Royce Homes, L.P. v. Decker Oaks Development II, Ltd. (In Re Decker Oaks Development II, Ltd.)

415 B.R. 239, 2009 U.S. Dist. LEXIS 57763
CourtDistrict Court, S.D. Texas
DecidedJuly 6, 2009
DocketCivil Action No. H-08-2070. Bankruptcy No. 07-35557. Adversary No. 07-3421
StatusPublished

This text of 415 B.R. 239 (Royce Homes, L.P. v. Decker Oaks Development II, Ltd. (In Re Decker Oaks Development II, Ltd.)) is published on Counsel Stack Legal Research, covering District Court, S.D. Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Royce Homes, L.P. v. Decker Oaks Development II, Ltd. (In Re Decker Oaks Development II, Ltd.), 415 B.R. 239, 2009 U.S. Dist. LEXIS 57763 (S.D. Tex. 2009).

Opinion

MEMORANDUM AND ORDER

LEE H. ROSENTHAL, District Judge.

Royce Homes, L.P. appeals from the bankruptcy court’s judgment in this adversary proceeding awarding Decker Oaks Development II, Ltd. $2,309,500 in damages. The damage award was based on the bankruptcy judge’s ruling, following a bench trial, that Royce Homes tortiously interfered with a third party’s earnest money contract to purchase raw land from Decker Oaks for development and that the tortious interference not only caused the third party to exercise its option to cancel the contract during a 30-day “feasibility period,” but also resulted in Decker Oaks’s mortgage lenders foreclosing on the property over a year later. The $2.3 million in damages consisted of the profits Decker Oaks would have made had the sale under the contract closed and the deficiency judgment remaining after its lenders foreclosed. The bankruptcy court also concluded that Royce Homes had materially breached a second contract it had with Decker Oaks, to purchase residential lots in a separate development. The court held that Decker Oaks was not required to release $62,000 that Royce Homes had paid as earnest money under that contract.

*245 Royce Homes appeals both rulings, asking this court to reverse the tortious interference damage award and to order Decker Oaks to release the $62,000 in earnest money. Decker Oaks cross-appeals, arguing that if this court concludes that Royce Homes did not tortiously interfere with an existing contract, it should hold that the bankruptcy court erred in finding no tor-tious interference with a prospective contract.

Based on a careful review of the record and the applicable law, this court reverses the bankruptcy court’s rulings that Royce Homes’s tortious interference with an earnest money contract Decker Oaks had with a third party proximately caused the loss of that contract and resulted in consequential damages that included the deficiency that remained after foreclosure. This court also reverses the bankruptcy court’s ruling that Decker Oaks is entitled to retain the $62,000 of Royce Homes’s earnest money. Decker Oaks’s cross-appeal is denied as moot.

The reasons for these rulings are explained in detail below.

I. Background

A. The Tortious Interference Claim

1. The Earnest Money Contract

Decker Oaks owned raw land north of Houston that it intended to develop as a residential subdivision called “Saratoga Springs.” On September 22, 2001, David Weber, the CFO and manager of the land-development department at Royce Homes, signed a contract with Decker Oaks for Royce Homes to purchase 196 single-family lots in the Saratoga Springs development. The contract specified that Royce Homes would purchase 55 by 120 foot lots for $23,000 per lot and 65 by 125 foot lots for $27,000 per lot. (Docket Entry No. 7, Ex. 1 § 1.02). The contract stated that the lots were described with greater particularity in an attached “Exhibit A.” (Id., Ex. 1 § 1.01). There was no Exhibit A attached to the contract that Weber signed.

Royce Homes’s obligation to purchase the lots was to be secured by $25,000 in earnest money. (Id., Ex. 1 § 1.04). The contract stated that Royce Homes would not be obligated to purchase any lot until “Substantial Completion” of the development. “Substantial Completion” included clearing and grading the lots, installing utility connections, and obtaining zoning and government permits. (Id., Ex. 1 § VI). The contract set a time frame for “Substantial Completion,” stating that “Seller [Decker Oaks] shall use Seller’s good faith efforts to achieve the Substantial Completion requirements by April 1, 2002.” (Id.). The contract gave Royce Homes the right, but not the obligation, to extend the period for up to 90 days if Decker Oaks had not achieved “Substantial Completion” by June 1, 2002. The contract stated:

If Seller has not achieved the Substantial Completion Date by June 1, 2002, Purchaser shall have the right, at Purchaser’s sole discretion, to terminate the Contract, or Purchaser may extend the date for Seller’s achievement of Substantial Completion for one or more periods not exceeding, in the aggregate, ninety (90) days. If Purchaser chooses to terminate the Contract, then the Purchaser shall be entitled to the immediate return of the Earnest Money.

(Id.).

The contract also set out remedies for Royce Homes in the event Decker Oaks defaulted under the contract:

If Seller defaults in performing Seller’s obligations hereunder ... Purchaser shall be entitled, as Purchaser’s sole and exclusive remedy, to (i) waive the con- *246 traetual obligations of Seller in writing; (ii) extend the time for performance by such period of time as may be mutually agreed upon in writing by the Parties hereto; (iii) terminate this Contract and receive a return of the Earnest Money then on deposit; or (iv) enforce specific performance of this Contract as Purchaser’s sole remedy at law.

(Id., Ex. 1 § 5.02).

The contract stated that an “Initial Closing” would occur no later than 30 days after “Substantial Completion.” (Id., Ex. 1 § 3.01). Royce Homes was obligated to purchase 10 lots at the Initial Closing, an additional 10 lots no later than 120 days thereafter, and at least 10 lots every 90 days thereafter until it had purchased 196 lots. (Id., Ex. 1 § 3.02). The contract provided that Royce Homes would pay interest in the amount of 8% per annum on each lot between the Initial Closing and the closing on the particular lot. Weber crossed out the “8%” and wrote in “7%,” initialing the change. (Id., Ex. 1 § 1.03).

On November 16, 2001, Decker Oaks’s principal, Robert Weedn, signed the copy of the Saratoga Springs contract that Weber had signed. Weedn made a handwritten, initialed modification increasing the purchase price on the 55 by 120-foot lots from $23,000 to $23,500. (Id., Ex. 1 § 1.02). Weedn did not initial Weber’s handwritten modification to the interest rate. (Id., Ex. 1 § 1.03). No one from Royce Homes initialed or signed the contract after Weedn’s modification. (Id., Ex. 1 at 18). There was no Exhibit A describing the land attached to the copy that Weedn signed.

Also on November 16, 2001, the parties signed a side agreement that gave Decker Oaks the right to enforce purchase of the first 25 lots by specific performance. (Id., Ex. 2). On January 16, 2002, under the contract, Royce Homes deposited $25,000 in earnest money with the Stewart Title Company. (Id., Ex. 4).

Decker Oaks did not achieve “Substantial Completion” by April 1, 2002, by June I, 2002, or by 90 days thereafter. Decker Oaks did not obtain approval from the City of Tomball for the Saratoga Springs subdivision, a required condition for “Substantial Completion,” until late 2005 due to delays in obtaining permits and problems in meeting the City’s infrastructure requirements. (Id., Exs. 11, 13).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Enplanar, Inc. v. Marsh
11 F.3d 1284 (Fifth Circuit, 1994)
Whitehead v. Food Max of Mississippi, Inc.
163 F.3d 265 (Fifth Circuit, 1999)
United States v. Adkism
180 F.3d 264 (Fifth Circuit, 1999)
Tompkins v. Cyr
202 F.3d 770 (Fifth Circuit, 2000)
Robertson v. Dennis (In Re Dennis)
330 F.3d 696 (Fifth Circuit, 2003)
Rosenzweig v. Azurix Corp.
332 F.3d 854 (Fifth Circuit, 2003)
Anderson v. Siemens Corporation
335 F.3d 466 (Fifth Circuit, 2003)
In Re: Argo Fincl
337 F.3d 516 (Fifth Circuit, 2003)
Schiller v. Physicians Resource Group Inc.
342 F.3d 563 (Fifth Circuit, 2003)
Perry v. Dearing (In Re Perry)
345 F.3d 303 (Fifth Circuit, 2003)
Templet v. Hydrochem Inc.
367 F.3d 473 (Fifth Circuit, 2004)
Bertucci Contracting Corp. v. M/V ANTWERPEN
465 F.3d 254 (Fifth Circuit, 2006)
Anderson v. City of Bessemer City
470 U.S. 564 (Supreme Court, 1985)
United States v. Olano
507 U.S. 725 (Supreme Court, 1993)
United States v. Irene Davis
443 F.2d 560 (Fifth Circuit, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
415 B.R. 239, 2009 U.S. Dist. LEXIS 57763, Counsel Stack Legal Research, https://law.counselstack.com/opinion/royce-homes-lp-v-decker-oaks-development-ii-ltd-in-re-decker-oaks-txsd-2009.