Ritchie's Food Dist. v. Ref. Const. Ser., Unpublished Decision (4-23-2004)

2004 Ohio 2261
CourtOhio Court of Appeals
DecidedApril 23, 2004
DocketNo. 03CA713.
StatusUnpublished
Cited by3 cases

This text of 2004 Ohio 2261 (Ritchie's Food Dist. v. Ref. Const. Ser., Unpublished Decision (4-23-2004)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ritchie's Food Dist. v. Ref. Const. Ser., Unpublished Decision (4-23-2004), 2004 Ohio 2261 (Ohio Ct. App. 2004).

Opinion

DECISION AND JUDGMENT ENTRY
JUDGMENT ENTRY
{¶ 1} Refrigerated Construction Services, Inc. ("RCS") appeals the Pike County Court of Common Pleas decision denying its motion to stay the proceedings pending arbitration. RCS contends that the trial court erred by finding that the contract between RCS and Ritchie's Food Distributor, Inc. ("Ritchie") did not include an arbitration clause. Because the contract is ambiguous, and because some competent, credible evidence supports the trial court's determination that the parties did not intend to include the arbitration clause in the contract, we disagree. RCS also contends that the trial court erred in refusing to enforce the arbitration clause because Ritchie did not demonstrate that its agreement to the arbitration clause was induced by fraud. Because we affirm the trial court's determination that Ritchie did not assent to the arbitration clause at all, Ritchie did not need to demonstrate fraud. Accordingly, we overrule RCS's assignments of error and affirm the judgment of the trial court.

I
{¶ 2} In 1999, RCS and Ritchie entered into a construction contract for RCS to construct a refrigerated warehouse in Pike County, Ohio. Under the contract, Ritchie agreed to pay RCS approximately $1,400,000 for the warehouse. Ritchie made progress payments as RCS completed work, and actually paid RCS more than the original $1,400,000 contract price. However, after RCS completed the project, Ritchie refused to pay $40,000 of RCS's final bill, claiming that there were problems with the construction of the building.

{¶ 3} RCS demanded that the dispute be submitted to arbitration pursuant to an arbitration clause contained at paragraph 9.10.4 of the contract. Ritchie responded by filing a complaint for breach of contract and a motion to enjoin the arbitration in the trial court. RCS filed a motion to dismiss the complaint or stay the proceedings pending arbitration under R.C.2711.02. After review, the trial court determined the contract is ambiguous with regard to whether the parties intended to agree to the arbitration clause. The court overruled RCS's motion to dismiss and enjoined the arbitration. RCS then filed a motion to vacate the order or to stay the proceedings pending appeal. The trial court held a hearing and overruled RCS's motion.

{¶ 4} RCS appealed to this court. We determined that the trial court had not yet issued a final ruling on whether an arbitration clause exists between the parties. Accordingly, we dismissed the appeal for lack of a final appealable order. We remanded to the trial court with instructions for the court to (1) hold an evidentiary hearing to resolve the factual questions concerning the very existence of an agreement to arbitrate, and (2) issue a final ruling on RCS's motion for a stay. Ritchie'sFood Distributor, Inc. v. Refrigerated Constr. Sers., Inc., Pike App. No. 02CA683, 2002-Ohio-3763.

{¶ 5} The trial court held a hearing and received testimony and exhibits. The evidence at the hearing revealed that RCS provided a construction industry form, which RCS procured from the American Institute of Architects, for the parties to use as their contract. At the top of the contract, RCS designated Ritchie as the "Owner," RCS as the "Contractor," and "Ritchie's Food Distributor" as the "Project." Under "Architect," RCS filled in "N/A."

{¶ 6} Representatives of Ritchie and RCS initialed each page of the agreement and signed the final page of the agreement. Predictably, a form created by the American Institute of Architects provides prominently for an architect's role throughout the contract. In particular, Article 9 of the contract is entitled "ARCHITECT'S ADMINISTRATION OF THE CONTRACT." Article 9 details requirements that the Architect approve all work, changes to the agreement, and bills for progress payments. Additionally, section 9.10 of Article 9 relates to claims and disputes, and subsection 9.10.1 provides that claims and disputes shall initially be referred to the Architect, then to mediation. Subsection 9.10.4 provides that claims not resolved by mediation shall be decided by arbitration.

{¶ 7} Based upon Mr. Ritchie's testimony and the exhibits it received at the hearing, the trial court concluded that the parties did not intend for the provisions of the contract relating to the Architect to bind them. The court further determined that this intention extended to exclude subsection 9.10.4 from the scope of the parties' intended agreement. Therefore, the trial court determined that Ritchie is not contractually required to submit to arbitration, and overruled RCS's motions.

{¶ 8} RCS timely appeals, asserting the following assignments of error: "I. The trial court erred by finding the parties did not contract to arbitrate their disputes. II. The trial court erred by not staying the action pursuant to R.C. 2711.02."

II
{¶ 9} When parties to a contract have agreed in writing to arbitration of disputes, the trial court must, upon application of a party and being satisfied that the issue is referable to arbitration, stay its proceedings pending the arbitration. R.C.2711.02(B). However, "arbitration is a matter of contract and a party cannot be required to submit to arbitration any dispute which he has not agreed to so submit * * *." Council of SmallerEnterprises v. Gates, McDonald Co., 80 Ohio St.3d 661, 666-67,1998-Ohio-172; Divine Constr. Co. v. Ohio American Water Co. (1991), 75 Ohio App.3d 311, 316. If the party challenging arbitration has not agreed to arbitration by contract, there is a presumption against arbitration. Bell v. Everen Securities,Inc. (Feb.2, 2000), Summit App. No. 19581, citing Council ofSmaller Enterprises at 667.

{¶ 10} Until the existence of an agreement to arbitrate is established, "[o]ur inquiry is `"strictly confined" * * * to whether the parties agreed to submit disputes * * * to arbitration.'" (First alteration original.) Council of SmallerEnterprises at 668. General contract principals apply to the determination of whether the parties agreed to an arbitration clause. Id. at 668; Divine Constr. Co. at 316; Bell, supra. After the existence of an agreement to arbitrate is established, there is a strong presumption in favor of arbitration, and any ambiguities or doubts regarding the scope of the arbitration clause are resolved in favor of arbitration. Sasaki v. McKinnon (1997), 124 Ohio App.3d 613, 616; Gaffney v. Powell (1995),107 Ohio App.3d 315, 320.

{¶ 11} General contract law holds that a court must interpret a contract so as to carry out the intent of the parties. FosterWheeler Enviresponse, Inc. v. Franklin Cty. Convention FacilitiesAuth. (1997), 78 Ohio St.3d 353; Skivolocki v. East Ohio GasCo. (1974), 38 Ohio St.2d 244, paragraph one of the syllabus.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hay v. Summit Funding, Inc.
2017 Ohio 8261 (Ohio Court of Appeals, 2017)
Short v. Greenfield Meadows Assoc., 07ca14 (6-24-2008)
2008 Ohio 3311 (Ohio Court of Appeals, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
2004 Ohio 2261, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ritchies-food-dist-v-ref-const-ser-unpublished-decision-4-23-2004-ohioctapp-2004.