Envirotech Corp. v. Halco Engineering, Inc.

364 S.E.2d 215, 234 Va. 583, 6 U.C.C. Rep. Serv. 2d (West) 1494, 4 Va. Law Rep. 1545, 1988 Va. LEXIS 6
CourtSupreme Court of Virginia
DecidedJanuary 15, 1988
DocketRecord No. 841342, Record No. 841325
StatusPublished
Cited by25 cases

This text of 364 S.E.2d 215 (Envirotech Corp. v. Halco Engineering, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Envirotech Corp. v. Halco Engineering, Inc., 364 S.E.2d 215, 234 Va. 583, 6 U.C.C. Rep. Serv. 2d (West) 1494, 4 Va. Law Rep. 1545, 1988 Va. LEXIS 6 (Va. 1988).

Opinion

COMPTON, J.,

delivered the opinion of the Court.

In this controversy arising under the Uniform Commercial Code — Sales (UCC), Code § 8.2-101 et seq., the dispositive question on appeal deals with the validity and enforceability of contractual provisions that limit the buyer’s remedy for recovery of consequential damages.

In 1978, Arlington County contracted for a multimillion dollar expansion of the County’s sewage treatment facilities. Specifically, the County proceeded to construct a Water Pollution Control Plant including a Biological Sludge Processing Building. The new facility would receive raw sewage, treat it with chemicals, and remove solids from the water by pressurized filtration. This process produces cakes of dried sludge which are shredded and burned in an incinerator in the building. The heat produced by the incinerator is recovered and converted into supplementary electrical power for the facility.

In 1978, the general contractor, John W. Cowper Company, awarded a subcontract to Halco Engineering, Inc., the plaintiff below, to perform the mechanical work connected with the construction of the facility. Under that agreement, Halco, an experienced contractor, generally was responsible for procurement, *586 erection, and installation of equipment and associated piping for the plant.

Later in 1978, Halco awarded a subcontract to Envirotech Corporation, the defendant below. Envirotech was a manufacturer of sophisticated filtration equipment with considerable experience in the waste treatment industry. Under that agreement, the major pieces of equipment to be supplied by defendant were four filter presses, to compress and remove the water from raw sewage; four cake hoppers into which compressed sewage cakes were dropped; four cake breakers to grind the cakes into smaller particles; and four drive conveyers to carry the pulverized material for incineration. Other equipment supplied by Envirotech included blenders to mix the sludge with treating chemicals at the beginning of the process, plus conditioning tanks and chemical storage tanks. Most of the foregoing components were the source of the dispute between the parties. Although Envirotech had no responsibility for installation of the equipment, it had a duty to assist in “start-up” of the equipment and to train operators of the units.

The agreement between the parties, in which defendant was to be paid $850,000, was embodied in a series of letters with enclosures and a purchase order dated July 12, 1978. The following terms and conditions of the parties’ agreement generated this controversy. Under the heading “Shipments and Delivery,” the agreement provided

“Seller shall have no liability to Purchaser for damages or penalties, direct or indirect, for any delay in shipment or delivery, whether such delay is minor or substantial, nor shall Purchaser have the right to declare a breach of contract because of any such delay.”

Under the heading “Limitation of Liability,” the contract provided

“Seller shall not be liable to Purchaser for any incidental or consequential damages for any reason whatsoever, including, but without limitation, damages in the character of (a) loss of profits or revenues resulting from the failure of the equipment to meet specifications or warranties, (b) damages suffered by Purchaser as a result of loss of production facilities or equipment, (c) cost of replacement equipment, (d) damages suffered by customers of Purchaser, or (e) any fines or *587 penalties assessed for failure to comply with any law or governmental regulations.”

The completion date of the prime contract was originally fixed as November 10, 1980. The project was not completed on time and, by agreement between the owner and the general contractor, the date of completion was extended to December 31, 1982. Halco commenced work in May of 1978 and at the time of trial in January-February 1984 had not finished work under its contract with the general contractor.

In May 1982, Halco filed the present action against Envirotech seeking recovery in damages for $450,000, later amended to $843,081. Halco alleged that defendant failed to perform its contract in a timely manner. The plaintiff alleged that, under the contract, defendant was obligated to deliver all equipment and perform all services by January 1979, in accordance with the plans and specifications for the project. The plaintiff alleged that defendant’s delays were so material and so unreasonable under the agreement as to vitiate it. Halco further alleged that as the result of the delays and the defendant’s failure to perform, the plaintiff had been delayed materially in the performance of its contract with Cowper. In consequence, the plaintiff alleged certain additional costs were incurred.

Halco claimed damages consisting of costs for office overhead, field supervision, tools and equipment, labor, and financing which the plaintiff asserted it incurred because it had to remain on the job site past November 10, 1980. Although the plaintiff has maintained at times during this litigation that the damages claimed were direct and not consequential, counsel for Halco confirmed during oral argument that the damages sought by the plaintiff “may be fairly characterized as consequential under the UCC.” See Code § 8.2-715(2).

Envirotech responded to the plaintiff’s allegations by denying it was obligated in any amount. In addition, the defendant filed a counterclaim seeking judgment against the plaintiff for the sum of $96,314, allegedly due for equipment delivered pursuant to the agreement with Halco.

In a seven-day jury trial, the plaintiff obtained a verdict against the defendant for $428,554. The jury denied recovery on the counterclaim. Subsequently, the trial court overruled Envirotech’s motion to set aside the verdict on the main claim and entered judg *588 ment on the verdict in favor of Halco. But the trial court granted Envirotech’s motion to set aside as to the counterclaim and entered judgment in favor of the defendant against the plaintiff for $96,314. We awarded the parties separate appeals and consolidated them for oral argument.

A detailed recitation of the extensive evidence is not necessary in order to set the background for discussion of the central issue in this dispute. In essence, the plaintiff claimed that defendant represented itself as capable of supplying highly specialized sludge filtration equipment in accordance with the specifications fixed for the project by the consulting engineer. In spite of this representation, Halco contended, Envirotech failed to meet a fixed schedule for delivery of the equipment. Halco presented evidence that defendant had not completed its contractual obligations by delivering equipment by early 1979, or by November 1980, which was Halco’s completion date under its contract with Cowper, or by December 15, 1982, the date through which Halco claimed money damages from Envirotech.

In addition, the evidence showed that the plant was designed to be an integrated, closed-loop system in which each piece of equipment had to fit, had to be compatible with other components, and had to perform in accordance with design specifications.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McAuley v. FCA US LLC
E.D. Virginia, 2023
Elizabeth River Crossings v. Meeks
Supreme Court of Virginia, 2013
Columbia Realty Venture, L.L.C. v. Dang
83 Va. Cir. 258 (Fairfax County Circuit Court, 2011)
FRANSMART, LLC v. Freshii Development, LLC
768 F. Supp. 2d 851 (E.D. Virginia, 2011)
Hammond-Mitchell, Inc. v. Construction Materials Co.
77 Va. Cir. 5 (Alleghany County Circuit Court, 2008)
Gay v. CreditInform
Third Circuit, 2007
Howie v. Atlantic Home Inspection, Inc.
62 Va. Cir. 164 (Norfolk County Circuit Court, 2003)
Parker-Smith v. Sto Corp.
551 S.E.2d 615 (Supreme Court of Virginia, 2001)
Clark v. Orkin Exterminating Co.
147 F. Supp. 2d 458 (W.D. Virginia, 2001)
Pierce v. Catalina Yachts, Inc.
2 P.3d 618 (Alaska Supreme Court, 2000)
Parker-Smith v. STO Corp.
52 Va. Cir. 577 (Fairfax County Circuit Court, 1999)
E. J. Miller Construction Co. v. Holt
56 Va. Cir. 153 (Roanoke County Circuit Court, 1998)
International Financial Services, Inc. v. Franz
534 N.W.2d 261 (Supreme Court of Minnesota, 1995)
Reibold v. Simon Aerials, Inc.
859 F. Supp. 193 (E.D. Virginia, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
364 S.E.2d 215, 234 Va. 583, 6 U.C.C. Rep. Serv. 2d (West) 1494, 4 Va. Law Rep. 1545, 1988 Va. LEXIS 6, Counsel Stack Legal Research, https://law.counselstack.com/opinion/envirotech-corp-v-halco-engineering-inc-va-1988.