Riley Woodworks LLC v. Bond

CourtSuperior Court of Maine
DecidedMarch 3, 2016
DocketCUMcv-13-326
StatusUnpublished

This text of Riley Woodworks LLC v. Bond (Riley Woodworks LLC v. Bond) is published on Counsel Stack Legal Research, covering Superior Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Riley Woodworks LLC v. Bond, (Me. Super. Ct. 2016).

Opinion

( (

STATE OF MAINE SUPERlOR COURT CUMBERLAND, SS. CIVIL ACTION DOCKET NO. CV-PORSC-13-326

RlLEY WOODWORKS LLC ) ) Plaintiff and Counterclaim ) Defendant, ) ) v. ) JUDGMENT ) CHRlSTOPHER BOND, SEBEGO LAKE, ) ROWING AND SAILING CLUB, LLC, ) ) Defendants and Counterclaim ) Plaintiffs ) )

This matter came before the court during the course of a jury-waived trial. The parties

filed post-trial briefs on January 26, 2016 . The court has carefully considered the evidence

presented by the parties and adjudges as follows .

I. FACTS

The parties ' dispute involves competing allegations of a breach of contract. The parties

consummated two contracts. 1 One contract involved the promise by Plaintiff to perform certain

renovations, improvements and alterations to a structure owned by Defendants Bond and Sebago

Rowing, located in Standish, Maine . During the trial, this property was commonly referred to by

the parties as the "Sebago Project." The second contract involved renovation work to be

performed on a condominium owned by Christopher Bond, located in South Portland, Maine and

to which the parties have referred as the "Harborplace Project." For purposes of analytical

clarity, the court examines the two contracts in chronological succession.

1 Mr. Bond contends that these contracts should be considered a single contract. There was nothing in the record to support such a conclusion. The two projects involved distinctly different properties and involved equally different contractual agreements . ( (

Riley submitted several iterations of estimates, outlining time and material to complete

certain renovations on the Sebago property . Riley estimated the Sebago cost at $26,781.19; the

sum of labor ($16,327) and materials ($10,454.19) . Riley and Bond signed the Sebago contract

on November 28, 2012. Bond inserted the total estimate figure in handwriting on the contract

and scribbled through the provision that reduced the figure into separate estimated time and

materials. Bond also attempted to delete the merger clause and attached the revised estimate as

part of the contract, which itself reflected the estimated time and materials.

The Sebago project involved an older building that was in exceptionally poor repair.

Riley testified that this is precisely the type of project that requires a baseline estimate but that

often involve unforeseen difficulties, such that require the scope of work to change. Such was in

fact the case with the Sebago property. Riley disclosed to Bond the issues presented by the old

structure, such as rotted floor joists and subfloor and outdated electrical systems. Bond agreed to

have Riley address those issues with the attendant increased cost to do so. Riley continued the

work on the Sebago proj ect.

In January 2012, Bond asked Riley to renovate Harborplace. Riley and Bond signed the

contract, which consisted of a host of handwritten estimates. Bond placed some urgency on the

Harborplace project and as such, asked Riley to make it a priority. As with the Sebago project,

Bond requested a number of changes and extras to the Harborplace project that delayed its

completion.

Riley had substantially completed the work to Harborplace by March 27, 2013. Riley

requested final payment of $6,674, plus payment for the extra work he performed. Bond

conceded at trial that he owed Riley this sum, but refused payment because the remaining extra

work required an additional day to complete. This refusal was the catalyst, along with a general

2 (

pastiche of conflicting personality types, to Bond's letter of March 28, 2013 to Riley, instructing

Riley to stop work on both projects. Riley complied, leaving both job sites. A final demand

from Riley to Bond for payment related to the Sebago project was memorialized in a letter dated

May 23 2013 . Bond refused payment of any kind, nature and amount for both projects. Riley

recorded liens on both properties and this action ensued.

The material facts were not generally in dispute and are not particularly complex, despite

the parties' consuming efforts to characterize these facts . This is not entirely unique in such

small construction contract disputes, but perhaps more overwrought here than typically is the

case.

Plaintiffs Exhibits 15-17 support actual costs of the Sebago and Harborplace projects,

including the amount paid by Bond. Riley testified and the court finds that the labor costs were

reasonable, necessary and customary. Mr. Bond did not at trial dispute the labor costs related to

Harborplace. As for Sebago, Mr. Bond challenges those labor costs that exceeded the estimated

cost pointing out for what evidentiary value it has, that Mr. Bond did not memorialize the labor

increases. The labor costs in dispute are for demolition, foundation, roofing, electrical, plumbing

and painting. The tally of these above-estimate costs is $8,908.00. Mr. Bond disputes these

costs as being presented through a final invoice after the unhappy dissolution of the business

relationship between the parties. As such, Mr. Bond urges the court to discredit the accuracy of

these costs as reflecting nothing more than inflated charges that were motivated by Mr. Riley's

anger toward Mr. Bond. The court declines to adopt that characterization and finds the above-

estimated costs for work actually performed by Mr. Riley to be supported by the balance of the

record, to include Plaintiffs Exhibit 15 and testimony by Mr. Riley and supporting time cards.

3 (

Defendants assert counterclaims for breach of contract in the form of faulty workmanship

and untimely completion, violations of the Home Construction Contract Act, and Unfair Trade

Practices Act.

II. Conclusions

In order to prevail on the contract claims, the parties must prove (1) breach of a material

contract term; (2) causation; and (3) damages. See Me. Energy Recovery Co. v. United Steel

Structures, Inc., 1999 ME 31, p 7, 724 A.2d 1248.

A material breach of contract "is a non-performance of a duty that is so material and important as

to justify the injured party in regarding the whole transaction as at an end." Jenkins, Inc. v. Walsh

Bros., Inc., 2001 ME 98, P 13, 776 A.2d 1229, 1234 (quotation marks omitted); see also Forrest

Assocs. v. Passamaquoddy Tribe, 2000 ME 195 , P 9, 760 A.2d 1041, 1044 (stating that "whether

a breach has occurred ... [is a] question[] of fact").

The ineluctable conclusion is that Mr. Bond's failure to pay any amount toward the

Harborplace invoice constituted a material breach of contract. Mr. Bond 's argument that he did

not yet owe the balance because work remained at Harborplace, estimated to have constituted

one day, is of no moment to the legal analysis . Riley 's testimony that all contractual work was

completed is credible and that whatever "extra" work remained should not have formed the basis

for Mr. Bond to fail to pay any amount whatever.

Mr. Bond' s demand that Riley stop work on both jobs on March 28 , 20 13 (Plaintiff's

Exh. 12) constituted a material breach of the Sebago contract, insofar as that did not absolve Mr.

Bond fro m the outstanding amounts owed on the contract and was merely a reaction to Riley's

March 27 demand for payment on the projects.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Forrest Associates v. Passamaquoddy Tribe
2000 ME 195 (Supreme Judicial Court of Maine, 2000)
Frost v. Barrett
246 A.2d 198 (Supreme Judicial Court of Maine, 1968)
Raisin Memorial Trust v. Casey
2008 ME 63 (Supreme Judicial Court of Maine, 2008)
Maine Energy Recovery Co. v. United Steel Structures, Inc.
1999 ME 31 (Supreme Judicial Court of Maine, 1999)
Jenkins, Inc. v. Walsh Bros., Inc.
2001 ME 98 (Supreme Judicial Court of Maine, 2001)
Maine Mutual Fire Insurance v. Watson
532 A.2d 686 (Supreme Judicial Court of Maine, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
Riley Woodworks LLC v. Bond, Counsel Stack Legal Research, https://law.counselstack.com/opinion/riley-woodworks-llc-v-bond-mesuperct-2016.