Robertson's Marine, Inc. v. I4 Solutions, Inc.

2010 UT App 9, 223 P.3d 1141, 648 Utah Adv. Rep. 8, 2010 Utah App. LEXIS 10, 2010 WL 199675
CourtCourt of Appeals of Utah
DecidedJanuary 22, 2010
Docket20080962-CA
StatusPublished
Cited by18 cases

This text of 2010 UT App 9 (Robertson's Marine, Inc. v. I4 Solutions, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Robertson's Marine, Inc. v. I4 Solutions, Inc., 2010 UT App 9, 223 P.3d 1141, 648 Utah Adv. Rep. 8, 2010 Utah App. LEXIS 10, 2010 WL 199675 (Utah Ct. App. 2010).

Opinions

OPINION

THORNE, Judge:

[ 1 I4 Solutions, Inc. (I4) appeals from the district court's judgment in this contract and unjust enrichment action between I4 and Robertson's Marine, Inc. (Robertson). Specifically, I4 challenges the district court's failure to award attorney fees to I4 under the parties' contract. Robertson cross-appeals, challenging the district court's conclusion that Robertson was unjustly enriched and seeking an award of attorney fees incurred in defending against 14's appeal. We affirm the district court's judgment but remand this matter for a determination of Robertson's reasonable attorney fees incurred in defending against I4's appeal.

BACKGROUND

T2 In April 2005, Robertson and I4 entered into a services contract whereby I4 was to design and implement a website for Robertson's boat dealership. Robertson paid I4 $3275, one half of the total contract price of $6550, at the time the contract was entered and agreed to pay the remaining $8275 when the website was completed and approved. The parties' contract included the following language pertaining to attorney fees: "II, Robertson,] agree to pay all collection costs, including court costs and reasonable attorney[ ] fees if collection is required."

T3 Although the contract did not contain a deadline for I4 to complete the website, Robertson anticipated that the website would be complete and operational by mid-summer of 2005 so that it would be usable by potential Robertson customers during the 2005 boating season. By December 2005, I4 had still not completed the website to Robertson's satisfaction, and Robertson demanded a refund of the $3275 it had paid I4. I4 refused Robertson's demand and Robertson sued 14 for breach of contract and unjust enrichment. I4 brought counterclaims against Robertson seeking payment under the contract or unjust enrichment damages.

T4 The district court conducted a bench trial in August 2008 and took the matter under advisement. On September 8, 2008, the district court issued a minute entry containing its ruling on the matter. In the minute entry, the district court described the terms of the contract and determined that I4 had substantially completed its work under the contract. However, the district court determined that I4 had failed to complete one component of the website-a price calculator that the parties had valued at $600. The district court did not find that either party had prevailed on its breach of contract claim. Rather, the district court ruled that Robertson had been unjustly enriched because I4 "complet[ed] the majority of the work on [Robertson's] website" and "[i]t would be unjust to permit [Robertson] to retain the benefit of these services and the resulting website without having paid for them." However, in light of 14's failure to complete the calculator component of the website and delay in completing the work, the district court ordered Robertson to pay I4 only $1800 rather than the full $3275 contemplated by the contract. The district court also ordered that each party was to be responsible for its own attorney fees and costs.

1 5 Despite the district court's attorney fee ruling, I4 filed a motion seeking an award of attorney fees under the contract. I4's motion argued that the district court should amend its ruling to find that I4 had prevailed on its breach of contract claim, but that, in any event, I4 was the prevailing party because of the unjust enrichment award. The district court effectively denied T4's motion in a minute entry noting that it had already ruled on attorney fees and again ordered each side to pay its own attorney fees and costs. Subsequently, the district court entered findings of fact and conclusions of law substantially reflecting its September 3 minute entry, and a judgment of $1800 in favor [1144]*1144of 14. 14 appeals from that judgment, and Robertson cross-appeals.

ISSUES AND STANDARDS OF REVIEW

16 We first address Robertson's argument on cross-appeal that the district court's factual findings do not support its legal conclusion that Robertson was unjustly enriched.2 "Questions about the legal adequacy of findings of fact and the legal accuracy of the trial court's statements present issues of law, which we review for correctness, according no deference to the trial court." Shar's Cars, LLC v. Elder, 2004 UT App 258, 1 12, 97 P.3d 724 (internal quotation marks omitted). However, challenges to the adequacy or detail of a trial court's factual findings must be preserved for appeal in the trial court or such challenges are waived. See In re K.F., 2009 UT 4, " 58-64, 201 P.3d 985 (affirming and clarifying the preservation rule announced in 488 Main Street v. Hasy Heat, Inc., 2004 UT 72, 99 P.3d 801).

17 Next, we address I4's argument on appeal, that it was the prevailing party in the action below and was therefore entitled to an award of attorney fees under the parties' contract. "The question of which party is the prevailing party 'depends, to a large measure, on the context of each case, and, therefore, it is appropriate to leave this determination to the sound discretion of the trial court"" Radman v. Flanders Corp., 2007 UT App 351, 1 26, 172 P.3d 668 (quoting R.T. Nielson Co. v. Cook, 2002 UT 11, ¶ 25, 40 P.3d 1119), cert. denied, 186 P.3d 957 (Utah 2008). The discretion permitted to the district court allows it the "flexibility to handle circumstances where both, or neither, parties may be considered to have prevailed." R.T. Nielson Co., 2002 UT 11, T 25, 40 P.3d 1119.

¶8 Finally, we address Robertson's request on cross-appeal that it be awarded its reasonable attorney fees incurred in defending against 14's appeal. "The general rule is that when a party who received attorney fees below prevails on appeal, the party is also entitled to fees reasonably incurred on appeal." Brown v. Richards, 840 P.2d 143, 156 (Utah Ct.App.1992).

ANALYSIS

I. Adequacy of the District Court's Factual Findings

¶9 On cross-appeal, Robertson argues that the district court's factual findings do not adequately support its legal conclusion that Robertson was unjustly enriched by I4. Specifically, Robertson argues that the district court failed to make adequate findings as to each of the three elements of unjust enrichment: (1) that a benefit was conferred; (2) appreciation or knowledge of the benefit by the conferee; and (8) acceptance or retention of the benefit under cireumstances making it inequitable for the conferee to retain the benefit without payment of value. See generally Allen v. Hall, 2006 UT 70, T 26, 148 P.3d 989; Desert Mirigh, Inc. v. B & L Auto, Inc., 2000 UT 83, 1 13, 12 P.3d 580.

T10 Robertson did not raise these alleged deficiencies in the factual findings to the district court, and has therefore failed to preserve them as issues for appeal. "[In order to preserve an issue for appeal{,] the issue must be presented to the trial court in such a way that the trial court has an opportunity to rule on that issue." 488 Main St. v. Easy Heat, Inc., 2004 UT 72, 151, 99 P.3d 801 (alterations in original) (internal quotation marks omitted). "This requirement puts the trial judge on notice of the asserted error and allows for correction at that time in the course of the proceeding." Id.

T 11 The Utah Supreme Court has specifically addressed the preservation requirement as it applies to challenges to the adequacy of factual findings. In In re KF., 2009 UT 4, 201 P.3d 985, the court stated,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Checkerprop Utah v. Butcher
2024 UT App 124 (Court of Appeals of Utah, 2024)
Thomas v. Thomas
2021 UT App 8 (Court of Appeals of Utah, 2021)
Mitchell v. ReconTrust Company
2016 UT App 88 (Court of Appeals of Utah, 2016)
Martin v. Rasmussen
2014 UT App 200 (Court of Appeals of Utah, 2014)
Levin v. Carlton-Levin
2014 UT App 3 (Court of Appeals of Utah, 2014)
Burningham v. Westgate Resorts, Ltd.
2013 UT App 244 (Court of Appeals of Utah, 2013)
Dennett v. Ferber
2013 UT App 209 (Court of Appeals of Utah, 2013)
Anderson & Karrenberg v. Warnick
2012 UT App 275 (Court of Appeals of Utah, 2012)
All Clean, Inc. v. Timberline Properties
2011 UT App 370 (Court of Appeals of Utah, 2011)
GOLDEN MEADOWS PROPERTIES, LC v. Strand
2011 UT App 76 (Court of Appeals of Utah, 2011)
LaCHANCE v. Richman
2011 UT App 40 (Court of Appeals of Utah, 2011)
State v. L.A.
2010 UT App 356 (Court of Appeals of Utah, 2010)
Robertson's Marine, Inc. v. I4 Solutions, Inc.
2010 UT App 9 (Court of Appeals of Utah, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
2010 UT App 9, 223 P.3d 1141, 648 Utah Adv. Rep. 8, 2010 Utah App. LEXIS 10, 2010 WL 199675, Counsel Stack Legal Research, https://law.counselstack.com/opinion/robertsons-marine-inc-v-i4-solutions-inc-utahctapp-2010.