Rorick's, Inc. v. Corporex Dev. & Constr. Mgt., L.L.C.

2017 Ohio 8694
Ohio Court of Appeals·Decided November 20, 2017·No. 2017CA00075·Published·Cited by 1 cases

Opinion

COURT OF APPEALS

STARK COUNTY, OHIO

FIFTH APPELLATE DISTRICT

RORICK'S INC. : JUDGES:

: Hon. Patricia A. Delaney, P.J.

Plaintiff-Appellee : Hon. William B. Hoffman, J.

: Hon. Earle E. Wise, Jr., J.

-vs- :

:

CORPOREX DEVELOPMENT & : CONSTRUCTION MANAGEMENT, LLC : Case No. 2017CA00075 :

Defendant-Appellant : OPINION

CHARACTER OF PROCEEDING: Appeal from the Court of Common Pleas, Case No. 2016CV02670

JUDGMENT: Reversed and Remanded

DATE OF JUDGMENT: November 20, 2017

APPEARANCES: For Plaintiff-Appellee For Defendant-Appellant

OWEN J. RARRIC MARK L. RODIO TERRY A. MOORE 200 Public Square ALETHA M. CARVER Suite 3000 4775 Munson Street Cleveland, OH 44114 Canton, OH 44735-6963

Stark County, Case No. 2017CA00075 2 Wise, Earle, J.

{¶ 1} Defendant-Appellant, Corporex Development & Construction Management, LLC, (Corporex), appeals the May 3, 2017 judgment entry of the Stark County Court of Common Pleas denying Corporex’s motion to stay pending arbitration. Plaintiff-appellee is Rorick’s Inc.

FACTS AND PROCEDURAL HISTORY

{¶ 2} In April 2014, CPX Canton Airport, LLC (Owner) contracted with Corporex for the construction of an Embassy Suites Hotel in North Canton (the Project). Corporex then entered into a contract (Prime Contract) with Bennett Construction Management (BCM) to serve as the Prime Contractor to manage and direct the project.

{¶ 3} A year later, in April 2015, BCM awarded all of the drywall work on the project - floors one through six - and acoustic ceiling tiles to Rorick’s Inc. (Rorick’s). Rick Rorick is the president of Rorick’s, Inc. BCM presented Rorick with a Subcontractor Agreement (Subcontract) on April 24, 2015. Rorick refused to sign the document because he objected to the arbitration provision. The initial amount discussed between BCM and Rorick for completion of Rorick’s scope of work was $1,153,000.

{¶ 4} The Subcontract included “the attached Standard Conditions dated June 1, 1999.” However, the Standard Conditions attached to the Subcontract were actually dated November 1, 2013.

{¶ 5} Despite never signing a contract, Rorick’s began its scope of work on the Project immediately. Rorick submitted one pay application to BCM for work completed through April 2015 for $130,950 and received payment for the same. He submitted other pay applications to BCM for work completed in May, June, and July for more than

Stark County, Case No. 2017CA00075 3

$300,000, but by the end of July had not been paid. These pay applications included charges for work completed by Rorick’s on the tower floors of the project. This work was beyond that originally contemplated between BCM and Rorick’s. These change orders expanded Rorick’s scope of work and added $186,130 to the original stated cost.

{¶ 6} During the course of the Project, there were significant disputes between BCM and Corporex due to BCM’s mismanagement of the Project. On July 21, 2015, Rorick’s received a letter from Corporex advising it that BCM had abandoned the project. Corporex then assumed some of BCM’s duties and hired Summit Construction to assume BCM’s project management obligations.

{¶ 7} Corporex, through Michael O’Donnell, asked Rorick’s to stay on the job, but requested a copy of Rorick’s signed Subcontract, invoices, and any change orders that Rorick’s entered into with BCM before BCM abandoned the Project. According to Rorick, O’Donnell assured him he would be paid for the outstanding amounts owed by BCM and that his scope of work would not change.

{¶ 8} On August 10, 2015, Rorick received a draft Assignment and Assumption Agreement (Assignment) from Corporex. Again, Rorick refused to sign the document. This time however, Rorick did not object to the arbitration provisions, but rather because of a rumor he had heard that Corporex was going to hire someone else to complete the drywall and acoustic ceiling tiles on the first floor, thus narrowing Rorick’s original scope of work.

{¶ 9} The same day, Rorick’s attached a proposed addendum to the Assignment.

The addendum at paragraph 9 would have prohibited Corporex from narrowing Rorick’s scope of work. The addendum did not, however, make any mention of dispute resolution.

Stark County, Case No. 2017CA00075 4

Rorick did not discuss the arbitration provisions referenced in the Assignment with anyone from Corporex, but did consult his counsel and believed he was not subject to the arbitration provisions of the Subcontract.

{¶ 10} On August 11, 2015, Corporex rejected paragraph 9 of Rorick’s addendum, and further requested Rorick’s to submit documentation to support its claim that additional monies were owed for work on the tower floors of the Project.

{¶ 11} Rorick’s submitted a second proposed addendum on August 13, 2015, deleting the prohibition on narrowing its scope of work and instead offering additional workers for completion of the first floor work. The same day, Corporex responded and asked Rorick’s to provide three additional pieces of information – cost, time to completion, and how many of the additional workers would be “hangers,” i.e, workers hanging drywall as opposed to performing finishing work.

{¶ 12} The next day, Rorick’s responded that the drywall installation would take twice as long as normal due to conditions on the Project, but provided no actual time frame. By August 20, 2015, after some back and forth, Rorick’s still had not provided Corporex the answers it sought. Corporex thus removed the first floor from the scope of Rorick’s work and notified Rorick’s in writing of the same on August 21, 2015. Corporex presented Rorick’s with a written change order removing the first floor work from Rorick’s scope of work. Rorick’s refused to sign the change order and responded that the removal of the first floor work was a breach of its Subcontract with BCM.

{¶ 13} Meanwhile, Rorick’s still had not been paid for May, June, July, and August, was unable to make payroll, and was further concerned about possible bankruptcy.

Rorick’s had expected payment at the beginning of August based on O’Donnell’s oral assurances that it would be paid the amount owed Rorick’s by BCM.

{¶ 14} Corporex advised, however, that before Rorick’s could be paid, the Assignment must be signed. On August 26, 2015, Rorick chose to sign the Assignment. Rorick’s made some changes to the document, none of which concerned dispute resolution. The Assignment incorporated the previously unsigned Subcontract and the Prime contract to the extent applicable to Rorick’s scope of work on the Project.

{¶ 15} Thereafter, Corporex released overdue payments to Rorick’s.

{¶ 16} On January 28, 2016 Rorick’s requested mediation in an attempt to resolve its disputes with Corporex over reduction in its scope of work and monies owed. Mediation was conducted in May 2016 and was unsuccessful.

{¶ 17} On December 8, 2016, Rorick’s filed a complaint against Corporex alleging fraudulent inducement, breach of contract, violation of the prompt pay act, promissory estoppel, unjust enrichment, and defamation. Rorick’s claimed damages exceeding $100,000. On January 13, 2017, Corporex filed an answer and a motion to stay pending arbitration. Rorick’s filed a memorandum in opposition.

{¶ 18} An evidentiary hearing was held March 2, and 6, 2017 on Corporex’s motion to stay and Rorick’s fraudulent inducement argument. Following the hearing, Rorick’s and Corporex each filed proposed findings of fact and conclusions of law.

{¶ 19} On May 3, 2017, the trial court issued its opinion denying Corporex’s motion.

Corporex then filed this appeal. Corporex presents two assignments of error:

Stark County, Case No. 2017CA00075 6

I

{¶ 20} "THE TRIAL COURT ERRED IN DENYING DEFENDANT-APPELLANT CORPOREX DEVELOPMENT & CONSTRUCTION MANAGEMENT, LLC'S ("CORPOREX") MOTION TO STAY PENDING ARBITRATION ("MOTION") AND IN FINDING THAT PLAINTIFF-APPELLEE RORICK'S INC. ("RORICK'S") DID NOT AGREE TO ARBITRATE DISPUTES IN EXCESS OF $1000,000 BASED ON INCORRECT LEGAL CONCLUSIONS."

II

Free access — add to your briefcase to read the full text and ask questions with AI

Rorick's, Inc. v. Corporex Dev. & Constr. Mgt., L.L.C., 2017 Ohio 8694 (Ohio Ct. App. 2017).

2017 Ohio 8694 (Rorick's, Inc. v. Corporex Dev. & Constr. Mgt., L.L.C.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Katz v. Katz
2018 Ohio 3210 (Ohio Court of Appeals, 2018)