Rorick's, Inc. v. Corporex Dev. & Constr. Mgt., L.L.C.

2017 Ohio 8694
CourtOhio Court of Appeals
DecidedNovember 20, 2017
Docket2017CA00075
StatusPublished
Cited by1 cases

This text of 2017 Ohio 8694 (Rorick's, Inc. v. Corporex Dev. & Constr. Mgt., L.L.C.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rorick's, Inc. v. Corporex Dev. & Constr. Mgt., L.L.C., 2017 Ohio 8694 (Ohio Ct. App. 2017).

Opinion

[Cite as Rorick's, Inc. v. Corporex Dev. & Constr. Mgt., L.L.C., 2017-Ohio-8694.]

COURT OF APPEALS STARK COUNTY, OHIO FIFTH APPELLATE DISTRICT

RORICK'S INC. : JUDGES: : Hon. Patricia A. Delaney, P.J. Plaintiff-Appellee : Hon. William B. Hoffman, J. : Hon. Earle E. Wise, Jr., J. -vs- : : CORPOREX DEVELOPMENT & : CONSTRUCTION MANAGEMENT, LLC : Case No. 2017CA00075 : Defendant-Appellant : OPINION

CHARACTER OF PROCEEDING: Appeal from the Court of Common Pleas, Case No. 2016CV02670

JUDGMENT: Reversed and Remanded

DATE OF JUDGMENT: November 20, 2017

APPEARANCES:

For Plaintiff-Appellee For Defendant-Appellant

OWEN J. RARRIC MARK L. RODIO TERRY A. MOORE 200 Public Square ALETHA M. CARVER Suite 3000 4775 Munson Street Cleveland, OH 44114 Canton, OH 44735-6963 Stark County, Case No. 2017CA00075 2

Wise, Earle, J.

{¶ 1} Defendant-Appellant, Corporex Development & Construction Management,

LLC, (Corporex), appeals the May 3, 2017 judgment entry of the Stark County Court of

Common Pleas denying Corporex’s motion to stay pending arbitration. Plaintiff-appellee

is Rorick’s Inc.

FACTS AND PROCEDURAL HISTORY

{¶ 2} In April 2014, CPX Canton Airport, LLC (Owner) contracted with Corporex for

the construction of an Embassy Suites Hotel in North Canton (the Project). Corporex then

entered into a contract (Prime Contract) with Bennett Construction Management (BCM)

to serve as the Prime Contractor to manage and direct the project.

{¶ 3} A year later, in April 2015, BCM awarded all of the drywall work on the project

- floors one through six - and acoustic ceiling tiles to Rorick’s Inc. (Rorick’s). Rick Rorick

is the president of Rorick’s, Inc. BCM presented Rorick with a Subcontractor Agreement

(Subcontract) on April 24, 2015. Rorick refused to sign the document because he

objected to the arbitration provision. The initial amount discussed between BCM and

Rorick for completion of Rorick’s scope of work was $1,153,000.

{¶ 4} The Subcontract included “the attached Standard Conditions dated June 1,

1999.” However, the Standard Conditions attached to the Subcontract were actually dated

November 1, 2013.

{¶ 5} Despite never signing a contract, Rorick’s began its scope of work on the

Project immediately. Rorick submitted one pay application to BCM for work completed

through April 2015 for $130,950 and received payment for the same. He submitted other

pay applications to BCM for work completed in May, June, and July for more than Stark County, Case No. 2017CA00075 3

$300,000, but by the end of July had not been paid. These pay applications included

charges for work completed by Rorick’s on the tower floors of the project. This work was

beyond that originally contemplated between BCM and Rorick’s. These change orders

expanded Rorick’s scope of work and added $186,130 to the original stated cost.

{¶ 6} During the course of the Project, there were significant disputes between

BCM and Corporex due to BCM’s mismanagement of the Project. On July 21, 2015,

Rorick’s received a letter from Corporex advising it that BCM had abandoned the project.

Corporex then assumed some of BCM’s duties and hired Summit Construction to assume

BCM’s project management obligations.

{¶ 7} Corporex, through Michael O’Donnell, asked Rorick’s to stay on the job, but

requested a copy of Rorick’s signed Subcontract, invoices, and any change orders that

Rorick’s entered into with BCM before BCM abandoned the Project. According to Rorick,

O’Donnell assured him he would be paid for the outstanding amounts owed by BCM and

that his scope of work would not change.

{¶ 8} On August 10, 2015, Rorick received a draft Assignment and Assumption

Agreement (Assignment) from Corporex. Again, Rorick refused to sign the document.

This time however, Rorick did not object to the arbitration provisions, but rather because

of a rumor he had heard that Corporex was going to hire someone else to complete the

drywall and acoustic ceiling tiles on the first floor, thus narrowing Rorick’s original scope

of work.

{¶ 9} The same day, Rorick’s attached a proposed addendum to the Assignment.

The addendum at paragraph 9 would have prohibited Corporex from narrowing Rorick’s

scope of work. The addendum did not, however, make any mention of dispute resolution. Stark County, Case No. 2017CA00075 4

Rorick did not discuss the arbitration provisions referenced in the Assignment with anyone

from Corporex, but did consult his counsel and believed he was not subject to the

arbitration provisions of the Subcontract.

{¶ 10} On August 11, 2015, Corporex rejected paragraph 9 of Rorick’s addendum,

and further requested Rorick’s to submit documentation to support its claim that additional

monies were owed for work on the tower floors of the Project.

{¶ 11} Rorick’s submitted a second proposed addendum on August 13, 2015,

deleting the prohibition on narrowing its scope of work and instead offering additional

workers for completion of the first floor work. The same day, Corporex responded and

asked Rorick’s to provide three additional pieces of information – cost, time to completion,

and how many of the additional workers would be “hangers,” i.e, workers hanging drywall

as opposed to performing finishing work.

{¶ 12} The next day, Rorick’s responded that the drywall installation would take

twice as long as normal due to conditions on the Project, but provided no actual time

frame. By August 20, 2015, after some back and forth, Rorick’s still had not provided

Corporex the answers it sought. Corporex thus removed the first floor from the scope of

Rorick’s work and notified Rorick’s in writing of the same on August 21, 2015. Corporex

presented Rorick’s with a written change order removing the first floor work from Rorick’s

scope of work. Rorick’s refused to sign the change order and responded that the removal

of the first floor work was a breach of its Subcontract with BCM.

{¶ 13} Meanwhile, Rorick’s still had not been paid for May, June, July, and August,

was unable to make payroll, and was further concerned about possible bankruptcy. Stark County, Case No. 2017CA00075 5

Rorick’s had expected payment at the beginning of August based on O’Donnell’s oral

assurances that it would be paid the amount owed Rorick’s by BCM.

{¶ 14} Corporex advised, however, that before Rorick’s could be paid, the

Assignment must be signed. On August 26, 2015, Rorick chose to sign the Assignment.

Rorick’s made some changes to the document, none of which concerned dispute

resolution. The Assignment incorporated the previously unsigned Subcontract and the

Prime contract to the extent applicable to Rorick’s scope of work on the Project.

{¶ 15} Thereafter, Corporex released overdue payments to Rorick’s.

{¶ 16} On January 28, 2016 Rorick’s requested mediation in an attempt to resolve

its disputes with Corporex over reduction in its scope of work and monies owed. Mediation

was conducted in May 2016 and was unsuccessful.

{¶ 17} On December 8, 2016, Rorick’s filed a complaint against Corporex alleging

fraudulent inducement, breach of contract, violation of the prompt pay act, promissory

estoppel, unjust enrichment, and defamation. Rorick’s claimed damages exceeding

$100,000. On January 13, 2017, Corporex filed an answer and a motion to stay pending

arbitration. Rorick’s filed a memorandum in opposition.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Katz v. Katz
2018 Ohio 3210 (Ohio Court of Appeals, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
2017 Ohio 8694, Counsel Stack Legal Research, https://law.counselstack.com/opinion/roricks-inc-v-corporex-dev-constr-mgt-llc-ohioctapp-2017.