Riggs v. Curran

863 F.3d 6, 2017 WL 2928123, 2017 U.S. App. LEXIS 12307
CourtCourt of Appeals for the First Circuit
DecidedJuly 10, 2017
Docket16-2083P
StatusPublished
Cited by9 cases

This text of 863 F.3d 6 (Riggs v. Curran) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Riggs v. Curran, 863 F.3d 6, 2017 WL 2928123, 2017 U.S. App. LEXIS 12307 (1st Cir. 2017).

Opinion

TORRUELLA, Circuit Judge.

Benjamin Riggs, Laurence Ehrhardt, and the Rhode Island Manufacturers Association (collectively, “Plaintiffs”) challenge the development of an .offshore wind farm (the “Wind Farm”) near Block Island, Rhode Island. The district court dismissed Plaintiffs’ claims, ruling that - they were barred by Rhode Island’s three-year personal injury statute of limitations. We affirm. , .

I. BACKGROUND

A. Factual Background

In 2009, the Narragansett Electric Company, d/b/a National Grid (“National Grid”) entered into a power purchase agreement with Deepwater Wind Block Island, LLC (“Deepwater”), pursuant to a Rhode Island statute seeking to facilitate the development of a “newly developed renewable energy resources project of ten (10) megawatts or less” near Block Island. 2009 R.I. Pub. Laws ch. 53, § 1. Under the agreement, National Grid was to pass on the cost of constructing and operating the Wind Farm to mainland Rhode Island ratepayers, increasing their electricity rates for up to twenty years;

On . December 10, 2009, National Grid submitted the agreement for approval to the Rhode Island Public Utilities Commission (the “PUC”), which, on March 30, 2010, rejected the application because it was not commercially reasonable. The PUC found, among other things, that ratepayers would pay above-market rates for the entire twenty-year period and that the project offered poor value when measured against other renewable-energy projects.

On June 30, 2010, National Grid submitted a slightly-revised power purchase agreement (the “PPA”) after the Rhode Island General Assembly amended the statutory definition of “commercial reasonableness” applicable to the Wind Farm and directed the PUC to apply this amended standard in reviewing any future application. See 2010 R.I. Pub. Laws ch. 32, § 1 (codified at 39 R I. Gen. Laws § 39-26.1-7). The PPA provided that “[t]he effectiveness of. this Agreement ... is conditioned upon and shall not become effective or binding until the receipt of the PPA Regulatory Approval,” meaning “the PUC’s approval of this Agreement without material modification or conditions pursuant to [R.I. Gen. *9 Laws § 39-26.1-7].” On August 11, 2010, the PUC granted the approval, in large part due to the newly-adopted standard. The PUC issued the -order memorializing its decision on August 16, 2010 (the “PUC Order”), stating that the PPA “met the intent and requirements of the 2010 Amendments to R.I. Gen. Laws § 39-26.1-7.”

The PUC Order contained no conditions precedent, although the PPA’s terms' allowed Deepwater to subsequently terminate the approved and effective PPA if certain tax credit deadlines in the Internal Revenue Code were not extended, if Deepwater could not secure tax equity financing, or if Deepwater failed to timely receive additional approvals from other government entities, including:

1. Approval and a license from the Rhode Island Coastal Resources Management Council;
2. Permits under the federal Rivers and Harbors Act and the federal Clean Water Act from the U.S. Army Corps of Engineers;
3. A Conformity Determination/Air Emissions Permit and a General Stormwater Permit from the Environmental Protection Agency; and
4. Approval from the Rhode Island Department of Transportation, the Rhode Island Natural History Survey, and several municipal entities for laying the cable transmitting power from the Wind.Farm to the mainland.

After obtaining the PUC’s approval, Deep-water applied for and received all required permits by the end of 2014. In 2016, after the project received new financing, construction of the Wind Farm became imminent. 1

' Throughout this period, the Wind Farm faced - numerous challenges. Multiple parties, including members of the Rhode Island Manufacturers Association, intervened in the PUC proceeding. Some parties then challenged the PUC Order bn state law grounds in the Rhode Island Supreme. Court, and on August 1, 2011, that court affirmed the PUC Order. In re Review of Proposed Town of New Shoreham Project, 19 A.3d 1226 (R.I. 2011).

Thereafter, Benjamin Riggs filed two administrative petitions with the Federal Energy Regulatory Commission (“FERC”) on August 22, 2012 and April 21, 2016, alleging that the PUC Order 'violated the Federal Power Act (the “FPA”), the Public Utilities Regulatory Policies Act (“PURPA”), and the Supremacy and Commerce Clauses of the U.S. Constitution. On October 18, 2012 and June 18, 2015, FERC issued notices of its intention not to act on the petitions and stated that “Mr. Riggs may himself bring an enforcement action against the Rhode Island Commission in the appropriate court.” 141 F.E.R.C, ¶ 61,172 (2012); 161 F.E.R.C. ¶ 61,222.

B. Procedural History

Plaintiffs are Rhode Island ratepayers who claim that their economic interests will be adversely affected because the PPA will raise their electricity bills. On August 14, 2016, four years and 364 days after the issuance of the PUC Order,. Plaintiffs filed this lawsuit against three PUC commissioners, in their official capacities, National Grid, and Deepwater (collectively, “Defen-dánts”) in the United States District Court for the District of Rhode Island, arguing that the PUC Order violated the FPA, PURPA, and the Commerce and Supremacy Clauses of the U.S. Constitution. The *10 district court never reached the merits. Instead, it held that Plaintiffs’ complaint was time-barred. Riggs v. Curran, 196 F.Supp.3d 338 (D.R.I. 2016). It reasoned that 28 U.S.C. § 2462, the federal statute of limitations for civil enforcement actions, did not apply, as the case is neither a government enforcement action nor an enforcement action brought by a private attorney general. Id. at 340-41. Instead, the district court applied Rhode Island’s three-year statute of limitations for personal injury actions to Plaintiffs’ claims. Id. at 341-42.

The district court then determined that the clock started to run on Plaintiffs’ claims on August 16, 2010, when the PUC Order was issued. Id. at 340. It rejected Plaintiffs’ arguments that their causes of action accrued only when Defendants obtained all of the permits required by the PPA, when Plaintiffs were first charged higher rates, or after Plaintiffs exhausted all of their administrative remedies. Id. at 342-44.

H. ANALYSIS

We review a district court’s order granting a motion to dismiss under Rule 12(b)(6) de novo. Guadalupe-Báez v. Pesquera, 819 F.3d 509, 514 (1st Cir. 2016). “In conducting this review, we accept the truth of all well-pleaded facts and draw all reasonable inferences therefrom in the pleader’s favor.” Id. (quoting Grajales v. P.R. Ports Auth., 682 F.3d 40

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gordon v. Neronha
D. Rhode Island, 2025
Dougan v. Centerplate, Inc.
S.D. California, 2023
(PC) Schowachert v. Polley
E.D. California, 2023
Zhao v. CIEE, Inc.
3 F.4th 1 (First Circuit, 2021)
(PC) Luedtke v. Griesbach
E.D. California, 2021
Short v. Brown Univ.
320 F. Supp. 3d 363 (D. Rhode Island, 2018)
Zell v. Ricci
321 F. Supp. 3d 285 (D. Rhode Island, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
863 F.3d 6, 2017 WL 2928123, 2017 U.S. App. LEXIS 12307, Counsel Stack Legal Research, https://law.counselstack.com/opinion/riggs-v-curran-ca1-2017.