R.J. Cummins, d/b/a Bob Cummins Constr. Co. v. Bradford Sanitary Auth.

CourtCommonwealth Court of Pennsylvania
DecidedJune 8, 2020
Docket1000 & 1009 C.D. 2019
StatusUnpublished

This text of R.J. Cummins, d/b/a Bob Cummins Constr. Co. v. Bradford Sanitary Auth. (R.J. Cummins, d/b/a Bob Cummins Constr. Co. v. Bradford Sanitary Auth.) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
R.J. Cummins, d/b/a Bob Cummins Constr. Co. v. Bradford Sanitary Auth., (Pa. Ct. App. 2020).

Opinion

IN THE COMMONWEALTH COURT OF PENNSYLVANIA

Robert J. Cummins, d/b/a Bob : Cummins Construction Company : : v. : : Bradford Sanitary Authority, : No. 1000 C.D. 2019 Appellant : : Robert J. Cummins, d/b/a : Bob Cummins Construction Company, : Appellant : : v. : : No. 1009 C.D. 2019 Bradford Sanitary Authority : Submitted: May 15, 2020

BEFORE: HONORABLE P. KEVIN BROBSON, Judge HONORABLE ANNE E. COVEY, Judge HONORABLE BONNIE BRIGANCE LEADBETTER, Senior Judge

OPINION NOT REPORTED

MEMORANDUM OPINION BY JUDGE COVEY FILED: June 8, 2020

Bradford Sanitary Authority (Authority) appeals from the McKean County Common Pleas Court’s (trial court) June 27, 2019 order denying its Motion for Post-Trial Relief (Authority Motion). Robert J. Cummins d/b/a Bob Cummins Construction Company (Cummins) also appeals from the trial court’s June 27, 2019 order denying in part Cummins’ Motion to Mold the Verdict for Interest, Penalty Interest and Attorney’s Fees (Cummins Motion). The Authority presents four issues for this Court’s review: (1) whether the trial court erred by finding that the Authority’s Contract 2013-2 General Construction (Contract) was ambiguous, thereby allowing Cummins to introduce expert testimony; (2) whether the trial court erred by finding that the Authority acted in bad faith; (3) whether the trial court erred by allowing the jury to decide Cummins’ change order claims; and (4) whether the trial court erred by denying the Authority a new trial. Cummins presents two issues for this Court’s review: (1) whether the trial court erred by denying Cummins penalty interest; and (2) whether the trial court abused its discretion by denying Cummins the balance of its attorney’s fees. After review, we reverse the trial court’s June 27, 2019 order denying the Authority’s Motion, and vacate the trial court’s June 27, 2019 order denying, in part, Cummins’ Motion.

Background The Authority owns and operates a wastewater treatment plant (Plant) in Foster Township, McKean County, that serves the City of Bradford and other nearby communities. When the Authority sought to conduct Wastewater Treatment Plan Upgrades (Project), it retained Gannett Fleming, Inc. (GF) to provide engineering and construction management services. See Reproduced Record (R.R.) at 1152a. Part of the Project required the construction of concrete tanks containing sequencing batch reactors (SBR)1 to treat sewage and other wastewater at the Plant. In 2013, the Authority issued an Invitation for Bids (IFB) from contractors for the Project that included the Contract and documents attached thereto

1 “A[n SBR] is a type of bioreactor used to remove sludge and other organic matter from sewage in order to produce clean water for discharge.” Amici Br. at 3. More specifically, [a]n SBR sequentially conducts each phase of the treatment of wastewater in a single tank: filling the tank with untreated wastewater (fill stage); reacting the untreated wastewater with diffused oxygen (aeration stage); allowing the reacted wastewater to settle so solids can fall to the bottom of the tank (settle stage); decanting the treated water out of the tank (decant stage). Authority Br. at 11-12. 2 and incorporated therein (Contract Documents).2 The IFB included a Project Manual containing, inter alia, Instructions to Bidders and the Contract.3 Section 11393 of the Project Manual contained the specifications for the SBR and its ancillary structures, equipment and controls (SBR Specifications). See R.R. at 148a-171a. The Authority described that GF’s design and the SBR Specifications were based on

a continuous-flow SBR manufactured by ABJ Sanitaire . . . with four separate SBRs installed in 4 adjacent, contiguous tanks (Tanks 1-4) (thereby increasing the total volume of wastewater that could be treated). Tanks 1 and 2 shared a common ‘influent box’ where wastewater entered the SBR, as did Tanks 3 and 4. ‘Influent’ is the untreated wastewater, so the wastewater first entered the influent box. Each tank had its own manual gate in the influent box, and as designed the influent was to continuously and intentionally flow over the gate, which generally remained in the open position (unless a tank was being cleaned or repaired). Influent entered the influent boxes through 20- inch ductile iron influent pipes capable of supplying 13.88 million gallons per day (‘MGD’) of wastewater.

Authority Br. at 12 (record citations omitted); see also R.R. at 152a, 196a-198a. GF’s drawings, included in the Contract Documents, were of the above-described system. Notwithstanding, because the Project was competitively bid, in Section 1.05

2 “‘The statutory mandate of competitive bidding is grounded in sound public policy.’ Philips Bro[s.] Elec[.] Contractors, Inc. v. P[a.] T[pk.] Comm[’]n, 960 A.2d 941, 945 (Pa. Cmwlth. 2008). ‘[I]t is the taxpaying citizen who provides the necessary funds and whose interest must be protected.’ Yohe [v. City of Lower Burrell,] 208 A.2d [847,] 850 [(Pa. 1965)].” Hanisco v. Twp. of Warminster, 41 A.3d 116, 123 (Pa. Cmwlth. 2012). The first round of bids were received in June 2013. However, the Project was rebid, and rebids were received in September 2013. See R.R. at 632a-633a. 3 The Contract consisted of the documents set forth in Article 15.01 of the parties’ Agreement, see R.R. at 56a, and in Article 1.01.A.16 of the General Conditions (see R.R. at 317a), which included, inter alia: Instructions to Bidders, Agreement, General Conditions, Supplementary Conditions, Specifications, GF’s Contract Drawings, Addenda, Agreement Exhibits including the Notice to Proceed and Cummins’ Bid, plus any Written Amendments, Work Change Directives and Change Orders to be delivered on or after the Contract’s effective date (collectively, the Contract Documents). 3 of the SBR Specifications, the Authority designated as “ACCEPTABLE MANUFACTURERS”: A. ABJ Sanitaire B. Ashbrook Simon Hartley [(Ashbrook)] C. Aqua Aerobics

R.R. at 152a. Although the SBR Specifications authorized bidders to select Ashbrook or Aqua Aerobics as acceptable manufacturers, Section 11.01.B of the Instructions to Bidders (Section 11.01.B.3) stated:

1. Products named on the Contract Drawings, if any, and products of manufacturers named first throughout the Project Manual[,] constitute [GF’s] design. 2. Products of named manufacturers, other than the first named manufacturer, appearing throughout the Project Manual or on the Contract Drawings are accepted as equal; however, the requirements of [Section] 6.03 of the General Conditions regarding ‘equipment’ and ‘machinery’ shall apply. 3. If products of manufacturers other than those named first differ from those named first in the Project Manual or on the [Contract] Drawings to the extent that their proper incorporation into the [work required by the Contract Document (]Work[)4] requires changes to the structural, piping, mechanical, electrical, instrumentation, or any

4 Section 1.01.A.42 of the General Conditions (DEFINED TERMS) defined “Work” as: The entire completed construction, or the various separately identifiable parts thereof required to be provided under the Contract Documents. Work includes and is the result of performing or providing all labor, services, and documentation necessary to produce such construction, and furnishing, installing, and incorporating all materials and equipment into such construction, all as required by the Contract Documents. R.R. at 320a.

4 other changes of whatsoever nature, the [c]ontractor shall be responsible for such changes.

Section 11.01.B (R.R. at 137a).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Florida Bd. of Regents v. Mycon Corp.
651 So. 2d 149 (District Court of Appeal of Florida, 1995)
Vogel v. Berkley
511 A.2d 878 (Supreme Court of Pennsylvania, 1986)
Philips Bros. Electrical Contractors, Inc. v. Pennsylvania Turnpike Commission
960 A.2d 941 (Commonwealth Court of Pennsylvania, 2008)
A. G. Cullen Construction, Inc. v. State System of Higher Education
898 A.2d 1145 (Commonwealth Court of Pennsylvania, 2006)
Parshall v. Parshall
560 A.2d 207 (Supreme Court of Pennsylvania, 1989)
Walnut Street Associates, Inc. v. Brokerage Concepts, Inc.
982 A.2d 94 (Superior Court of Pennsylvania, 2009)
Kripp v. Kripp
849 A.2d 1159 (Supreme Court of Pennsylvania, 2004)
Walnut Street Associates, Inc. v. Brokerage Concepts, Inc.
20 A.3d 468 (Supreme Court of Pennsylvania, 2011)
A. Scott Enterprises v. City of Allentown, Aplt.
142 A.3d 779 (Supreme Court of Pennsylvania, 2016)
PBS Coals, Inc. and Penn Pocahontas Coal, Co. v. Comwlth of PA, DOT
206 A.3d 1201 (Commonwealth Court of Pennsylvania, 2019)
Hanisco v. Township of Warminster
41 A.3d 116 (Commonwealth Court of Pennsylvania, 2012)
Southwestern Energy Production Co. v. Forest Resources, LLC
83 A.3d 177 (Superior Court of Pennsylvania, 2013)
Commonwealth v. E. J. Albrecht Co.
430 A.2d 328 (Commonwealth Court of Pennsylvania, 1981)
W.G. Yates & Sons Construction Co. v. United States
53 Fed. Cl. 83 (Federal Claims, 2002)
George Sollitt Construction Co. v. United States
64 Fed. Cl. 229 (Federal Claims, 2005)
Conner Brothers Construction Co. v. United States
65 Fed. Cl. 657 (Federal Claims, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
R.J. Cummins, d/b/a Bob Cummins Constr. Co. v. Bradford Sanitary Auth., Counsel Stack Legal Research, https://law.counselstack.com/opinion/rj-cummins-dba-bob-cummins-constr-co-v-bradford-sanitary-auth-pacommwct-2020.