RSM Prod v. Gaz du Cameroun

117 F.4th 707
CourtCourt of Appeals for the Fifth Circuit
DecidedSeptember 19, 2024
Docket23-20583
StatusPublished
Cited by2 cases

This text of 117 F.4th 707 (RSM Prod v. Gaz du Cameroun) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
RSM Prod v. Gaz du Cameroun, 117 F.4th 707 (5th Cir. 2024).

Opinion

Case: 23-20583 Document: 77-1 Page: 1 Date Filed: 09/19/2024

United States Court of Appeals for the Fifth Circuit United States Court of Appeals Fifth Circuit ____________ FILED September 19, 2024 No. 23-20583 ____________ Lyle W. Cayce Clerk RSM Production Corporation,

Plaintiff—Appellee,

versus

Gaz du Cameroun, S.A.,

Defendant—Appellant. ______________________________

Appeal from the United States District Court for the Southern District of Texas USDC No. 4:22-CV-3611 ______________________________

Before Wiener, Elrod, and Wilson, Circuit Judges. Cory T. Wilson, Circuit Judge: This appeal asks whether the district court properly vacated part of an arbitral tribunal’s “Addendum Award” as exceeding the arbitrators’ power. For the reasons below, we conclude the court erred and reverse and remand with instructions to confirm the Addendum Award. I. In 2001, RSM Production Corporation (RSM) and the Republic of Cameroon executed a concession contract giving RSM 100% of the right to explore and develop hydrocarbons in an area called the Logbaba Block. In Case: 23-20583 Document: 77-1 Page: 2 Date Filed: 09/19/2024

No. 23-20583

2005, RSM and Gaz du Cameroun (GdC)1 entered into two agreements stemming from the concession contract: a Farmin Agreement (the Farmin)2 and a Joint Operating Agreement (JOA), which designated GdC as the Logbaba project’s operator. The Farmin granted GdC 60% of RSM’s 100% participating interest in the concession contract in exchange for GdC’s agreement to perform the well work. As part of the Farmin’s compensation scheme, RSM agreed that GdC was entitled to recover a “Payout” of 100% of its drilling costs via 100% of the production revenues, less an overriding royalty of 0.8%. The Farmin set when the Payout was to happen: Payout shall be deemed to occur on the first day of the calendar month following the calendar month in which the credit balance of the payout account equals the charge balance of the payout account[.]

After Payout, i.e., full cost recovery by GdC, the parties were entitled to their proportionate shares of production revenues, 60% for GdC and 40% for RSM. As it happened, a dispute arose between the parties over the Payout date. RSM believed that GdC had achieved full cost recovery by January 2016, making the Payout date February 1, 2016. RSM also asserted that GdC improperly offset royalty payments to another entity, Cameroon Holdings, Ltd., (the CHL Royalty) against pre-Payout revenues, artificially delaying GdC’s full cost recovery until May 2016, which shifted the Payout date to

_____________________ 1 GdC was formerly known as Logbaba Development, Ltd. For ease of reference, we refer to GdC in this opinion. 2 A farmin agreement (sometimes called “farm-in”) “is a contract whereby one company acquires an interest in an exploration or production license by paying some of the past or future costs of another company that is relinquishing part of its interest.” Apache Bohai Corp., LDC v. Texaco China, B.V., 330 F.3d 307, 308 n.1 (5th Cir. 2003).

2 Case: 23-20583 Document: 77-1 Page: 3 Date Filed: 09/19/2024

June 1, 2016. GdC contested RSM’s version of events and insisted on the June 1 Payout date. Under Articles 9.1 and 9.2 of the Farmin and Article 18.2(B) of the JOA, disputes between the parties were to be resolved by binding arbitration applying Texas law and International Chamber of Commerce (ICC) Rules. In October 2018, RSM filed an arbitration demand against GdC, alleging a number of claims, including three centered on the Payout dispute.3 In its pre-hearing filings, RSM sought $10,578,123.28 in damages for its primary Payout-related claim, which the arbitrators (hereafter, the Tribunal) labeled Claim 1. RSM explained to the Tribunal the “three steps” it took to reach that number. Step one was based on “revenues that accrued (i.e., petroleum sales) from February 1, 2016 through May 31, 2016,” of which RSM’s 40% share totaled $6,566,497.38. Step two accounted for RSM’s $3,866,616.70 share of “sales proceeds received from February 1, 2016 for petroleum that was delivered prior to February 1, 2016.” And in the third step, RSM added its $145,009.20 share of “sales proceeds received in January 2016 after GdC achieved 100% cost-recovery, but before the February 1, 2016 date of Payout.” RSM asserted two alternate damages computations—referred to by the Tribunal as Claims 2 and 3. Both were contingent on “the Tribunal . . . rul[ing] against RSM regarding the CHL Royalty and conclud[ing] that Payout occurred on June 1, 2016[,] as GdC contends.” RSM expressly urged that the Tribunal need not reach either alternative claim if it “ruled for RSM regarding the CHL Royalty . . . and if it calculate[d] RSM’s damages correctly at $10,578,123.28[.]”

_____________________ 3 RSM raised 23 claims in all. GdC asserted three counterclaims. This appeal concerns only RSM’s claims pertaining to the parties’ Payout dispute.

3 Case: 23-20583 Document: 77-1 Page: 4 Date Filed: 09/19/2024

After extensive discovery and a ten-day hearing, the Tribunal rendered a 142-page “Partial Final Award” addressing the parties’ respective claims.4 The Tribunal ruled in favor of RSM as to its principal Payout claim, Claim 1, and awarded RSM $10,578,123.28 in damages. This award tracked RSM’s “three step” computation and was based on a Payout date of February 1, 2016. The tribunal held that Claims 2 and 3 were moot “based upon the Tribunal’s determination as to RSM’s Claim No. 1.” Shortly after the Tribunal handed down its award, the parties jointly applied to correct two errors and thereby increase RSM’s award by $47,710. GdC separately filed a contested “Application to Correct Award and Address Omitted Claims,” requesting that the Tribunal “correct” the amount awarded on RSM’s Claim 1 and decide Claims 2 and 3, which GdC contended were not moot. GdC did not challenge the Tribunal’s conclusion that GdC had improperly included the CHL Royalty in its Payout calculation or its determination that February 1, 2016 was the proper Payout date. Instead, GdC argued that the Tribunal erroneously included damages for claims related to production revenue that occurred before the Payout date, even though RSM had only prevailed with respect to the improper inclusion of the CHL Royalty. Put differently, GdC argued that the Tribunal erred by factoring into its award damages related to Claims 2 and 3, which the Tribunal never substantively addressed. The Tribunal held a hearing to resolve both the agreed and contested correction requests. The Tribunal questioned the parties regarding ICC Rule 36’s application to GdC’s contested corrections. Under the governing 2017

_____________________ 4 The award was styled “Partial Final Award” because, at the parties’ request, the Tribunal left for subsequent resolution the identity of the prevailing party and an award of interest, attorneys’ fees, and costs of the arbitration. Otherwise, the Tribunal’s decision addressed all the parties’ claims.

4 Case: 23-20583 Document: 77-1 Page: 5 Date Filed: 09/19/2024

version of that rule, an arbitrator was permitted to “correct a clerical, computational or typographical error, or any errors of similar nature contained in an award.” The Tribunal specifically grappled with whether GdC sought “a correction of law,” ostensibly exceeding the Tribunal’s authority, or a “correction of fact,” which the Tribunal read to fall within the bounds of ICC Rule 36. In an “Addendum to Partial Final Award” (the Addendum Award), the Tribunal granted both the agreed corrections and GdC’s contested correction requests. After summarizing each side’s contentions, the Tribunal addressed whether it had the authority to address the “computational errors” raised by GdC.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
117 F.4th 707, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rsm-prod-v-gaz-du-cameroun-ca5-2024.