RW Granger & Sons, Inc. v. Rojac Co., Inc.

885 F. Supp. 319, 1995 U.S. Dist. LEXIS 6785, 1995 WL 302503
CourtDistrict Court, D. Massachusetts
DecidedMay 16, 1995
DocketCiv. A. 93-40045-NMG
StatusPublished
Cited by5 cases

This text of 885 F. Supp. 319 (RW Granger & Sons, Inc. v. Rojac Co., Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
RW Granger & Sons, Inc. v. Rojac Co., Inc., 885 F. Supp. 319, 1995 U.S. Dist. LEXIS 6785, 1995 WL 302503 (D. Mass. 1995).

Opinion

MEMORANDUM AND ORDER

GORTON, District Judge.

Pending before this Court is a motion by the defendant, Rojac Company, Inc. (“Rojac”), to dismiss this case for improper venue. More specifically, Rojac alleges that the forum selection clauses in the subcontracts between itself and the plaintiff, R.W. Granger & Sons, Inc. (“Granger”), are unreasonable, and therefore, unenforceable. Rojac also contends that Massachusetts is a forum non conveniens for this case, and that this case should be dismissed to permit the parties to proceed with the two related actions in Connecticut and New York. The plaintiff opposes the motion to dismiss on the grounds that the forum selection clauses in the Granger-Rojac subcontracts are enforceable and Massachusetts is a convenient forum in which to try this case.

I. FACTUAL AND PROCEDURAL BACKGROUND

This case involves two subcontracts between Granger, the general contractor, and *321 Rojac, the lath and drywall subcontractor. Granger, a Massachusetts corporation, hired Rojac, a Connecticut corporation, to perform certain work on a correctional facility in Lansing, New York (the “Lansing Project”) and on schools in Danbury, Connecticut (the “Danbury Project”).

Both subcontracts contain the following provision:

This agreement shall be governed by and construed in accordance with the laws of the Commonwealth of Massachusetts. Trade Contractor agrees to submit to the jurisdiction of the courts of the Commonwealth of Massachusetts ...

That provision appears on the signature page of both contracts, and was the subject of negotiations between the parties.

Both the Lansing and Danbury Projects are public works projects. Pursuant to New York and Connecticut law, Granger, as the general contractor, was required to obtain Labor and Material Bonds to protect its suppliers. The bonds in both projects provided that actions commenced on such bonds or by any claimants thereunder would be brought in the respective state in which the bond was issued.

In the pending action, Granger has sued Rojac in Massachusetts alleging breach of contract (for abandoning its work on the Lansing Project), breach of duty to provide non-negligent performance (for negligence for causing asbestos contamination at the Danbury Project), and unfair and deceptive acts (for filing deliberately exaggerated liens). After the initiation of Granger’s Massachusetts suit, Rojac filed actions in New York and Connecticut on the bonds in the Lansing and Danbury Projects, respectively. Rojac contends that, pursuant to the bond agreements, it is obligated to sue on the bonds in New York and Connecticut and that it is unreasonable and judicially inefficient for disputes between the parties to be litigated in Massachusetts, New York, and Connecticut. Rojac concluded that this Court should, therefore 1) decline to enforce the forum selection clause in the subcontract which designates Massachusetts as the forum for Granger’s claims and 2) dismiss this case.

II. THE FORUM SELECTION CLAUSES

A. The Legal Standard

Under federal common law, it is well-settled that “parties to a contract may agree in advance to submit to the jurisdiction of a given court ...” National Equipment Rental, Ltd. v. Szukhent, 375 U.S. 311, 316, 84 S.Ct. 411, 414, 11 L.Ed.2d 354 (1964); The Bremen v. Zapata Off-Shore Co., 407 U.S. 1, 15, 92 S.Ct. 1907, 1916, 32 L.Ed.2d 513 (1972); Insurance Corporation of Ireland, Ltd. v. Compagnie des Bauxites de Guinee, 456 U.S. 694, 703-04,102 S.Ct. 2099, 2104-05, 72 L.Ed.2d 492 (1982). Federal law dictates that a court should enforce a forum selection clause in a contract unless the objecting party can “clearly show that enforcement would be unreasonable and unjust, or that the clause was invalid for such reasons as fraud or overreaching.” The Bremen, 407 U.S. at 15, 92 S.Ct. at 1916.

The law of Massachusetts was recently settled when the Supreme Judicial Court held, “[w]e accept the modern view that forum selection clauses are to be enforced if it is fair and reasonable to do so.” Jacobson v. Mailboxes Etc. U.S.A., Inc., 419 Mass. 572, 574-75, 646 N.E.2d 741 (1995), citing Restatement (Second) of Conflict of Laws § 80 (1988 revision). Because there is no material discrepancy between Massachusetts law and federal law, “we need confront neither the choice-of-law issue nor the daunting question whether forum selection clauses are to be treated as substantive or procedural for Erie purposes.” Lambert v. Kysar, 983 F.2d 1110 (1st Cir.1993).

B. Rojac’s Argument

Rojac asserts that this Court should neither enforce the forum selection clause nor exercise jurisdiction over Rojac because it is unreasonable and inefficient to force Rojac to appear in Massachusetts to defend this claim. In support of its position, Rojac cites cases in which subcontractors filed suit on payment bonds in the jurisdiction of the building projects, as required by the forum selection clauses in those bonds. In the cited cases, however, where different forums were desig *322 nated, the Courts opted to favor the bond forum selection clauses over the subcontract forum selection clauses because: 1) the suits were based on the payment bonds, 2) witnesses and evidence were located in the bond forums, and 3) the subcontractors might otherwise have been deprived of a forum in which to litigate their claims if the alternative forums refused to entertain suits on the bonds. Johnson Acoustics, Inc. v. P.J. Carlin Construction Co., 29 Conn.Sup. 457, 292 A.2d 273 (1971); Omega New York Products Corp. v. Parisi Bros. Inc., 57 Misc.2d 1000, 293 N.Y.S.2d 878 (1968); St. Paul Fire & Marine Ins. Co. v. Travelers Indemnity Co., 401 F.Supp. 927 (D.Mass.1975).

Mass.R.Civ.P. 13(a) provides that counterclaims arising out of the same transaction or occurrence as the opposing party’s claims are not compulsory if they “constitute an action required by law to be brought in a county other than the county in which the court is sitting.” Accordingly, Rojac’s bond claims are not compulsory counterclaims in Granger’s suit because those claims are statutorily and contractually required to be asserted in the New York and Connecticut courts. Therefore, Rojae will not be deprived of a forum in which to litigate its claims against Granger if this Court enforces the subcontract forum selection clause and denies the motion to dismiss.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Oscomp Systems, Inc. v. Bakken Express, LLC
930 F. Supp. 2d 261 (D. Massachusetts, 2013)
Inso Corp. v. DEKOTEC HANDELSGES, mbH
999 F. Supp. 165 (D. Massachusetts, 1998)
Hazen v. Resort Condo Intern'l
D. New Hampshire, 1996

Cite This Page — Counsel Stack

Bluebook (online)
885 F. Supp. 319, 1995 U.S. Dist. LEXIS 6785, 1995 WL 302503, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rw-granger-sons-inc-v-rojac-co-inc-mad-1995.