Johnson v. Benson

725 P.2d 21
CourtColorado Court of Appeals
DecidedApril 17, 1986
Docket84CA0619
StatusPublished
Cited by14 cases

This text of 725 P.2d 21 (Johnson v. Benson) is published on Counsel Stack Legal Research, covering Colorado Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Johnson v. Benson, 725 P.2d 21 (Colo. Ct. App. 1986).

Opinion

STERNBERG, Judge.

Defendants, James L. and Carl E. Benson (sellers), appeal from a judgment awarding plaintiffs, R.M. and Lindsey A. Johnson (buyers), restitution of money paid under a receipt and option contract. We affirm.

In August 1981, the parties executed a contract whereby buyers agreed to purchase a house to be constructed by sellers in the Aspen area. Contract provisions pertinent to this appeal state:

“Closing shall take place thirty-two (32) days after the issuance of the Certificate of Occupancy for the subject premises but in no event any earlier than February 15, 1982, nor any later than March 15, 1982.
*23 The hour and place of closing shall be as designated by sellers.
Time is of the essence hereof....”

The agreement specified a payment schedule. It also provided remedies: Upon buyers’ failure to make or tender payment or to perform “any other condition,” sellers could terminate the contract and keep all payments as liquidated damages; if sellers failed to perform any condition provided in the contract, buyers were given an election to rescind or proceed against sellers for specific performance and damages. Buyers made all payments as required by the agreement, totaling $110,000 at the time of the parties’ controversy.

As the period agreed upon for closing approached, buyers indicated that they would prefer a later date. The parties negotiated this point, but no agreement to modify the contract was reached. Sellers, however, understood that buyers had agreed to a March 15, 1982, closing and told their attorney to write to buyers requesting their signatures formalizing certain amendments to the contract. The resulting letter put forth the proposed extension of closing, stated the attorney’s understanding that a Certificate of Occupancy had been obtained for the property, and proposed deletion of the 32-day language quoted above. Buyers did not sign the proposed amendments.

As February 15 approached, sellers’ attorney became concerned at buyers’ lack of response and urged buyers by telephone that if no agreement regarding extension of closing was forthcoming, sellers would hold them to a closing on February 15 in order to protect sellers’ rights with respect to a claim of waiver of the “time is of the essence” clause of the contract. After further negotiation and discussion, sellers formally notified buyers by wire dated Febru-. ary 11 that closing would occur on February 15.

Buyers did not appear at the place and time designated by sellers. Consequently, on February 15, sellers’ attorney sent to buyers the following telegram:

“You have failed to close pursuant to your receipt and option' contract with Carl and Jim Benson dated August 18, 1981. Your contract is therefore null and void and all payments made by you will be retained by the Bensons as liquidated damages pursuant to [its terms].”

On February 17, plaintiff R.M. Johnson traveled from his home in Houston to Aspen, engaged counsel, and returned home. On February 21, sellers contacted buyers by telephone and assured them that they wanted to perform the contract. On February 22, buyers’ attorney filed this action seeking damages or specific performance. It is uncontroverted that as of February 15 only a temporary Certificate of Occupancy had been approved for the house.

After a bench trial, the court found, inter alia, that: “[Tjaken as a whole, the contract required substantial completion of the residence [and] [t]he procuring of a Certificate of Occupancy for the benefit of both parties 32 days prior to closing.” It further found that buyers had no obligation to be present for a February 15 closing, and that sellers’ February 15 telegram constituted an anticipatory repudiation of the contract which was acted upon by buyers, thus preventing timely retraction. These findings were adopted without change from proposed findings submitted by buyers. The trial court then concluded that, as sellers had “failed to perform conditions and obligations on their part to be performed, [and] failed to complete construction of the house prior to the last date for closing specified in the contract,” buyers’ performance was excused, and they were entitled to restitution of all payments made under the contract.

I.

Sellers contend that the trial court’s findings and conclusions are inadequate under C.R.C.P. 52(a) to support its judgment. They assert that critical issues were not addressed therein, including the questions *24 whether substantial completion and the obtaining of a Certificate of Occupancy were conditions precedent to buyers’ duty to close as directed by sellers and, if so, whether these conditions had been performed or waived. We disagree.

Where a trial court adopts findings proposed by a party, a reviewing court should carefully examine them in light of the whole record. See Ficor, Inc. v. McHugh, 639 P.2d 385 (Colo.1982). An appellate court:

“will assume that the trial judge examined the proposed findings and agreed that they correctly stated the facts as he himself found them to be.... It is only when the findings themselves are inadequate and do not indicate the basis for the trial court’s decision that the judgment will be reversed.”

Uptime Corp v. Colorado Research Corp., 161 Colo. 87, 420 P.2d 232 (1966). Under C.R.C.P. 52(a) “ ‘[t]he ultimate test as to the propriety of the findings is whether they are sufficiently comprehensive to provide a basis for decision and [are] supported in the evidence. ” Mowry v. Jackson, 140 Colo. 197, 343 P.2d 833 (1959). This standard is met when “the ultimate facts have been determined and conclusions of law are entered thereon.” Manor Vail Condominium Ass’n v. Town of Vail, 199 Colo. 62, 604 P.2d 1168 (1980).

The ultimate questions of fact before the court were: (1) whether buyers were obligated to close on February 15; (2) if not, whether sellers’ February 15 telegram constituted an anticipatory breach; and (3) if so, whether buyers relied upon the repudiation so as to preclude its retraction by sellers. The trial court expressly resolved these issues.

We conclude that the findings of the trial court provide a sound basis for its judgment. See Zimmerman v. Hinderlider, 112 Colo. 277, 148 P.2d 813 (1944) (on appeal, all presumptions are in favor of the trial court’s findings and judgment); City of Alamosa v. Holbert, 82 Colo. 582, 262 P. 87 (1927) (general findings create presumption that trial court found all facts necessary to sustain a judgment).

II.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lawry v. Palm
192 P.3d 550 (Colorado Court of Appeals, 2008)
Ranta Construction, Inc. v. Anderson
190 P.3d 835 (Colorado Court of Appeals, 2008)
Highlands Ranch University Park, LLC v. Uno of Highlands Ranch, Inc.
129 P.3d 1020 (Colorado Court of Appeals, 2005)
Fuhlrodt v. Rela, Inc.
71 F. App'x 615 (Ninth Circuit, 2003)
Albright v. McDermond
14 P.3d 318 (Supreme Court of Colorado, 2000)
In Re Mount Carbon Metropolitan District
242 B.R. 18 (D. Colorado, 1999)
Villa Sierra Condominium Ass'n v. Field Corp.
878 P.2d 161 (Colorado Court of Appeals, 1994)
Ruiz v. Varan
797 P.2d 267 (New Mexico Supreme Court, 1990)
Durango Transportation, Inc. v. City of Durango
786 P.2d 428 (Colorado Court of Appeals, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
725 P.2d 21, Counsel Stack Legal Research, https://law.counselstack.com/opinion/johnson-v-benson-coloctapp-1986.