Riegel Power Corporation Mount Vernon Mills, Inc. v. Voith Hydro Crowder Construction Company

888 F.2d 1043, 11 U.C.C. Rep. Serv. 2d (West) 552, 1989 U.S. App. LEXIS 16799, 1989 WL 131688
CourtCourt of Appeals for the Fourth Circuit
DecidedNovember 6, 1989
Docket88-1316
StatusPublished
Cited by15 cases

This text of 888 F.2d 1043 (Riegel Power Corporation Mount Vernon Mills, Inc. v. Voith Hydro Crowder Construction Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Riegel Power Corporation Mount Vernon Mills, Inc. v. Voith Hydro Crowder Construction Company, 888 F.2d 1043, 11 U.C.C. Rep. Serv. 2d (West) 552, 1989 U.S. App. LEXIS 16799, 1989 WL 131688 (4th Cir. 1989).

Opinion

DONALD RUSSELL, Circuit Judge;

This is an action by a buyer-plaintiff to recover of a seller-defendant damages for breach of a warranty of merchantability and freedom of defects in connection with the sale of an electric turbine. The buyer-plaintiff originally was Riegel Textile Company, but Riegel Power Corporation and Mount Vernon Mills, Inc. are the successors in “interest or assignees of Riegel Textile rights under the contract” and sue as such. The plaintiffs are collectively referred to by the parties and the district court as “Riegel”; we do likewise. The defendant Voith Hydro is the successor in interest of the initial defendant, Allis-Chal-mers Hydro, Inc. We refer herein to the defendant as “Voith Hydro.” The defendant pled by way of defense (1) the provision in the contract of sale of an exclusive limitation of liability for a breach of warranty to an obligation to repair or replace and (2) the provision proscribing recovery of consequential damages. Admitting the exclusive limitation of the limitation provision, the plaintiff responded that under Delaware law, which was controlling, an exclusive limitation of warranty liability is ineffective “where circumstances cause an exclusive or limited remedy to fail of its essential purpose,” 6 Del.Code § 2-719(2), and that in this case there is such failure of “essential purpose.”

On motion for summary judgment, based on affidavits filed by the parties, the district court sustained, under Delaware law, *1044 the validity of the exclusive limitation of the liability clause in the contract of sale herein and found that such provision had not failed of its “essential purpose.” It therefore granted judgment in favor of the defendant on that ground and did not address the provision in the contract proscribing recovery of consequential damages. We affirm.

On February 12, 1982, the plaintiff accepted a written offer of the defendant to supply a hydro-electric turbine for use in the plaintiff’s Ware Shoals (South Carolina) installation. The installation of the turbine was contracted by Riegel to a third party. The defendant shipped, as agreed, certain parts to be imbedded into the concrete foundation below the turbine and in January 1983 was ready to deliver and tendered, as if actually shipped, the turbine. The plaintiff, however, was not ready to accept delivery and requested the defendant not to ship the turbine. Due to this delay by the plaintiff and its installation contractor, the turbine was not actually installed and put in operation until June 11, 1984.

The repair or replace warranty obligation of the plaintiff under the contract of sale had a time limit of 18 months for delivery or tender of delivery. Such warranty would expire in July 1984, two or three weeks after the turbine was put in operation. The defendant called this fact to the plaintiffs attention by letter of February 17, 1984, and offered, for a fee, to extend the warranty. The plaintiff did not avail itself of the offer. On its copy of the defendant’s letter of February 17, someone in the plaintiff’s organization with the initials “RG” had written as of “2-27-84 not necessary generator will be insurance.” The defendant took this to mean that, since the plaintiff already had a usable turbine and this new turbine was to supplement or operate as a back-up for the existing turbine, the latter turbine would provide the “necessary” insurance. Whatever the reason, the plaintiff did not elect to extend the warranty which, by its terms, expired in July 1984. Even though the warranty had expired, caused, as defendant says, largely by the fact that “the construction and installation schedules (which were the responsibility of third parties engaged by the plaintiff) were in excess of one year late,” the defendant declared in a letter to the plaintiff that nonetheless it committed itself to “the successful start-up and commissioning of the Ware Shoals unit” and it carried out this commitment by promptly responding to every complaint of the plaintiff and of correcting every problem until full operation.

After joinder of issues, the parties engaged in certain discovery. In answer to an interrogatory, the plaintiff listed four times during which the turbine was down for repairs on account of which it premised its claim of failure of its essential purpose defense. The first of these occurred in July 1984. The other problems occurred at various times from July 1984 until 1987, all after the warranty had expired. The turbine operated without any significant problems from October 1985 to October 1986. Any problems were corrected and the turbine was fully operational on July 26, 1984, thereby satisfying the commitment made by the defendant.

The plaintiff sought to prove by some records supplied by the affidavit of its president that because of “mechanical failures” the turbine in 1987 was inoperable for about half the time between 1984 and 1987 when the turbine became fully operational. The district court dismissed this evidence because the plaintiffs had “not made the requisite connection between the turbine’s lost time or possible future problems and any act attributable to [the defendant].” This finding was based on the records themselves and on other facts in the record, particularly the affidavit of the defendant’s project manager. In the affidavit of the defendant’s project manager for the Ware Shoals project he stated that “most or all of these problems (between 1984 and 1987) were caused by Riegel Textile’s (or its contractor’s) negligent installation of the turbine, Riegel Textile’s and the plaintiffs’ negligent maintenance and operation of the turbine, and the negligence of Riegel Textile, the plaintiffs, and their agents in overriding, bypassing or disabling certain protective devices on the tur *1045 bine.” It seems undisputed that, whatever differences may have existed as to the cause of the problems encountered in the shakedown of the turbine, between 1984 and early 1987 “Voith Hydro or A-C Hydro promptly sent, at no cost to Riegel or the plaintiffs, repair personnel to Ware Shoals to perform the diagnostic and repair services necessary to render and keep the turbine operational.” The plaintiffs made no attempt to refute this affidavit.

The defendant moved for summary judgment, contending that the undisputed record established that it had satisfied the requirement of repair or replace, which was the exclusive remedy under the contract of sale for breach of warranty. The parties agreed that the exclusive remedy for breach of warranty in this case was limited to repair or replace. Such a limitation was admittedly valid under the controlling Delaware Code. It seems equally agreed that the defendant responded promptly to every complaint of the plaintiffs and did finally furnish the plaintiffs a fully operational turbine. The real issue in the case, as posed by the plaintiffs, was whether the lost time in the operation of the turbine while the defendant was repairing the turbine was such that in a commercial sale such as this one it could be said that the exclusionary remedy for breach of warranty under the contract of sale had failed its “essential purpose.” The district judge found that the plaintiffs had failed to offer any credible proof to support the claim that the exclusive limitation had failed its “essential purpose” and, therefore, granted defendant’s motion for summary judgment. We agree.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Baney Corp. v. AGILYSYS NV, LLC
773 F. Supp. 2d 593 (D. Maryland, 2011)
Potomac Constructors, LLC v. EFCO Corp.
530 F. Supp. 2d 731 (D. Maryland, 2008)
Patapsco Designs, Inc. v. Dominion Wireless, Inc.
276 F. Supp. 2d 472 (D. Maryland, 2003)
Rheem Manufacturing Co. v. Phelps Heating & Air Conditioning, Inc.
746 N.E.2d 941 (Indiana Supreme Court, 2001)
Caudill Seed and Warehouse Co., Inc. v. Prophet 21, Inc.
123 F. Supp. 2d 826 (E.D. Pennsylvania, 2000)
Intrastate Piping & Controls, Inc. v. Robert-James Sales, Inc.
733 N.E.2d 718 (Appellate Court of Illinois, 2000)
Pierce v. Catalina Yachts, Inc.
2 P.3d 618 (Alaska Supreme Court, 2000)
Eastman Chemical Co. v. Niro, Inc.
80 F. Supp. 2d 712 (S.D. Texas, 2000)
Myrtle Beach Pipeline Corp. v. Emerson Electric Co.
843 F. Supp. 1027 (D. South Carolina, 1993)
Middletown Concrete Products, Inc. v. Black Clawson Co.
802 F. Supp. 1135 (D. Delaware, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
888 F.2d 1043, 11 U.C.C. Rep. Serv. 2d (West) 552, 1989 U.S. App. LEXIS 16799, 1989 WL 131688, Counsel Stack Legal Research, https://law.counselstack.com/opinion/riegel-power-corporation-mount-vernon-mills-inc-v-voith-hydro-crowder-ca4-1989.