burden of proof by a preponderance of the evidence and there was no[t] sufficient evidence for the Court to determine that the amount — that the defendant was requesting was a reasonable amount.

On appeal, the contractor challenges the judge’s invalidation of the liquidated damages claim and, in the alternative, he contends that his proof of lost profits was sufficient and, in fact, uncontradicted.

II.

LEGAL ANALYSIS

A century and a half ago, the New York Court of Appeals lamented that even “[t]he ablest judges have declared that they felt themselves embarrassed in ascertaining the principle upon which the decisions [distinguishing unenforceable penalties from valid liquidated damages clauses] were founded.” Cotheal v. Talmage, 9 N.Y. 551, 553 (1854). In more recent times, the issue has been raised whether the rule prohibiting penalty clauses in contracts between competent parties has any justification at all in light of general principles of freedom of contract. The Reporter for the Restatement (Second) of Contracts has written:

With the development of a doctrine of unconscionability capable of coping with abusive stipulated damage provisions in the same way as other abusive provisions, ... it has become increasingly difficult to justify the peculiar historical distinction between liquidated damages and penalties. Today the trend favors freedom of contract through the enforcement of stipulated damage provisions as long as they do not clearly disregard the principle of compensation.

E. Allen FaRNswoRth, FaunswoRth On Contracts § 12.18, at pp. 303-04 (3d ed. 2004) (footnote omitted). 6

In Vicki Bagley Realty, Inc. v. Laufer, 482 A.2d 359, 367 (D.C.1984), this court explicated the utility of liquidated damage clauses:

Upholding the liquidated damages provision in the present case is consistent with one of the main purposes of such a clause: to simplify the resolution of a breach of contract dispute. In addition to giving the parties an opportunity to resolve the damages question without resorting to litigation, ... a liquidated damages clause allows the parties to fix *1138 the measure of damages at the outset, before a breach even occurs. Such a provision is particularly appropriate when the parties enter into a contract like the one at bar, where the damages to be ascertained are uncertain in amount and cannot be easily ascertained.

(Citation and internal quotation marks omitted.)

This court’s jurisprudence has been tolerant of liquidated damages clauses unless they are demonstrably unreasonable.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hirecounsel Dc, LLC v. Connolly
District of Columbia, 2024
Tahmina Proulx v. 1400 Pennsylvania Avenue, SE, LLC
199 A.3d 667 (District of Columbia Court of Appeals, 2019)
Slinski v. Bank of America, N.A.
981 F. Supp. 2d 19 (District of Columbia, 2013)
Joseph v. Cuneo Law Group, P.C.
428 F. App'x 6 (D.C. Circuit, 2011)
The CUNEO LAW GROUP, PC v. Joseph
669 F. Supp. 2d 99 (District of Columbia, 2009)
Cuneo Law Group, P.C
District of Columbia, 2009
Ladd v. Chemonics International, Inc.
603 F. Supp. 2d 99 (District of Columbia, 2009)
Ladd v. Chemonics Inc
District of Columbia, 2009
Steele Foundations, Inc. v. Clark Construction Group, Inc.
937 A.2d 148 (District of Columbia Court of Appeals, 2007)
Willard Packaging Company, Inc. v. Javier
899 A.2d 940 (Court of Special Appeals of Maryland, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
850 A.2d 1135, 2004 D.C. App. LEXIS 270, 2004 WL 1171382, Counsel Stack Legal Research, https://law.counselstack.com/opinion/s-brooke-purll-inc-v-vailes-dc-2004.