Rockhill Insurance Company v. CFI-Global Fisheries

Court of Appeals for the Tenth Circuit·Decided July 24, 2019·No. 18-1201·Unpublished

Opinion

FILED

United States Court of Appeals UNITED STATES COURT OF APPEALS Tenth Circuit

FOR THE TENTH CIRCUIT July 24, 2019

Elisabeth A. Shumaker

Clerk of Court

ROCKHILL INSURANCE COMPANY,

Plaintiff - Counter Defendant -

Appellee

v. Nos. 18-1201 & No. 18-1207 (D.C. No. 1:16-CV-02760-RM-MJW)

CFI-GLOBAL FISHERIES (D. Colo.) MANAGEMENT; HEIRLOOM I, LLC.,

Defendant - Counterclaimant -

Appellant.

ORDER AND JUDGMENT*

Before BRISCOE, LUCERO, and MORITZ, Circuit Judges.

CFI-Global Fisheries Management (“CFI”) and Heirloom I, LLC., (“Heirloom”) appeal a district court order granting summary judgment in favor of Rockhill Insurance Company (“Rockhill”). The district court concluded that an exclusion in CFI’s professional liability policy for faulty workmanship barred recovery for damages related to poor design and construction of a river enhancement project. It further ruled that CFI’s bad faith claims failed because the company did

*

This order and judgment is not binding precedent, except under the doctrines of law of the case, res judicata, and collateral estoppel. It may be cited, however, for its persuasive value consistent with Fed. R. App. P. 32.1 and 10th Cir. R. 32.1.

not show Rockhill caused a business loss. We affirm the district court’s order as to CFI’s common law bad faith claim. However, we conclude the faulty workmanship exclusion does not apply to damages caused by negligent design work. We reverse the district court’s rulings on coverage under the professional liability policy and CFI’s statutory bad faith claim. Exercising jurisdiction under 28 U.S.C. § 1291, we affirm in part, reverse in part, and remand for further proceedings consistent with this order and judgment.

I

Heirloom owned property in southwestern Colorado. In 2012, it contracted with CFI to design and construct a fisheries enhancement project on the property. CFI completed the project, but its work was defective and the project was destroyed by natural processes four times in three years. Heirloom paid more than $800,000 to CFI under the contract.

On July 20, 2015, Heirloom initiated arbitration proceedings against CFI for breach of contract and negligence related to the design and execution of the project. CFI requested that Rockhill, its professional and general liability insurer, defend it in the arbitration. CFI had taken out an insurance policy with Rockhill, which included three coverage components: (1) commercial general liability coverage, which generally applies to “‘bodily injury’ or ‘property damage’” but excludes coverage for liability arising from professional services; (2) contractor’s pollution liability coverage; and (3) professional liability coverage. The professional liability coverage form applies to damages arising from a “[p]rofessional services incident,” defined as

“any negligent act, error or omission” in “your rendering, or your failing to render, ‘professional services’” that “results in injury or damage.” It also states that “your work” means: “(1) Work or operations performed by you or on your behalf; and (2) Materials, parts or equipment furnished in connection with such work or operations.”

On August 21, 2015, Rockhill sent CFI a letter agreeing to defend the arbitration but reserving its right to deny coverage. In outlining Rockhill’s coverage position, the insurer implied some of the damages could fall within the policy, but discussed several exclusions that might apply. Rockhill identified Exclusion M of the professional liability policy, which reads in full:

M. Faulty Workmanship Based upon, arising out of or for any loss, cost or expense incurred to withdraw, recall, inspect, repair, replace, adjust, remove or dispose of “your work”. This includes, but is not limited to, the cost to investigate “your work”, or the cost of any materials, parts, labor or equipment furnished in connection with such withdrawal, recall, inspection, repair, replacement, adjustment, removal or disposal.

Rockhill also noted Exclusion P of the professional liability policy, which states:

P. Expressed or Implied Warranties Based upon, as a consequence of or arising out of:

(1) Any expressed or implied warranties or guarantees, or (2) Any cost or other estimates for construction, renovation, removal or demolition being exceeded or inaccurate.

However, this exclusion does not apply to a warranty or guaranty by you that your “professional services” are in conformity with generally accepted architectural or engineering standards.

The letter states that Heirloom’s “allegations relative to CFI’s designs potentially implicate a ‘professional services incident’ that would trigger coverage” but “[t]o the extent that the damages sought arise out of . . . faulty workmanship apart from your

professional services . . . the [Professional Liability] Form will not provide coverage for such damages.”

In November 2015, Rockhill offered to settle with Heirloom for $15,000.

Heirloom promptly rejected this offer, demanding $990,000. A year passed with no additional settlement offers. On October 3, 2016, two weeks before the arbitration was set to begin, Rockhill wrote to CFI that the entirety of the damages claimed were excluded from coverage. The insurer proposed CFI agree to fund a settlement with Heirloom in which CFI would pay 75% of settlement costs up to $500,000, with Rockhill paying the remaining 25%. CFI responded on October 11, stating Rockhill’s proposal was a breach of its duties as an insurer and demanding Rockhill immediately pursue and fund settlement with Heirloom. Three days later, Heirloom made a settlement proposal of $750,000. CFI asked Rockhill to accept and fund the offer. Rockhill responded that it would be willing to pay $150,000 towards the settlement.

The arbitration proceeded from October 17 to 21, 2016. During the arbitration, Rockhill informed CFI it had offered an updated settlement of $260,000 to Heirloom, after CFI explained it could contribute only $10,000 to a settlement offer. Internal communications indicate Rockhill authorized a potential offer up to $400,000. The arbitrators awarded Heirloom $609,994.91 plus pre-judgment interest. The parties subsequently stipulated to an additional $265,000 award of attorney’s fees and costs. Neither party requested the arbitrators’ decision be accompanied by an explanation of reasoning. However, attached to the final award is a spreadsheet

identifying invoices paid to third party contractors who worked on the river enhancement project following CFI’s failures, and a line item for remaining construction.

Rockhill filed a declaratory-judgment action against CFI and Heirloom prior to the issuance of the award. It sought a declaration that it had no duty to defend and indemnify CFI in connection with the Heirloom arbitration. CFI and Heirloom asserted counterclaims for declaratory judgment and breach of contract. CFI also asserted statutory and common law bad faith claims against Rockhill based upon its failure to timely settle. The district court granted summary judgment for Rockhill, holding the entirety of the damages awarded to Heirloom were excluded under the policy’s Faulty Workmanship exclusion, along with the attorneys’ fees and costs. On CFI’s bad faith claims, the court held that CFI failed to present any evidence to prove any business loss caused by non-settlement. CFI and Heirloom timely appealed.

II

We review de novo the grant of summary judgment. MarkWest Hydrocarbon, Inc. v. Liberty Mut. Ins. Co., 558 F.3d 1184, 1189 (10th Cir. 2009). In doing so, we view the facts in the light most favorable to the non-moving party. Id. at 1189-90. Summary judgment is proper if “there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(a).

Free access — add to your briefcase to read the full text and ask questions with AI

Rockhill Insurance Company v. CFI-Global Fisheries, (10th Cir. 2019).

Rockhill Insurance Company v. CFI-Global Fisheries (Rockhill Insurance Company v. CFI-Global Fisheries) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Norris v. Baxter Healthcare Corp.
397 F.3d 878 (Tenth Circuit, 2005)
Stickley v. State Farm Mutual Automobile Insurance
505 F.3d 1070 (Tenth Circuit, 2007)
Pompa v. American Family Mutual Insurance
520 F.3d 1139 (Tenth Circuit, 2008)
Specialty Beverages, L.L.C v. Pabst Brewing Co.
537 F.3d 1165 (Tenth Circuit, 2008)
MacK Trucks Inc. v. Borgwarner Turbo Systems, Inc.
508 F. App'x 180 (Third Circuit, 2012)
Nunn v. Mid-Century Insurance Co.
244 P.3d 116 (Supreme Court of Colorado, 2011)
Copper Mountain, Inc. v. Industrial Systems, Inc.
208 P.3d 692 (Supreme Court of Colorado, 2009)
Bankruptcy Estate of Morris Ex Rel. Goodwin v. COPIC Insurance Co.
192 P.3d 519 (Colorado Court of Appeals, 2008)
American Family Mutual Insurance Co. v. Hansen
2016 CO 46 (Supreme Court of Colorado, 2016)
State Farm Mutual Automobile Insurance Co. v. Fisher
2018 CO 39 (Supreme Court of Colorado, 2018)
East Ridge of Fort Collins, LLC v. Larimer & Weld Irrigation Co.
109 P.3d 969 (Supreme Court of Colorado, 2005)
Hoang v. Assurance Co. of America
149 P.3d 798 (Supreme Court of Colorado, 2007)
Federal Deposit Insurance Corp. v. Fisher
2013 CO 5 (Supreme Court of Colorado, 2013)
Hansen v. American Family Mutual Insurance Co.
2013 COA 173 (Colorado Court of Appeals, 2013)