Connor, J.

We concur with, his Honor’s view in regard to the measure of duty which the railroad company owed to the plaintiff in constructing its roadbed and track over her land. We further concur with him in the opinion that when defendant contractor entered upon the land for the purpose of constructing the roadbed and track, pursuant to the plans and specifications made by the engineers, it came under a legal liability‘to use all reasonable efforts to protect.plaintiff’s land and the crops growing thereupon from damage, and for negligent failure to meet this standard of duty both the railroad and defendant are liable. There was ample evidence to sustain the plaintiff’s allegation and the verdict of the jury in this respect. The defendant’s motion for judgment of nonsuit, therefore, was properly denied.

The questions presented upon defendant’s exceptions pointed to the third issue are much more serious. We do not find any evidence of negligence on the part of defendant in performing the work, constructing the roadbed, in accordance with the plans and specifications furnished to it by the company’s engineer. The only evidence upon this phase of the case comes from plaintiff’s witness, Colvin, who says that he was the engineer. “White & Co. had nothing to do with the plan and diagram; they had to build the railroad as I directed. I was in charge of that section and I represented the railroad compány; they built this according to the lines I laid out. I put the size and position of the pipes on the map, and they put it in according to that. White & Co. had no authority over me. If there is any defect in the ditches I should say it was due to the plans of the railroad. They carried out the general plans as I made them.” It is apparent, therefore, upon plaintiff’s evidence — and there is none to the contrary — that whatever permanent damage plaintiff’s land sustained is due to the mistake of the engineer in fixing the size of the drainpipe. It is alleged in the complaint that defendant began work in June, 1906, and concluded 1’January, 19,07. It is manifest that for all damage sustained by injury to the crop of 1906 plaintiff has recovered in this action on the first and second issues. It is in evidence that plaintiff sued the *203 railroad company in another action for “damage and injury to crops growing on the land,” and her tenant recovered pay from defendant for Ms interest in the crops of 1906. It is clear that full compensation bas been recovered for all damage sustained prior to the institution of this action 29 May, 1907. Is defendant, an independent contractor, liable for permanent damage to the land by reason of the mistake of the engineer of the railroad company in fixing the size of the drain? It was the absolute duty of the company to provide a sufficient drain through its roadbed and thereby avoid ponding water upon plaintiff’s land. There is no question of negligence involved. The principle controlling the liability of the railroad is laid down by Shepherd, C. J., in Staton v. Railroad, 111 N. C., 278. Applied to this case, the railroad was entitled to construct its roadbed across plaintiff’s land, but in doing so was not entitled to close up a ditch draining the land. It was under an absolute duty to provide means sufficient to.permit the water to flow under or through the roadbed, as it did when the right of way was granted. For a failure to make such provision it was liable to an action when substantial damage was sustained — that is, the cause of action accrued from that time, and not from the time the roadbed was constructed. Staton v. Railroad, 147 N. C., 428; Ridley v. Railroad, 118 N. C., 996. The cause of action, therefore, is not for a trespass committed in building the road, but for injury caused by maintaining a nuisance whereby plaintiff’s land is “sogged and soured.” For this the plaintiff may, as against the railroad company, recover' in one action permanent damages, for the reason that the structure is permanent. The road, upon paying the judgment, acquires an easement to maintain its roadbed and track for the reasons set forth in Ridley’s case, supra, and many others, including Beasley v. Railroad, 147 N. C., 362; Revisal, see. 394. If defendant be liable at all for constructing the roadbed according to the plans and specifications furnished by the railrojid company’s engineers, it certainly cannot be so fox any other damage than accrued prior to the completion of the work and delivery to the owner. There is much doubt whether, in the absence of any negligence in construction, a builder or contractor is liable to third parties for damages caused by mistake in *204 tbe architect or engineer. In Pearson v. Zable, 78 Ky., 168, a municipal corporation prescribed tbe plan for making street improvement, and employed defendants to perform tbe 'work, wbicb resulted, by reason of tbe defective plan, in injury to an owner of adjoining lots. Tbe court beld tbat tbe town was liable, but, in respect to tbe contractor, said: “It is not alleged tbat tbe appellants did not grade tbe street in all respects as required by tbe ordinance and contracts, and we must therefore assume tbat they did. "What they did having been done under authority of law, they are not responsible for injury resulting to tbe appellee in consequence of tbe failure to provide an outlet for tbe water accumulating in tbe street, or for tbe consequences resulting from it. It was not their duty, but tbe duty of the city, to provide plans for tbe work and'to guard against unnecessary injury to tbe property.” Tbe distinction between liability for negligent construction and for injuries resulting from errors of tbe engineers is stated by tbe. editor of tbe Am. and Eng. Ene. (YoL 16, p. 208). Tbe railroad company is not liable for' injuries caused to persons or property by tbe wrongful act of tbe contractor “for failure to provide drains in constructing tbe railroad, whereby injuries result before tbe road is turned over to tbe railroad company. * * * An independent contractor is not liable, as a general rule, for injuries to a third person accruing after bis completion of tbe work and its acceptance by tbe employer.” There are exceptions to tbe general rule, but tbe present case does not' come within them. Curtin v. Somersett, 140 Penn. St., 70; 23 Am. St. Rep., 220. It is manifest tbat upon tbe evidence in this case tbe only damage sustained by tbe plaintiff is caused by tbe failure of tbe engineers to provide for a drain of sufficient size. There is, so far as we can perceive, no evidence tbat tbe land was “sogged and soured” at tbe time tbe road was completed and turned over to tbe company. No cause of action, therefore, accrued against tbe defendant, because there was no trespass on her property and no substantial injury sustained at tbat time. For damages resulting thereafter tbe company was liable for maintaining a nuisance resulting in injury. Under tbe common-law system of procedure tbe plaintiff’s action would be trespass on tbe case and not quare clausum frigit.

*205 Again, if defendant was liable at all, tbe damages could be assessed only to tbe time of tbe trial. Tbe reasons upon wbicb permanent damages are allowed to be• assessed against'a railroad company, or any other corporation having tbe right of eminent domain, do not apply to tbe defendant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Thrift v. Food Lion, Inc.
433 S.E.2d 481 (Court of Appeals of North Carolina, 1993)
Romano v. ROSSANO CONSTRUCTION CO. INC.
171 N.E.2d 853 (Massachusetts Supreme Judicial Court, 1961)
Price v. Johnston Cotton Co. of Wendell
40 S.E.2d 344 (Supreme Court of North Carolina, 1946)

Cite This Page — Counsel Stack

Bluebook (online)
63 S.E. 942, 150 N.C. 199, 1909 N.C. LEXIS 28, Counsel Stack Legal Research, https://law.counselstack.com/opinion/willis-v-white-nc-1909.