Romano v. ROSSANO CONSTRUCTION CO. INC.

171 N.E.2d 853, 341 Mass. 718, 1961 Mass. LEXIS 841
CourtMassachusetts Supreme Judicial Court
DecidedFebruary 3, 1961
StatusPublished
Cited by10 cases

This text of 171 N.E.2d 853 (Romano v. ROSSANO CONSTRUCTION CO. INC.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Romano v. ROSSANO CONSTRUCTION CO. INC., 171 N.E.2d 853, 341 Mass. 718, 1961 Mass. LEXIS 841 (Mass. 1961).

Opinion

Cutter, J.

The plaintiff seeks to recover for injuries sustained when, on the evening of January 8, 1958, she fell on a public way. She alleged (count 1) that Bossano Construction Company, Inc. (Construction), negligently collected water upon city land upon which it was erecting concrete walls and negligently discharged water in definite channels, by means of holes in such walls, into the street, where it formed an artificial accumulation of ice. She alleged also (count 4) that Construction created “a nui *719 sauce by the . . . construction work, so that an artificial accumulation of ice was formed. ’ ’ The case is here on the plaintiff’s exceptions to the action of the judge in directing a verdict for the defendant on each count. The evidence is stated in its aspect most favorable to the plaintiff.

In January, 1957, the city started to build a school on a lot in East Boston with street frontage of about 360 feet. The lot had been open with some light shrubbery and small trees on it. Both before and after January, 1957, the land rose sharply from the street. Retaining walls were built at least twenty to twenty-five feet above a metal fence inside the sidewalk at the bottom edge of an embankment.

During the second half of December, 1957, “fresh earth . . . was packed against the retaining walls” and on the ‘ steep slope ’ ’ between the walls and the fence. A photograph shows that, in the retaining walls, at a level about eight to ten feet above the upper edge of the embankment, there were “weep holes” each apparently a little less than a foot in diameter, at intervals of about fifteen feet. Behind the retaining wall earth “goes up nearly to the top of the wall . . . [and] above the weep holes.” A witness testified that “ice formed on the weep holes . . . and a considerable amount of water ran out from the weep holes down the ground, gouged out the dirt,” and flowed “over the sidewalk and into the street.” 2 “ [T]here is a sewer at the base of the fence between the sidewalls and the street” and one “just at the bottom of the incline on” the street. This witness “noticed” that, on January 2,1958, on the street, “there was ice forming and out of the weep holes it was like ice . . . cascading out.” This condition “was building up” during the next few days. “ [0]n January 7 . . . he observed the same thing, more ice on the ground than . .. before.” The “ice was one big mass . .. approxi *720 mately 12 feet wide from the curb and . . . approximately 75 to 100 feet long.” On that day, “there were gullies in the dirt piled up in front of the retaining walls.” These gullies were filled in with more earth between January 8 and April 24, 1958, when some of the pictures were taken. On January 8,1958, there was a snow storm “about 3 or 4 inches. ’ ’ The plaintiff ‘ ‘ never showed ’ ’ this witness where she fell. He “was not in that area on January 8,” and “did not know what the conditions were” on that day.

The plaintiff testified that at the time of the accident the snow had not been plowed. She slipped and fell “about six feet from the sidewalk” on some ice as she walked down the street on “a clear night,” in “car tire tracks.’’ A man tried to help her and he fell too. “ [S]he observed that the ground where she fell was ice, all ice underneath, as far as she could see around her,” and “the entire area was covered with snow.”

In February, 1957, Construction had entered into a contract (with plans and specifications not in evidence) to build a school on the city’s lot. Retaining walls were put up prior to October 7, 1957, and on that date Construction was “notified to remove excavated materials deposited at retaining walls.” There was no evidence whether this had been done. On January 3, 1958, progress was “slow due to freezing weather conditions.” On January 6, 1958, crushed stone was placed “for area drains and trenching for ground drain in area” which was “wet, muddy due to thawing.” The evidence does not disclose where the materials were placed or where the drains were to be. The progress report for January 8, 1958, referred to “heavy snow, rain during the evening of the 7ith, working progress . . . slow, slippery due to ice and snow accumulation.”

An engineer, called by the plaintiff, testified that he had studied the plans and specifications, that the water absorption qualities of the city land were very poor and it had a high ground water level. There “was evidence of ground water leaking out from the surface.” The pictures indicated to this witness “that there was water behind the wall . . . [which] did not necessarily originate from under the *721 ground,” although he could not say “whether it. . . seeped down through the dirt until it reached the weep hole. ’ ’ The purpose of the weep holes was not “to let water through” but “to relieve water pressure after construction has been completed.” In the opinion of this witness “good construction practice, in addition to . . . weep holes . . . called for a ditching to remove the water that comes through those weep holes ’ ’ which would ‘ ‘lead into the nearest place where you can dispose of” the water without inconvenience. The nearest place would be “one of the catch basins,” the locations of which are not clear from the record.

There was no evidence about what the plans and specifications were or that Construction in any manner failed to follow them. From the testimony that progress reports were still being made, it could be inferred that Construction was still doing some work on the city lot. The evidence, however, did not show -the extent of that work or of the responsibilities still resting upon Construction.

So far as appears, Construction was merely doing work that it was hired to do in the manner specified. The only suggestion in the evidence that the plans may have been in any respect deficient was the testimony of the engineer called by the plaintiff that good practice called for ditching. This testimony, however, did not disclose whether the plans failed to provide for proper drainage. This testimony also did not show that, if the plans were followed, the danger of improper collection and drainage of water was so apparent that a contractor like Construction should have appreciated the danger and realized that the plans were inadequate. Construction should be “charged with only so much competence to pass on plans as such contractors ordinarily have.” The “standard of responsibility for the ordinary contractor is that usually possessed by persons in his place; and it should be proved like any other such fact.” See Person v. Cauldwell-Wingate Co. Inc. 187 F. 2d 832, 836 (2d Cir.), cert. den. 341 U. S. 936. Beyond the circumstance that Construction was general contractor on the school building project, it was not shown whether Construction was an ordinary contractor, or one specializ *722 ing in particular work. There was no evidence about the extent of Construction’s competence or about the expert knowledge of soil conditions the members of its staff had or should have had.

It is said in Restatement: Torts, § 384, “One who on behalf of the possessor of land erects a structure or creates any other condition” on the land “is subject to the same liability ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Soave v. National Velour Corp.
863 A.2d 186 (Supreme Court of Rhode Island, 2004)
Churilla v. Wachusetts
First Circuit, 1992
Shell v. Sirois
1989 Mass. App. Div. 29 (Mass. Dist. Ct., App. Div., 1989)
Robert E. McDonough v. Whalen
304 N.E.2d 199 (Massachusetts Appeals Court, 1973)
McDonald v. Frontier Lanes, Inc.
272 N.E.2d 369 (Appellate Court of Illinois, 1971)
Acker v. City of Haverhill
231 N.E.2d 907 (Massachusetts Supreme Judicial Court, 1967)
Arnold v. Edelman
375 S.W.2d 167 (Supreme Court of Missouri, 1964)
Baker v. Pagani Bros.
25 Mass. App. Dec. 117 (Mass. Dist. Ct., App. Div., 1962)

Cite This Page — Counsel Stack

Bluebook (online)
171 N.E.2d 853, 341 Mass. 718, 1961 Mass. LEXIS 841, Counsel Stack Legal Research, https://law.counselstack.com/opinion/romano-v-rossano-construction-co-inc-mass-1961.