Rky Mtn Microsystems v. Public Safety

Court of Appeals for the Tenth Circuit·Decided March 25, 1999·No. 98-1059·Unpublished

Opinion

F I L E D

United States Court of Appeals Tenth Circuit

UNITED STATES COURT OF APPEALS MAR 25 1999

FOR THE TENTH CIRCUIT

PATRICK FISHER

Clerk

ROCKY MOUNTAIN MICROSYSTEMS, INC. a Colorado corporation,

Plaintiff-Appellee, No. 98-1059 (D.C. No. 95-WM-726)

v. (D. Colo.)

PUBLIC SAFETY SYSTEMS, INCORPORATED, a Virginia corporation,

Defendant-Appellant.

ORDER AND JUDGMENT *

Before PORFILIO, BALDOCK, and HENRY, Circuit Judges.

After examining the briefs and appellate record, this panel has determined unanimously that oral argument would not materially assist the determination of

*

This order and judgment is not binding precedent, except under the doctrines of law of the case, res judicata, and collateral estoppel. The court generally disfavors the citation of orders and judgments; nevertheless, an order and judgment may be cited under the terms and conditions of 10th Cir. R. 36.3.

this appeal. See Fed. R. App. P. 34(a)(2); 10th Cir. R. 34.1(G). The case is therefore ordered submitted without oral argument.

Defendant Public Safety Systems, Inc. (PSSI) appeals from an adverse judgment entered after a bench trial on plaintiff Rocky Mountain Microsystems, Inc.’s (RMMI’s) claims for breach of contract and quantum meruit. Pursuant to contractual stipulation, Colorado law controls in this diversity action. See Appellant’s Appendix (App.) at 270. We review the district court’s legal conclusions de novo and its factual findings for clear error, see Salve Regina College v. Russell , 499 U.S. 225, 231, 233 (1991), and affirm for substantially the reasons stated in its opinion, see generally Rocky Mountain Microsystems, Inc. v. Public Safety Sys., Inc. , 989 F. Supp. 1352 (D. Colo. 1998).

The district court’s extensive discussion of the evidence need not be repeated in full here. Some discussions of the facts are necessary to understand the outcome. PSSI contracted to provide the City and County of Denver with an integrated computer-aided dispatching (“CAD”) system for the city’s fire, police, and emergency medical service departments. PSSI then subcontracted with RMMI, which agreed to design and install combined hardware-and-software devices, called “Interface Modules,” to connect the city’s existing dispatching equipment with the CAD system PSSI was to provide. The PSSI-RMMI agreement set out a payment schedule tied to three performance “milestones.”

The first, consisting of twenty-five percent of the contract price due (and paid) upon execution of the contract, is not in dispute. This case involves RMMI’s effort to obtain payment for the second and third milestones, regarding delivery/installation and demonstration/acceptance of the Interface Modules. PSSI, whose contract with the city was definitively terminated after RMMI had invoiced the last two milestones, defended against the suit on the basis that RMMI had not satisfied certain conditions precedent to payment.

Delivery/Installation

Section 3.3 of the parties’ contract states that RMMI “shall deliver the Hardware [and associated software] to PSSI and install the Hardware at the Facilities.” App. at 259; see also id. at 260. “Facilities” is elsewhere specified to be the Combined Communications Center for the city’s fire, police, and emergency medical services. See id. at 258, 281. The second milestone payment, consisting of fifty percent of the contract total, was due “[u]pon completion of the installation.” Id. at 280.

PSSI contends RMMI failed to comply with a contractual duty to deliver the Hardware to PSSI independently of the delivery and installation at the Center. The district court rejected PSSI’s dual-delivery position, reading the quoted provision of section 3.3 instead to contemplate a single delivery and installation

at the Center in Denver, where PSSI’s CAD system was located. See Rocky Mountain Microsystems, Inc. , 989 F. Supp. at 1356-57. We agree.

In addition to the points made by the district court, we note that PSSI is located in Maryland, and no reasonable construction of the parties’ contract would require a redundant delivery thousands of miles from the actual installation site without fairly clear language to that effect including, for example, some indication of the location intended for such delivery. The only site specified in the contract, however, is the Center in Denver. Indeed, that location is repeated without qualification in the warranty section of the contract as well. See App. at 265 (Section 9.1 of the contract stating RMMI’s warranty of “the Hardware, at the time of delivery to the Facilities”).

In addition to its objections regarding delivery, 1 PSSI contends RMMI did

not complete installation of the Interface Modules, which was necessary to consummate its duty with respect to the second milestone. PSSI argues, as a general matter, that the Interface Modules were not fully installed and functioning

1 Our agreement with the district court over the import of the contract’s delivery provision obviates some collateral points argued by PSSI. For example, PSSI’s contention that it had not formally authorized anyone at the Center to receive delivery from RMMI merely reflects an omission on PSSI’s part, not any noncompliance by RMMI, which fulfilled its contractual duty when it completed delivery to the specified destination and notified PSSI of that fact by invoice. See also Colo. Rev. Stat. § 4-2-503. And, as PSSI itself states, the “title” issue discussed in its brief is immaterial. See Colo. Rev. Stat. § 4-2-401.

when further work was curtailed by the breakdown of PSSI’s relationship with the city and, more specifically, that the Interface Modules were never connected to PSSI’s CAD system, the last step necessary for complete installation.

With respect to installation generally, the district court found from conflicting evidence that RMMI had completed its work connecting the Interface Modules to the city’s equipment at the Center: “Everything was installed except for the connection to [PSSI’s CAD] computer.” Rocky Mountain Microsystems, Inc. , 989 F. Supp. at 1355. The record is sufficient to support this factual determination. As for connection to PSSI’s CAD system, the undisputed evidence showed this step “could only be accomplished by [PSSI],” id. , because PSSI had expressly prohibited RMMI and city personnel from touching the CAD system. We agree with the district court that PSSI “should not be allowed to frustrate any of [RMMI’s] remaining performance by [its] own inaction.” Id. at 1357 (citing Comment 3 to Colo. Rev. Stat. § 4-2-311(3), which provides that “when . . . cooperation by one party is necessary to or materially affects the other party’s performance, but it is not seasonably forthcoming; th[is] subsection relieves the other party from the necessity for performance or excuses his delay in performance as the case may be”); see also I.M.A., Inc. v Rocky Mountain Airways, Inc. , 713 P.2d 882, 889 (Colo. 1986) (applying same general rule of contract law, without relying on § 4-2-311).

PSSI’s brief also includes a passing, conclusory objection that RMMI did not deposit the source code for the Interface Modules’ software into escrow, as required by section 3.5 of the contract. We do not consider this pertinent to the issue at hand. The source code was to be deposited in escrow “ [u]pon completion of the installation,” App. at 260 (emphasis added), not as part of the installation, and, in any event, the undisputed evidence showed that the purpose of this provision was to protect the city--not PSSI--should RMMI cease to be available for maintenance of the Interface Modules at some future date. Id. at 518-19, 557-59. Any suggestion that this obligation of RMMI was a “dominant purpose” of its contract with PSSI, and thus a condition precedent to a milestone payment, 2

Free access — add to your briefcase to read the full text and ask questions with AI

Rky Mtn Microsystems v. Public Safety, (10th Cir. 1999).

Rky Mtn Microsystems v. Public Safety (Rky Mtn Microsystems v. Public Safety) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Salve Regina College v. Russell
499 U.S. 225 (Supreme Court, 1991)
Surplus Electronics Corp. v. Gallin
653 P.2d 752 (Colorado Court of Appeals, 1982)
I.M.A., Inc. v. Rocky Mountain Airways, Inc.
713 P.2d 882 (Supreme Court of Colorado, 1986)
Lockhart v. Elm
736 P.2d 429 (Colorado Court of Appeals, 1987)
Rohauer v. Little
736 P.2d 403 (Supreme Court of Colorado, 1987)
Western Conference Resorts, Inc. v. Pease
668 P.2d 973 (Colorado Court of Appeals, 1983)
Johnson v. Benson
725 P.2d 21 (Colorado Court of Appeals, 1986)