Rocky Mountain Microsystems, Inc. v. Public Safety Systems, Inc.

989 F. Supp. 1352, 1998 U.S. Dist. LEXIS 326, 1998 WL 10632
CourtDistrict Court, D. Colorado
DecidedJanuary 13, 1998
Docket1:95-cv-00726
StatusPublished
Cited by4 cases

This text of 989 F. Supp. 1352 (Rocky Mountain Microsystems, Inc. v. Public Safety Systems, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rocky Mountain Microsystems, Inc. v. Public Safety Systems, Inc., 989 F. Supp. 1352, 1998 U.S. Dist. LEXIS 326, 1998 WL 10632 (D. Colo. 1998).

Opinion

FINDINGS OF FACT, CONCLUSIONS OF LAW, AND ORDER

MILLER, District Judge.

Following a two-day trial in this matter and the submission of arguments of the parties, I make the following factual findings and conclusions of law pursuant to Rule 52(a), Fed.R.Civ.P.

FINDINGS OF FACT

Many of these findings are based upon the Stipulated Facts filed by the parties on April 22,1997.

Breach of Contract Claim

1. Plaintiff Rocky Mountain Micro Systems, Inc. (“RMMI” or “Plaintiff’) is a Colorado corporation.

2. Defendant Public Safety Systems, Incorporated, (“PSSI” or “Defendant”) is a Virginia corporation.

3. On September 3, 1992, Defendant contracted with the City and County of Denver, Colorado, (“Denver”) for the design and installation of an integrated computer-aided dispatching system (“CAD”) for Denver’s Fire, Police and Emergency Medical Services departments (Exhibit 2).

4. That contract provides that it expired on December 31,1993.

5. Plaintiff entered into a subcontract with Defendant, entitled Development and License Agreement (“Agreement”) and dated February 26, 1993 (Exhibit 10), whereby Plaintiff was to design and install a combination of hardware and licensed software (collectively “Interface Modules”) that would pass information between Denver’s existing equipment and the CAD Defendant was developing.

6. The Agreement obligated Plaintiff to:

a. “[D]eliver the Hardware to PSSI and install the Hardware at the Facilities,” which were designated in the Agreement to be Denver’s Combined Communications Center.

b. Arrange access to the Facilities with Denver for installation and implementation of the Interface Modules.

c. “[P]rovide prompt notice to PSSI of any actual or anticipated delays in the delivery of the Interface Modules and ... report periodically concerning the progress of the development efforts.”

d. “[D]eliver the Licensed Software for each Interface Module to PSSI within 10 days of the delivery of the Hardware for that Interface Module and ... manage on-site installation of the Licensed Software at the Facilities.”

e. ‘Within five days of completion of delivery and installation of each Interface Mo-dule____demonstrate to PSSI, or its designated representative, the functions of the particular Interface Module.”

7. Pursuant to the Agreement, Defendant was to:

a. Conduct acceptance testing of the Interface Modules for a period of thirty days, immediately following their successful demonstration.

b. Pay Plaintiff $131,730 in three installments as hereafter described.

8. It is undisputed that Plaintiff completed development of the Interface Modules by June 1994. As discussed infra, a meeting of the parties with Denver representatives resulted in a decision to enhance those Modules which was completed by Plaintiff by September 1994.

9. The “Status Interface Module” (see Exhibits B and C to Agreement) consists of software alone. It was delivered to Defen *1355 dant via modem in June 1994 for testing and demonstration.

10. The testing of the Status Interface Module went well according to the Plaintiff and Defendant’s representative (Elijah Titus). Although further testing was discussed, neither Mr. Titus nor anyone else from Defendant requested further testing from the Plaintiff and Defendant never complained of any defect in that Module.

11. Sometime in September 1994, Plaintiff made the necessary arrangements with the Denver Fire Department for access to deliver and install the remaining Modules at the Combined Communications Center (“Center”).

12. The installation of the remaining Interface Modules, which consisted of software and hardware, began in mid-September 1994, and was completed on or about December 30, 1994.

13. Everything was installed except for the connection to the Defendant’s computer which could only be accomplished by Defendant. That connection has never been made.

14. Plaintiff testified that the testing and demonstration via modem in the summer of 1994 satisfactorily demonstrated the suitability of the Modules for Defendant’s computer. That testimony was unrebutted.

15. Plaintiff otherwise demonstrated all Modules at the Center to the reasonable satisfaction of Denver Fire Department personnel.

16. Although there had been discussion of doing so, the Denver Fire Department personnel had not been formally named as the “designated representatives” of Defendant under the Agreement for purposes of demonstration.

17. Defendant was not present during the demonstrations and there is no evidence that it was given prior notice of those demonstrations.

18. Defendant did receive notice of the installation and demonstration from Plaintiff’s December 30, 1994, invoice which was received by Defendant in early January, 1995 (see infra).

19. During 1994, Defendant had ongoing discussions with Denver for an extension of their contract which otherwise expired at the end of 1993 (see Exhibits D-2, 29, 30, 31, 32 and 33). Defendant did not give Plaintiff any notice of these discussions or of any potential difficulties.

20. In September, 1994, at about the time Plaintiff was commencing installation of the Interface Modules, Mr. Bruce Shannon of the Defendant called Plaintiff’s President, Ray Burton, and told him that there had been “a little snag” in Defendant’s contract with Denver, but that Plaintiff should proceed with the work on the Interface Modules rather than wait for Mr. Titus’s call concerning any further testing via modem.

21. Lewis Henneke, President of the Defendant, testified that he told Mr. Shannon to give the Plaintiff a stop work order in the first part of September, 1994, but Mr. Burton’s unequivocal denial that any such order was given is not rebutted by Defendant and it did not call Mr. Shannon as a witness.

22. Section 12.3 of the Agreement 1 permitted Defendant to terminate the Agreement in the event Denver terminated its contract with Plaintiff. There is no evidence that Defendant ever sought to terminate the Agreement on that basis and no notice of such termination was given to Plaintiff by Defendant as required by § 13.18 of the Agreement.

23. Ultimately, in May 1995, Denver formally notified Defendant that it was not reviving or extending the contract (Exhibit 39). Defendant did not notify Plaintiff of the city’s action.

24. It is undisputed that 99% of the contract work had been performed by Plaintiff prior to delivery and installation which, combined, constitute only 1% of the work.

25. Pursuant to § 11.3 and Exhibit D of the Agreement, Plaintiff was to be paid $131,730 in three installments, with the first installment of 25% ($32,932.50) being due on the effective date of the Agreement. Defendant paid Plaintiff that amount in April 1993.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
989 F. Supp. 1352, 1998 U.S. Dist. LEXIS 326, 1998 WL 10632, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rocky-mountain-microsystems-inc-v-public-safety-systems-inc-cod-1998.