City of Alamosa v. Holbert

262 P. 87, 82 Colo. 582, 1927 Colo. LEXIS 507
CourtSupreme Court of Colorado
DecidedDecember 5, 1927
DocketNo. 11,766.
StatusPublished
Cited by3 cases

This text of 262 P. 87 (City of Alamosa v. Holbert) is published on Counsel Stack Legal Research, covering Supreme Court of Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Alamosa v. Holbert, 262 P. 87, 82 Colo. 582, 1927 Colo. LEXIS 507 (Colo. 1927).

Opinion

Mr. Justice Sheabor

delivered the opinion of the court.

Deeehdaht in error, herein referred to as plaintiff, brought suit against plaintiff in error, herein designated as defendant, or the city, on a written contract for the sinking of an artesian well. Trial to the court without a jury, judgment for plaintiff, and defendant brings the case here.

The contract was entered into February 6, 1924, and contained the following, among other provisions:

“Unforeseen difficulties — No claim. — The contractor agrees that he will sustain all losses or damages arising from the action of the elements, the nature of the work to be done under the contract and specifications, or from any unforeseen obstructions or encumbrances which may be encountered in the prosecution of the work.

“Drilling. — The well shall be drilled at a place designated by the engineer. The hole shall be started with sufficient size to insure a depth of 1200 feet. * * *

The well shall be drilled to sufficient depth to insure contact with a big artesian sand below the one now furnishing water for the city water works. The engineer has the authority to decide as to what depth drilling shall cease.

“Water. — The engineer shall, at his discretion, conduct a twenty-four-hour test of each artesian sand encountered. The contractor agrees to drill to a deeper sand in case the engineer deems it necessary after such test or *584 tests. All water flowing from the well by reason of such test or tests shall be conducted into the city sewer system at the expense of the city.

“Casing. — The casing shall be set to a depth as sufficient to exclude or case off all soft or sandy material and said casing shall be firmly embedded in clay or gumbo at the lower end.”

For this work the plaintiff was to receive the sum of $2,000.

It appears that there are several artesian sands under the city of Alamosa which supply water and at the time this contract was entered into, the city was being supplied with artesian water from a well about 756 feet deep.

The evident purpose of requiring plaintiff to drill the xiew well to a depth to insure contact with the big artesian sand below the one then supplying the city with water was to iixcrease the water supply and avoid diminishing the flow from the existing well.

While the contract provided that the consideration should be paid in accordance with semi-monthly estimates furnished by the engineer, the plaintiff appears to have waived those estimates and has never beeix paid any part of the contract price.

About March 1, 1924, plaintiff commenced the construction of a well and drilled the same to a depth of about 788 feet when the drill-rod stuck in the quicksand and he was unable to complete it, and unable to set the casing according to contract and could not seal it in.

Being forced to abandon that well he moved to a new location selected by himself and the city water superintendent Mr. Bollier, and started the drilling of another well. When plaintiff had drilled the ixew well to a depth of about 788 feet his drill penetrated some two or three feet into a red heavy gravel. He testified that his bit was then so worn that he could not drill; that he could not cut in and started to pull the drill out; that he and his men agreed that it was a good water sand and he *585 called for Mr. Johnston, the city’s engineer, who drew the contract; that Johnston and he had agreed to set the casing in the first well at 777 feet and when Johnston came they tallied over the matter of setting the casing of this new well in the same clay. He then said: “It was a good clay and the contract called for it to be sealed in and he came np and I asked him if he was satisfied with the measurement of the well at 758 feet and he said well he felt he had to be satisfied with what he could measure and had measured it twice and I had once and it tallied and he said we might set the casing in this but with one understanding between me and Mr. Johnston I’ll tell the world and that was that I was to go inside of the casing and properly clean it out and drill in to this sand to determine to see if it wouldn’t be increased if it didn’t properly flow. * # * I reamed it out to eight inches to let the casing go down and we pulled out the reamer and thought we had it safe to go ahead and we attempted to set the casing and failed and we had to pull the casing out and re-ream it to get down to 770 feet, there is where we expected to set the casing at 770 feet, that was some feet above this strata of gravel and sand. * * * We set the casing at 765 or 766 feet * * * and we measured the casing up and it was 769 feet and 9 inches, and it measured that at that time; that is as close as Mr. Bollier could get it without cutting a joint and we thought that was good enough.”

Mr. Bollier and others assisted him in setting, the casing. He testified that a few days after setting the casing they put in the rods and cleaned it out so that the flow came in pretty strong; that they then cut the pipe off so that they could go inside and drill down to 816 feet and thoroughly develop that sand; that they measured the rods and Mr. Bollier added them up; that after going 816 feet and pulling the rods out they had a big flow of water.

The witness stated that at the first council meeting after the well was completed, Johnston was there and re *586 jected Ms work and would not allow the city to pay for it; that Johnston demanded that plaintiff finish the well; that several days later Johnston wrote him a letter telling him to pull the casing and drill the well deeper, which witness said was an impossibility and something he had never agreed to do; that he told Johnston whenever they set the casing they were done.

Mr. Bollier, the water superintendent, testified that the depth of the casing was 785 feet 7 inches; that after the casing had been set plaintiff drilled further to a depth of 816 feet; that a heavy flow came in; that the well was allowed to flow probably a month before it was turned into the reservoir; that the flow gradually increased until he shut the well off.

Joseph Hays testified that the casing was set at 769 feet 9 inches, after which they went down to 816 feet and cleaned out. Holbert was from four to six weeks sinking the well.

Evidence was introduced showing that there is a water bearing sand at about 730 feet; the next one 760 to 770 feet, and the next one 825 to 850 feet with a strong flow.

Reilly, a witness for defendant, testified that the two wells were getting water from different flows and he further testified that he could not say that the two wells were taking water from the same flow; that the only way he could tell that they were taking water from the same flow was the effect it has on one when the other is open; that whether they were taking it from the same flow he could not say and that the real test is to test the depth.

Before and at the time the court rendered judgment the judge made certain remarks to the effect that judgment ought to be entered as upon a quantum meruit.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Johnson v. Benson
725 P.2d 21 (Colorado Court of Appeals, 1986)
Ray L. Atchison Construction Co. v. Sossaman
717 P.2d 988 (Colorado Court of Appeals, 1985)
James v. James
262 P. 925 (Supreme Court of Colorado, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
262 P. 87, 82 Colo. 582, 1927 Colo. LEXIS 507, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-alamosa-v-holbert-colo-1927.