Bullard v. Mattoon

8 N.E.2d 348, 297 Mass. 182, 1937 Mass. LEXIS 754
Massachusetts Supreme Judicial Court·Decided April 2, 1937·Published·Cited by 25 cases

Opinion

Donahue, J.

The plaintiff testified that, while walking on the sidewalk on a public highway in Pittsfield, she'slipped on an accumulation of ice three or four inches high, fell and was injured. It was agreed that adjoining the sidewalk was a building owned by the defendants, the wall of which was built substantially on the street line, that is, on the inner line of the sidewalk. It was also agreed that, over a plate glass window on the side of the building nearest the street, there was a projecting cornice, nine feet long and one foot wide, which overhung the sidewalk and that on~the second íióor of the building just beyond the end of the cornice there were two windows under each of which was a granite ledge three feet long, the outer edges of which projected over the sidewalk about an inch. There were no gutters or conductors on the street side of the building.

There was testimony that at the time of the plaintiff’s injury there was snow on the cornice and on the window [184]*184ledges and icicles were hanging therefrom; that water from the melting snow was dripping from the icicles; and^hat there'was a ridge oFIce^underneath on the sidewalk running parallel with the~Euilding. There was evidence warranting the conclusion that the ridge of ice had been formed by water dropping from the icicles on the cornice and window ledges and freezing on the sidewalk and that the plaintiff’s injury was due to slipping on a mound-shaped area of ice which was part of that ridge. There was evidence that the structural condition of the side of the building nearest the sidewalk had been the same for twenty-six years, that the defendants’ agent in charge of the premises was at the building each day and that a similar ridge of ice had been formed on the sidewalk at an earlier time on a day following a snow storm. There had been a six-inch fall of snow the night before the plaintiff’s injury and a similar fall of snow two nights before. The bill of exceptions recites that the only questions raised by the exceptions relate to the judge’s instructions to the jury, his refusals to instruct the jury as requested by the plaintiff and his exclusion of certain evidence offered by the plaintiff.

The case was tried in the Superior Court and there was a verdict for the defendants. The plaintiff excepted to the refusal of the judge to give her first and second requests and to a portion of the judge’s charge pertaining to the same subject matter. These are the only exceptions argued before us.

In the course of his charge the judge instructed the jury “as a matter of law,” that if a landowner in possession of property “by negligent act in construction, collects water into a definite channel in any way and then turns it out on the highway or a street where, through the operation of natural causes, ice forms, itthen becomes, or may become. under some circumstances, a condition which the jury might say was a nuisance, and if an individual does that, of~course he is liable To"any damage that results from maintaining a nuisance.” The plaintiff concedes in her brief that if the words “by negligent act in construction” were omitted, [185]*185this portion of the charge would be in substantial accord with her first request for a ruling.

Following the portion of the charge above quoted the judge went on to say: “Or if the defendant maintains a building with structures or anything added to it so that those structures, through either improper or negligent construction or improper and negligent maintenance, cause water to flow in channels other than the usual channels, and it flows out on the sidewalk and freezes and then causes injury to a person, the plaintiff can recover.” The plaintiff concedes in her brief that this statement would be substantially in accord with her second request if the words “through either improper or negligent construction or improper and negligent maintenance” were omitted.

At the close of the charge the plaintiff’s attorney claimed exceptions “to that part of your charge where you said the plaintiff must prove negligence in the construction” or maintenance of the building and to the failure of the judge to" grant his requests for rulings. A discussion then followed in which the attorney stated: “My contention is that you don’t need to prove negligence if you prove that the building is so constructed that in the natural course of events water will fall and freeze,” and the judge declined to rule that the plaintiff did not have to prove negligence.

At the- outset of the charge the judge stated that a landowner has the right to erect a building upon the street line and to have eaves, cornices or window sills overhanging the street line in the absence of a specific ordinance to the contrary, that the obligation of such an owner is “To use the methods in the construction and maintenance of his building that are considered good building construction methods,” and that “if he does that and maintains it with good care, in good condition, and by that I mean the condition that the ordinarily careful and prudent individual would consider proper,” he has fulfilled his obligation.

Following the portions of the charge first above quoted the judge instructed the jury, “there is no liability at all for snow and ice unless there is something negligent con[186]*186nected with it ... . That means failure to do that which á person should do, or an individual doing something in the construction of a building that is not in accordance with the proper structural method or proper care and maintenance” of the building. At the end of the portion of the charge dealing with the matter of liability the judge instructed the jury that the plaintiff could not recover unless she proved: “that there was negligent construction in the building which resulted in . . . turning water in a channel of some sort on the sidewalk and that it was that water which froze and did the damage.”

The basis of the liability of an owner of land or buildings for injury received by a traveller on an adjacent highway due to ice formed from water coming from the owner’s premises, is the creation of a condition on the highway dangerous to those lawfully using it. A landowner “has no right to collect water into a definite channel by a spout or otherwise and^DourTFupoffi a public way. If he does this and"througfT~tKe operation of naturalhauses the water freezes, he is the efficient cause in the creation of a nuisance and is liable for whatever damage ensues as a probable consequence.” Field v. Gowdy, 199 Mass. 568, 570-571. This principle applies whether water so collected is poured directly on the street, Shipley v. Proctor, 177 Mass. 498, Leahan v. Cochran, 178 Mass. 566, Cerchione v. Hunnewell, 215 Mass. 588; or is deposited some distance from the street but flows down a concrete walk, Field v. Gowdy, 199 Mass. 568; or a sloping bank, Cochran v. Barton, 233 Mass. 147, or other graded area on the owner’s premises, to the highway. It applies also where a building is so constructed that a portion of it overhangs the street and water drops therefrom to tire sidewalk underneath and freezes, Marston v. Phipps, 209 Mass. 552, Stefani v. Freshman, 232 Mass. 354, Allen v. Salmansohn, 254 Mass. 500; and where water drops from icicles formed on an overhanging part of a building and freezes on the sidewalk, Solomon v. Welshman, 265 Mass. 423.

Free access — add to your briefcase to read the full text and ask questions with AI

Bullard v. Mattoon, 8 N.E.2d 348, 297 Mass. 182, 1937 Mass. LEXIS 754 (Mass. 1937).

8 N.E.2d 348 (Bullard v. Mattoon) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Larder v. Jennings
1981 Mass. App. Div. 35 (Mass. Dist. Ct., App. Div., 1981)
Pritchard v. Mabrey
260 N.E.2d 712 (Massachusetts Supreme Judicial Court, 1970)
Romano v. ROSSANO CONSTRUCTION CO. INC.
171 N.E.2d 853 (Massachusetts Supreme Judicial Court, 1961)
Delano v. Mother's Super Market, Inc.
163 N.E.2d 920 (Massachusetts Supreme Judicial Court, 1960)
Berman v. Massachusetts Building Trust
123 N.E.2d 388 (Massachusetts Supreme Judicial Court, 1954)
Laskowski v. Manning
91 N.E.2d 231 (Massachusetts Supreme Judicial Court, 1950)
Clark v. New York Central Railroad
83 N.E.2d 871 (Massachusetts Supreme Judicial Court, 1949)
Conboy v. Boston Mutual Life Insurance
82 N.E.2d 597 (Massachusetts Supreme Judicial Court, 1948)
Ferreira v. Gross
80 N.E.2d 481 (Massachusetts Supreme Judicial Court, 1948)
Hooper v. Kennedy
11 Mass. App. Div. 209 (Mass. Dist. Ct., App. Div., 1946)
Whittaker v. Town of Brookline
60 N.E.2d 85 (Massachusetts Supreme Judicial Court, 1945)
Tomasunas v. Khoury
51 N.E.2d 325 (Massachusetts Supreme Judicial Court, 1943)
Lamereaux v. Tula
44 N.E.2d 789 (Massachusetts Supreme Judicial Court, 1942)
Cavanaugh v. Texas Distributing Co.
45 N.E.2d 142 (Ohio Court of Appeals, 1942)
Sullivan v. Long
37 N.E.2d 478 (Massachusetts Supreme Judicial Court, 1941)
Jones v. Hayden
37 N.E.2d 243 (Massachusetts Supreme Judicial Court, 1941)
Cobb v. Salt River Valley Water Users' Ass'n
114 P.2d 904 (Arizona Supreme Court, 1941)
Perry v. Boston & Maine Railroad
1 Mass. App. Dec. 12 (U.S. District Court, 1941)
Nelson v. Economy Grocery Stores Corp.
25 N.E.2d 986 (Massachusetts Supreme Judicial Court, 1940)
Blanchard v. Stone's Inc.
24 N.E.2d 688 (Massachusetts Supreme Judicial Court, 1939)