Roberts v. West Virginia American Water Co.

655 S.E.2d 119, 221 W. Va. 373
CourtWest Virginia Supreme Court
DecidedDecember 26, 2007
Docket33326
StatusPublished
Cited by19 cases

This text of 655 S.E.2d 119 (Roberts v. West Virginia American Water Co.) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Roberts v. West Virginia American Water Co., 655 S.E.2d 119, 221 W. Va. 373 (W. Va. 2007).

Opinions

ALBRIGHT, Justice:

This is an appeal by the plaintiff below, Mark Roberts, (hereinafter referred to as “Appellant”) from the June 10, 2005, and June 29, 2006, orders of the Kanawha County Circuit Court granting summary judgment in favor of the defendants below, West Virginia American Water Company, E.L. Robinson Engineering Co. and Famco Contracting, Inc. (hereinafter referred to collectively as “Appellees”),1 on statute of limitations [376]*376grounds in a property damage suit. On appeal to this Court, Appellant maintains that the lower court incorrectly found that his suit was not timely filed because both the continuous tort doctrine and the discovery rule tolled the running of the statute in this case. Upon completion of review of the arguments of the parties, the record presented for appellate consideration, and the pertinent authorities, we affirm the ruling of the circuit court.

I. Factual and Procedural Background

The underlying civil action involves a claim of property damage occurring on Appellant’s twenty-acre tract of land2 in Kanawha County, West Vii'ginia, which allegedly was caused by the installation of water lines in 1999. The waterline installation project was undertaken in 1998 by the Kanawha County Commission through the Regional Development Authority of Charleston in conjunction with West Vii'ginia American Water Company (hereinafter referred to individually as “WVAW”). WVAW contracted with' E.L. Robinson Engineering Co. (hereinafter referred to individually as “ELRE”) and Fam-co Contracting, Inc. (hereinafter referred to individually as “Famco”) to engineer, design and/or install the water lines.

The water lines were installed parallel to a gravel road on Appellant’s property. He maintains that during the course of the construction project the bottom of a concrete trough at the foot of his driveway was broken. Additionally, Appellant claims that a substantial portion of the hillside below the road was cut, moved and shifted during the installation causing the toe3 of the hillside to be significantly disturbed. Prior to this disturbance, Appellant said he never experienced any slips or landslides on or near his property. He asserts that the erosion of his road over time is the direct result of the damage done to the toe of the hill during the waterline installation project.

Appellant testified during a deposition that within three weeks of the completion of the waterline project he noticed that a slip had developed along his road. Appellant said he also noticed slips in March and October 2000. The first major slip on Appellant’s property happened on April 15, 2002, at which time travel on his gravel roadway became hazardous for trucks and larger vehicles. According to a phone log maintained by Appellant, Appellant called WVAW, Famco and ELRE on April 15 and April 18, 2002. During these conversations, Appellant advised the company representatives of the slippage and requested that his property be inspected and repaired. Two weeks thereafter another major slip occurred on Appellant’s property.

In June 2002, WVAW hired Triad Engineering, Inc. (hereinafter referred to as “Triad”) to inspect Appellants’ property and offer an opinion as to the cause of the slippages. Triad issued a report of its investigation on July 2, 2002, a copy of which was mailed to Appellant on August 5, 2002. The Triad report contained the following conclusion:

It is difficult to malee a positive assessment of the cause of the landslide since a significant amount of time has past [sic] since it first occurred. Based on our experience and knowledge, any excavation work performed at the toe of such a steep slope can initiate instability. Once instability has been initiated and a shear plane has formed within the soil, soil slippage typically continues to progress unless corrective action is taken. Based on our visual observations and information provided by Mr. Roberts, it is possible that the excavation work performed to install the water line caused the landslide.

Famco later obtained an inspection and report from CTL Ehgineering of West Virginia (hereinafter referred to as “CTL”). The CTL report dated September 2, 2003, reflects that:

[t]he slope failure appears to be related to some movements at the toe of the slope as in most slide occurrences. The slopes in the subject area are steep in nature and [377]*377no obvious causes related to the pipeline installation were visible due to the heavy vegetation on the slope and the elapsed time since the slope failure.

It was further noted in the CTL report that “[a]ccording to the West Virginia Landslide Study Pocatalico Quad Map (1976) the area was found to be in a naturally occurring slide-prone area of Kanawha County.” Following review of these reports, Appellant maintains that he requested that Appellees either repair the property or compensate him for damages and they refused.

According to Appellant, at the same time the reports were being prepared the erosion of his property continued to progress as manifested by a ten foot section of his driveway breaking off and sliding down the hill on March 12, 2003. By June 2003, the slip had expanded an additional twenty feet. The slips again expanded in January and March 2004, the last of which resulted in debris falling to the bottom of the hill near the public highway.

Appellant filed suit on July 22, 2004, for property damages resulting from Appellees’ negligent, defective and improper installation of water lines on his land. His complaint contained the allegations that although the waterline construction project specifications, maps and expert reports showed the area to be prone to slips, Appellees took no special precautions to prevent such problems. Following discovery, Appellees filed separate motions for summary judgment, contending inter alia that the suit was filed beyond the applicable two-year statute of limitations set forth in West Virginia Code § 55-2-12 (1959) (Repl.Vol.2000).4 Appellant responded by arguing that because the damage to his property was ongoing, separate and continuous, the statute of limitations did not begin to ran until the last damage occurred in March 2004. He additionally argued that even if the statute of limitations was not tolled under the continuing tort doctrine, it was tolled by the discovery rule. In support of this assertion, Appellant claimed that he did not discover the full extent of his claim against the named defendants until he received the report from Triad in August 2002, and his suit was filed within two years of receiving the Triad report.

Finding no genuine issue of material fact, the lower court granted WVAW’s motion for summary judgment on June 10, 2005,5 and the motions for summary judgment of ELRE and Famco on June 29, 2006. The orders reflect the lower court’s finding that under either theory advanced by Appellant, the two-year statute of limitations had expired by the time he filed suit. The orders specifically reflect the lower court concluding in all cases that the discovery rule did not apply because Appellant admittedly knew within three weeks of completion of the waterline project that his land had been damaged by the installation, knew the identity of Appel-lees and was aware of his claims against them no later than April 2002 when he contacted each of them. Moreover, the lower court found that the continuing tort doctrine did not apply under the facts of the case.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Christian v. Eaton Corporation
S.D. West Virginia, 2024
Greene v. C. J. Eastridge
S.D. West Virginia, 2022
Lydick v. Erie Ins. Prop. & Cas. Co.
358 F. Supp. 3d 552 (U.S. District Court, 2019)
Ali v. Raleigh County
S.D. West Virginia, 2018
Gary Sigman v. Discover Bank
West Virginia Supreme Court, 2017
Moore v. Equitrans, L.P.
49 F. Supp. 3d 456 (N.D. West Virginia, 2014)
Dunn v. Rockwell
689 S.E.2d 255 (West Virginia Supreme Court, 2009)
Roberts v. West Virginia American Water Co.
655 S.E.2d 119 (West Virginia Supreme Court, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
655 S.E.2d 119, 221 W. Va. 373, Counsel Stack Legal Research, https://law.counselstack.com/opinion/roberts-v-west-virginia-american-water-co-wva-2007.