Roger Perry and Doris Perry v. Donald Van Hise and Josephine Van Hise, Individually and D/B/A Van Hise Construction Company

CourtCourt of Appeals of Tennessee
DecidedFebruary 6, 1998
Docket01A01-9705-CH-00227
StatusPublished

This text of Roger Perry and Doris Perry v. Donald Van Hise and Josephine Van Hise, Individually and D/B/A Van Hise Construction Company (Roger Perry and Doris Perry v. Donald Van Hise and Josephine Van Hise, Individually and D/B/A Van Hise Construction Company) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Roger Perry and Doris Perry v. Donald Van Hise and Josephine Van Hise, Individually and D/B/A Van Hise Construction Company, (Tenn. Ct. App. 1998).

Opinion

ROGER PERRY and DORIS PERRY, ) ) Plaintiffs/Appellants, ) ) Warren Chancery VS. ) No. 6025 ) DONALD VAN HISE and JOSEPHINE ) VAN HISE, individually, and d/b/a ) VAN HISE CONSTRUCTION ) Appeal No. COMPANY, ) 01-A-01-9705-CH-00227 ) Defendants/Appellees, )

FILED IN THE COURT OF APPEALS OF TENNESSEE February 6, 1998 MIDDLE SECTION AT NASHVILLE Cecil W. Crowson Appellate Court Clerk APPEAL FROM CHANCERY COURT AT MCMINNVILLE, TENNESSEE

HONORABLE CHARLES HASTON, JUDGE

Aubrey Harper, BR: 015817 P.O. Box 588 McMinnville, TN 37110 ATTORNEY FOR PLAINTIFFS/APPELLANTS

J. Hilton Conger, BR: 3607 Thomas Bratcher, BR: 3869 200 South Third Street P.O. Box 568 Smithville, TN 37166 McMinnville, TN 37110 ATTORNEYS FOR DEFENDANTS/APPELLEES

MODIFIED, AFFIRMED AND REMANDED.

HENRY F. TODD PRESIDING JUDGE, MIDDLE SECTION

CONCUR:

BEN H. CANTRELL, JUDGE WALTER W. BUSSART, JUDGE ROGER PERRY and DORIS PERRY, ) ) Plaintiffs/Appellants, ) ) Warren Chancery VS. ) No. 6025 ) DONALD VAN HISE and JOSEPHINE ) VAN HISE, individually, and d/b/a ) Appeal No. VAN HISE CONSTRUCTION ) 01-A-01-9705-CH-00227 COMPANY, ) ) Defendants/Appellees, )

OPINION

This appeal involves the construction of a home. Plaintiffs engaged one of the

defendants, Donald Van Hise, (hereafter, the defendant) to construct a home on their property.

On May 24, 1994, defendant signed a proposal to construct the house, reserving the right to

withdraw the proposal within 30 days, if not accepted by plaintiff. One of the plaintiffs signed

an acceptance of the proposal. The other did not. On June 25, 1994, defendant tendered another

proposal on different terms, which proposal was accepted by both plaintiffs. The second

proposal contained an estimated time of completion of 3-1/2 - 4-1/2 months. Both proposals

contained a base contract price subject to revision for changes during construction. Both

contracts refer to “plans and specifications” but the record contains no plan and only a partial set

of specifications. The plans and specifications were not specifically prepared for plaintiffs, but

were “generic,” that is, sold on the general market, to be altered as desired; and alterations were

made, producing part of the present controversy.

Promptly after the second proposal was accepted, defendant began excavation which was

delayed by unseasonable rains. Other delays resulted from mistakes or misunderstandings

regarding details of construction. Plaintiff, Roger Perry, (hereafter plaintiff), met with defendant

once weekly on the job to discuss details and progress of construction which was proceeding

slowly because of change orders and other difficulties. Plaintiff made partial payments to

defendant to the total amount of $110,000, but refused to make further payment because of

-2- dissatisfaction with progress and quality of work. Defendant declined to proceed with

construction without further payment on the contract price.

Plaintiffs sued defendant for damages for abandonment of the work, and cost of

completion. Defendant filed a counter-complaint alleging a $30,551.00 unpaid balance of agreed

price of construction, $15,508.00 cost of changes in construction, and for lien upon the land.

On July 14, 1995, Ralph Griffin, d/b/a Ole South Carpets and Furniture was permitted

to intervene to assert a lien claim of $6,686.43 for tile installed and carpet ordered, but not

installed. Plaintiff’s answer admitted the installation of the tile and selection of the carpet, but

denied liability for either. Defendant’s answer denied ordering the tile or carpet and denied

liability therefor.

After hearing the cause without a jury, the Trial Judge filed a memorandum stating:

Having heard the proof at trial and rereading the transcribed testimony, the Court is of the opinion that there was a contract to build a home based upon a generic house plan. The Owner testified on direct that he authorized no changes in these plans and complains of poor workmanship and delays. However, on review of the proof, it appears that the Owner did authorize several changes, moved doors, windows, altered designs, materials, exceeded budget in many areas, but denied so doing until confronted with exhibits in his own handwriting authorizing the changes.

Apparently most delays were caused by the Owner himself. Subcontractors and the Contractor met with the Owner during construction to let him (Owner) air his objections, but he would not specify what was wrong, allowing on occasions the subcontractors to almost complete a project before telling them that a change was necessary, thus greatly increasing the costs. The Owner’s credibility as a witness in his own behalf was severally damaged by these revelations during the trial. For example, the air conditioning system was put in through Carrier Corporation, by whom the Owner is employed, and when this vendor was not paid, the Seller would not complete the final electrical inspection. The owner then approached the local electric company stating that he had put in the system personally, which is not borne out by the testimony.

-3- As for damages, the Contractor sues only for actual expenses and it would be inequitable to allow the Owner to take advantage of the Contractor’s hard work.

When the charges reached Fifteen Thousand, Five Hundred, Eight, and no/100 ($15,508.00) Dollars and the Owner refused to agree to pay, the Contractor was at his mercy. The Court finds the Contractor to be the more credible witness and determines that he has absorbed considerable expenses. It is, Therefore,

ORDERED that the Owner did authorize the charges and should be held responsible for the additional cost of Fifteen Thousand, Five Hundred, Eight & no/100 ($15,508.00) Dollars, plus the Thirty Thousand, Five Hundred, Fifty One and no/100 ($30,551.00) Dollars actual expenses proved by the Contractor.

As for the intervening party, carpet supplier, apparently their bill is not included in the Thirty Thousand, Five Hundred, Fifty One and no/100 ($30,551.00) Dollars paid by the Contractor, however the materials were used in the Owner’s house. These figures total Four Thousand, Four Hundred, Fifty Three and no/100 ($4,453.00) Dollars, and because the costs to repair the items in controversy at the home are approximately the same amount as the carpet supplier’s bill, It is, Therefore

ORDERED that the Contractor pay this bill, but not be required to make any repairs.

The Contractor’s Cross-Petition is dismissed at his costs.

The “Final Decree” of the Trial Court stated:

This cause came on to be heard before the Honorable Charles D. Haston, Circuit Judge, and the Court having filed its memorandum opinion and findings of fact, which is incorporated herein by reference thereto, and the pleadings are amended to conform to the proof. It is, accordingly,

ORDERED and ADJUDGED that the counter- defendants have and recover of the plaintiffs, Roger Perry and Doris Perry, the sum of Fifteen Thousand, Five Hundred Eight Dollars ($15,508) representing additional costs incurred by the contractor due to changes requested by the owner, together with the sum of Thirty Thousand, Five Hundred Fifty-one Dollars ($30,551) representing actual costs incurred by the contractor which remain unpaid, for a total of Forty-six Thousand, Fifty-nine Dollars ($46,059), together with prejudgment interest thereon at the rate of ten percent (10%) from February 14, 1995, the last date upon which any payment was made by the owner to the contractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Airline Construction, Inc. v. Barr
807 S.W.2d 247 (Court of Appeals of Tennessee, 1990)
Hillsboro Plaza Enterprises v. Moon
860 S.W.2d 45 (Court of Appeals of Tennessee, 1993)
Capital City Bank v. Baker
442 S.W.2d 259 (Court of Appeals of Tennessee, 1969)
Larson v. Cook Consultants, Inc.
690 S.W.2d 567 (Texas Supreme Court, 1985)
Schoen v. J.C. Bradford & Co.
642 S.W.2d 420 (Court of Appeals of Tennessee, 1982)
Smith v. Jarnagin
436 S.W.2d 310 (Court of Appeals of Tennessee, 1968)
HMF TRUST v. Bankers Trust Co.
827 S.W.2d 296 (Court of Appeals of Tennessee, 1991)
Harwell v. Harwell
612 S.W.2d 182 (Court of Appeals of Tennessee, 1980)
Hammon v. Miller
13 Tenn. App. 458 (Court of Appeals of Tennessee, 1931)
Turley v. Cooley
3 Shan. Cas. 68 (Tennessee Supreme Court, 1879)

Cite This Page — Counsel Stack

Bluebook (online)
Roger Perry and Doris Perry v. Donald Van Hise and Josephine Van Hise, Individually and D/B/A Van Hise Construction Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/roger-perry-and-doris-perry-v-donald-van-hise-and--tennctapp-1998.